CA Supreme Court Finds “Consent-to-Assignment” Clauses Unenforceable After Loss Occurs During the Policy Period
August 26, 2015 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Fluor Corporation v. Superior Court (No. S205889; filed 8/20/15), the California Supreme Court overruled its earlier decision in Henkel Corp. v. Hartford Accident & Indemnity Co. (2003) 29 Cal.4th 934, holding that notwithstanding the presence of a consent-to-assignment clause in a liability policy, Insurance Code section 520 bars an insurer from refusing to honor the insured’s assignment of coverage after a loss has taken place during the policy period.
In Henkel, the Supreme Court limited the ability of corporate successors to obtain coverage under predecessors’ policies on a contract theory. The Henkel Court held that where a successor corporation contractually assumed liabilities of the predecessor corporation, the insurance benefits would not automatically follow. The Henkel Court ruled that if the predecessor company’s policy contains a consent-to-assignment clause, any assignment of insurance policy benefits to a successor corporation required the insurer’s consent. The Court said that policy benefits are not transferable choses in action unless at the time of corporate transfer they could be reduced to a monetary sum certain. The Court reasoned that historic product or environmental liabilities might not even be known to the predecessor at that time, much less reduced to a sum certain, so coverage for such risks could not be considered a transferable chose in action. Thus, where the liability was inchoate at the time of the corporate transaction, the Henkel Court said that coverage would not necessarily follow because the insurer’s duties had not yet attached.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Subsequent Owners of Homes Again Have Right to Sue Builders for Construction Defects
October 07, 2016 —
Mark L. Parisi – White and Williams LLPOwners of homes with damage from construction defects have long had the standing to sue the builders of their homes using the legal theories of 1) breach of contract, 2) breach of implied warranty, and 3) breach of Pennsylvania’s consumer fraud statute, the Unfair Trade Practices and Consumer Protection Law (UTPCPL).
Before the 2014 decision of the Pennsylvania Supreme Court in Conway v. Cutler, even owners who were not the original purchasers of their homes, so-called subsequent owners, had a right to sue the builder of their homes using implied warranty as the legal theory. But the Supreme Court in Conway said in 2014 that even though an implied warranty theory is not based on a written contract, it is a quasi contract theory and because subsequent owners never had a contractual relationship with the builder of their home, the implied warranty cause of action was not available. Subsequent purchasers were thus left without a remedy for damage from defective construction in their homes and builders had a second safe harbor from claims regarding homes they built. The first safe harbor is Pennsylvania’s Statute of Repose. If the home was completed more than 12 years before a lawsuit was filed, the Statute of Repose bars the claim. But after Conway, if the home was sold, this also cut off a builder’s potential liability for construction defects in the home.
ENTER THE UTPCPL
On July 26, 2016 the Pennsylvania Superior Court in the case of Adams v. Hellings Builders issued a non-published (and therefore non-precedential) decision in a stucco construction defect case that held that subsequent purchasers could sue their home’s builder under the UTPCPL because the Act had no requirement that the purchaser of a product, or home, be the original purchaser. The decision cites several other appellate cases not involving construction defect claims that held that the UTPCPL was a valid legal theory for claims regarding products purchased second hand by the plaintiffs in those other cases. The court in Adams held that there was no reason that a suit regarding construction defects in a home should be treated any differently.
Read the court decisionRead the full story...Reprinted courtesy of
Mark L. Parisi, White and Williams LLPMr. Parisi may be contacted at
parisim@whiteandwilliams.com
Saving Manhattan: Agencies, Consultants, Contractors Join Fight to Keep New York City Above Water
November 27, 2023 —
Pam McFarland & Corinne Grinapol - Engineering News-RecordIn densely populated cities surrounded on all sides by water—the borough of Manhattan in New York City as a prime example—the risks from sea level rise and climate change are not just hypotheticals; they are existential threats.
