Professional Liability Alert: Joint Client Can't Claim Privilege For Communications With Attorney Sued By Another Joint Client
February 05, 2015 —
David W. Evans and Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Anten v. Superior Court (No. B258437 – Filed 1/30/2015), the Second Appellate District held that when joint clients do not sue each other, but one of them sues their former attorney, the nonsuing client cannot prevent the parties to the malpractice suit from discovering or introducing otherwise privileged attorney-client communications made in the course of the joint representation.
Under California Evidence Code §958, in lawsuits between an attorney and a client based on an alleged breach of a duty arising from their attorney-client relationship, communications relevant to the alleged breach are not protected by the attorney-client privilege. Similarly, Evidence Code §962 provides that if multiple clients retain or consult with an attorney on a matter of common interest and the joint clients later sue each other, then the communications between either client and the attorney made in the course of that relationship are not privileged in the suit between the clients.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com; Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
London Shard Developer Wins Approval for Tower Nearby
November 05, 2014 —
Neil Callanan - BloombergSellar Property Group, developer of the Shard in London, won local government approval to build a 26-story residential tower close to the skyscraper on the south bank of the River Thames.
The council for the Southwark borough voted in favor of the 148-apartment project, which also includes a 16-story tower, at a meeting yesterday, Sellar spokesman Baron Phillips said by e-mail. The project, like the Shard, will be developed in a partnership with the state of Qatar.
Developers plan to construct more than 25,000 luxury properties in London worth more than 60 billion pounds ($96 billion) over the next decade, EC Harris said in an Oct. 7 report. The homes approved yesterday at the Fielden House site are expected to sell for about 800,000 pounds each, according to a filing by the borough.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, BloombergMr. Callanan may be contacted at
ncallanan@bloomberg.net
South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Why Do Construction Companies Fail?
February 14, 2023 —
The Hartford Staff - The Hartford InsightsIf a construction company takes on a lot of work, it’s a good thing, right? Not exactly. In fact, overextension is one of the primary reasons why contractors fail. And it’s something that contractors should consider as a priority for their risk management plan.
Of the 43,277 construction businesses that started in March 2011, only 37.6% of companies survived 10 years later.
1
“The construction industry has a high rate of failure,” explains Tim Holicky, senior executive underwriter in The Hartford’s construction central bond team. “And more often than not, it’s because of too much work, rather than too little of it. The key to a contractor’s long-term survival is knowing when to say no.”
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Colorado HB 13-1090: Concerning Payment of Amounts Due Under a Construction Agreement
February 21, 2013 —
David M. McLain — Higgins, Hopkins, McLain & Roswell, LLCOn January 17, 2013 Representative Fischer introduced House Bill 13-1090 into the Colorado House of Representatives. HB 1090 was assigned the House Business, Labor, Economic and Workforce Development Committee.
The bill, sponsored by Senator Tochtrop in the Senate, sets the following requirements for both private and public construction contracts:
The owner and contractor must make regular progress payments approximately every 30 days to contractors and subcontractors for work actually performed.
To receive the progress payments, the contractor and subcontractor must submit a progress payment invoice plus any required documents.
A contractor must pass on the progress payment to the subcontractor within 5 days or by the end of the billing cycle.
Interest accrues on unpaid progress payments.
A contract may extend a billing cycle to 60 days, but the contract must duly warn of this.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainmclain@hhmrlaw.com
Land Planners Not Held to Professional Standard of Care
October 10, 2013 —
Heather Anderson — Higgins, Hopkins, McLain & Roswell, LLC.Recently, the Colorado Court of Appeals indicated that there is no professional duty of care applicable to land planners. See Stan Clauson Associates, Inc. v. Coleman Brothers Constr., LLC, 297 P.3d 1042 (Colo. App. 2013). Stan Clauson Associates, Inc. (“SCA”) agreed to provide land planning services to Coleman Brothers Construction, LLC (“Coleman”) for property referred to as Crown Mountain in a letter and then verbally agreed to provide a development analysis for another property, located on Emma Road in Basalt, Colorado. Thereafter, SCA sent letters to the defendant concerning the possible subdivision and development of the Emma Road property.
Approximately two years later, SCA sued Coleman for breach of the verbal agreement concerning the Emma Road property. Coleman then asserted counterclaims against SCA for negligently providing inaccurate advice about whether the Emma Road property could be subdivided and developed, and that the county had denied the planned unit development sketch plan SCA prepared and submitted on behalf of Coleman. The district court granted SCA’s motion for summary judgment thereby concluding that the economic loss rule barred Coleman’s negligence counterclaims. The Court of Appeals agreed.
In its opinion, the Court of Appeals reiterated the economic loss rule espoused in the Colorado Supreme Court in the Town of Alma v. AZCO Constr., Inc., 10 P.3d 1256, 1264 (Colo. 2000) case. “Under the economic loss rule, ‘a party suffering only economic loss from the breach of an express or implied contractual duty may not assert a tort claim for such a breach absent an independent duty of care under tort law.’”
Read the court decisionRead the full story...Reprinted courtesy of
Heather AndersonHeather Anderson can be contacted at
anderson@hhmrlaw.com
Fed Inflation Goal Is Elusive as U.S. Rents Stabilize: Economy
March 12, 2014 —
Michelle Jamrisko and Ilan Kolet - BloombergFederal Reserve efforts to nurture a more robust rate of inflation this year are likely to fall short. The reason: the biggest gains in rents are probably over.
The costs to lease residential real estate, the second-biggest component of the price measure tracked by U.S. central bankers, helped put a floor under inflation over the past two years as most other components decelerated. Now, with builders cranking out a record number of multifamily buildings and the job market still far from tight, the outlook for rents is the bleakest it’s been in four years.
“Because the economy is still not in the strongest position and certainly the labor market is not in the strongest position, landlords really can’t extract much more in the way of rent growth,” said Ryan Severino, a senior economist at real-estate data provider Reis Inc. in New York. Also, rents are already high, which makes more increases difficult, he said.
Ms. Jamrisko may be contacted at mjamrisko@bloomberg.net; Mr. Kolet may be contacted at ikolet@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko and Ilan Kolet, Bloomberg
Clean Water Act Cases: Of Irrigation and Navigability
January 06, 2020 —
Anthony B. Cavender - Gravel2GavelThe federal courts have recently decided two significant Clean Water Act (CWA) cases: State of Georgia, et al. v. Wheeler, where the US District Court for the Southern District of Georgia held that the 2015 rulemaking proceeding of EPA and the U.S. Army Corps of Engineers redefining the term “Waters of the United States” in the CWA violated the Act as well as the Administrative Procedure Act; and the Ninth Circuit’s decision in Pacific Coast Federation of Fishermen’s Associations, et al. v. Glaser, where the appeals court ruled that the lower court erroneously interpreted a CWA NPDES permitting exception involving agricultural return flows.
An Absence of Navigability: State of Georgia, et al. v. Wheeler
Decided on August 21, 2019, the district court, one of the few courts to grapple with the rule’s compliance with the CWA and the Administrative Procedure Act (APA), held that the agencies’ redefinition of the terms “Interstate Waters,” “Tributaries” and “Adjacent Waters” violated the CWA by reading “navigability” out of the new definitions, or by failing to adhere to the Supreme Court’s rulings in the 2005 case of Rapanos v. United States, in particular Justice Kennedy’s concurrence regarding the application of the “significant nexus” in case-by-case adjudications as to whether a particular body of water was covered by the Act. Moreover, some provisions of the rule conflicted with the APA because they were not a logical outgrowth of the rules proposed by the agencies in 2014, and on which they solicited comments, and other determinations were not supported by a reasonable explanation. In addition, without a clear statement from Congress that it supported the rule’s effect of increasing the nature and extent of enhanced federal jurisdiction over waters subject to the CWA, the court was loathe to approve the rule. Accordingly, the rule was remanded to the agencies for additional review consistent with this decision.
This decision is of particular importance as it may well be the first case to subject this new EPA rule—the linchpin of much of EPA’s regulation under the CWA—to extended review. (Other courts have only been asked to enjoin the rule, which involves a different type of review.)
Read the court decisionRead the full story...Reprinted courtesy of