Reprinted courtesy of
Pam McFarland, Engineering News-Record and
Corinne Grinapol, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
#2 CDJ Topic: Valley Crest Landscape v. Mission Pools
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFIn July of this year,
Christopher Kendrick and
Valerie A. Moore of
Haight Brown & Bonesteel LLP analyzed the results of the Valley Crest Landscape v. Mission Pools case, in which “a California appeals court held that equities favor an insurer seeking equitable subrogation over a subcontractor that agreed to defend and indemnify claims arising out of its performance of work under the subcontract.”
Read the full story...
In the article, “General Liability Insurer Entitled to Subrogate Against its Insured’s Indemnitor,”
Matthew S. Foy and
Michael A. Pursell of
Gordon & Rees LLP also discussed the details of the Valley Crest v. Mission Pools case that involved installing a swimming pool on a St. Regis hotel property: “In Valley Crest Landscape Development, Inc. v. Mission Pools of Escondido, Inc., the California Court of Appeal for the Fourth Appellate District held that an insurer was entitled to equitably subrogate a breach of express indemnity claim against its insured’s indemnitor.”
Read the full story...
This month,
Graham C. Mills of
Newmeyer & Dillion reported on the decision by the Court of Appeals regarding the Valley Crest case, which “reinforces the right of a general contractor to defense and indemnity by a subcontractor when the parties have contractually allocated risk to the subcontractor. To ensure compliance with that right, the Valley Crest court imposed a strong penalty against a subcontractor that defaulted on its obligation.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Connecticutt Class Action on Collapse Claims Faces Motion to Dismiss
January 02, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court dismissed some insurers from a class action suit alleging failure to provide coverage for collapse claims. Halloran v. Harleysville Preferred Ins. Co., 2018 U.S. Dist. LEXIS 179807 (D. Conn. Oct. 19, 2018).
A class of homeowners brought suit in 2016 against their homeowners insurance companies ("defendants") for failure to cover collapse claims. Plaintiffs alleged they bought their homes between 1984 and 2015. Each of the homes had basement walls that were "crumbling and cracking due to the oxidation of certain minerals contained in the concrete." As a result of the deteriorating concrete, plaintiffs claimed that their basement walls were in a state of collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
You May Be Able to Dodge a Bullet, But Not a Gatling Gun
November 16, 2020 —
Garret Murai - California Construction Law BlogIn the days before cable, and long before Netflix, I watched my fair share of spaghetti westerns on lazy weekend afternoons. Bullets zinging past cowboys, knocking off hats, and ricocheting off rocks. But while you might get lucky and dodge a bullet, not so with a Gatling gun.*
In the next case, C. W. Johnson & Sons, Inc. v. Carpenter, Case No. B300187 (August 7, 2020), a contractor who was unlicensed during a portion of a project dodged a bullet. However, I’m not so sure that he’s going to be able to dodge the hail of bullets that are coming after.
The C. W. Johnson & Sons Case
As cases go, the C. W. Johnson & Sons case is pretty straightforward. In March 2016, Contractor C. W. Johnson & Sons, a family owned flooring company, was contracted to install flooring at Randall Carpenter’s house for a total contract price of $68,343. Work was performed between March and September 2016 including some warranty, repair and corrective work after September 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
This Is the Most Remote and Magical Hotel on Earth
May 12, 2016 —
Sarah Hepola – BloombergThere are no signs leading to the Fogo Island Inn. That’s how hard it is to miss the place. Designed by architect Todd Saunders, who grew up in nearby Gander, the building takes its inspiration from the fishing shacks that dot the shoreline, sagging on old wooden stilts, but it was also made with the dimensions of a cruising vessel. Three hundred feet long by 30 feet wide. Like a ship that’s just sailed into harbor.
For decades, the flow of traffic in this community off the Newfoundland coast had moved in one direction: away. Fewer than 2,500 people live on an island four times the size of Manhattan. But the inn, the brainchild of Fogo Island native and tech millionaire Zita Cobb, reversed that trend when it was completed in 2013. Strangers now come from around the world to see the island, whose unspoiled landscape makes it a coveted spot for the under-the-radar traveler.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Hepola, Bloomberg