LAX Construction Defect Suit May Run into Statute of Limitations
December 30, 2013 —
CDJ STAFFCurrent arguments over the claims made by LAX that Runway 25L was built in a defective manner by Tutor-Saliba/O&G Industries are hinging over whether the airport knew the runway was defective less than four years after the construction was completed. The runway was built almost five years ago, and Tutor-Saliba is claiming that Los Angeles World Airports has delayed too long in making a construction defect complaint. Tutor-Saliba is not conceding that the runway is defective, only that if it were, the airport would have known it earlier.
Los Angeles World Airports, which operates LAX, is not commenting on the matter, but Robert Span, an aviation attorney at Steinbrecher & Span, told the Daily Breeze that while “there is a four year statute of limitations for dealing with construction defects, but that’s for what they called patent defects,” and that “there’s a 10-year statute of limitations for construction projects where the defect that is alleged is called latent — something that would not be readily apparent.”
Tim Pierce, a construction attorney at K&L Gates LLP described it as “a common defense,” though he said it is “raised in most cases and only works in some.”
Read the court decisionRead the full story...Reprinted courtesy of
Attorney Risks Disqualification If After Receiving Presumptively Privileged Communication Fails to Notify Privilege Holder and Uses Document Pending Privilege Determination by Court
May 03, 2017 —
David W. Evans & Stephen J. Squillario - Haight Brown & Bonesteel LLPIn McDermott Will & Emery LLP v. Superior Court (4/18/2017 – No. G053623), the Fourth Appellate District, in a 2-1 decision, considered two distinct issues: 1. Whether the attorney-client privilege for a confidential e-mail communication between a client and his attorney had been waived by the client’s inadvertent disclosure of the communication to a third party; and 2. Whether the opposing counsel’s failure to respect the claimed privilege as to the inadvertently produced document or to follow the rules for handling such documents set forth in State Compensation Ins. Fund v WPS, Inc. (1999) 70 Cal.App.4th 644 (State Fund) supported the trial court’s disqualification of counsel and his law firm.
This case arose from an intra-family dispute over the deceased matriarch’s substantial investment holdings, a related probate matter, and two subsequent legal malpractice actions. The opinion sets forth in great detail the facts surrounding the claimed inadvertent disclosure by the client (i.e., the privilege holder) of the subject attorney-client e-mail communication, its subsequent dissemination to, and use by, the client’s family members, the ultimate receipt and review by an opposing family member’s counsel, the efforts by the client’s counsel to assert the privilege and “claw-back” the document, and in the face of this privilege claim, the opposing counsel’s extensive use of the document during discovery, including depositions, in the legal malpractice actions. The opposing counsel, who had received the subject document from his own client, had independently concluded that the clearly privileged document lost its privileged status, believing that the privilege had been waived either because of disclosure to third parties or that his obligation to return inadvertently disclosed documents only applied to those produced in litigation during discovery. As a result, the opposing counsel refused all demands for the return or destruction of the document and insisted upon continuing to use it. This dispute finally came to a head over two years after the client’s disclosure in the context of the client’s motion for a judicial determination that the document was privileged (which the trial court granted) and then a motion to disqualify the opposing counsel (which the trial court also granted); both decisions were eventually reviewed by the appellate court.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
NLRB Hits Unions with One-Two Punch the Week Before Labor Day
November 18, 2019 —
John Baker & Robert Pettigrew - White and Williams LLPThe National Labor Relations Board (the Board) continues to modify the way employers, unions and employees view and relate to each other in the workplace. In two decisions right before Labor Day, the Board strengthened employer rights in their workplaces, while at the same time making life for their union counterparts more difficult.
On August 23, 2019, the Board revisited the issue of whether an employer must grant access to the off-duty employees of an onsite contractor so they can engage in Section 7 activities on the employer’s property. In general, Section 7 activities consist of employees acting together to improve their pay and working conditions, which constitute fundamental rights under the National Labor Relations Act (the Act). In Bexar County Performing Arts Center Foundation d/b/a Tobin Center, the San Antonio-based performing arts center, the Tobin Center, owned the Center as well as grounds that abutted the famed San Antonio River Walk. The Tobin Center housed three resident companies, one of which was the Ballet San Antonio with whom it had a licensor-licensee agreement.
In addition to plays, movies and other productions, the Tobin Center hosted the San Antonio Symphony (the Symphony) to perform for 22 weeks of the year. The Ballet San Antonio also occasionally utilized the Symphony for live musical performances at its ballets. When, however, the Ballet San Antonio decided to use recorded music for a particular production, off-duty employees of the Symphony protested by leafletting the public on the Tobin Center property. The leaflets advised the public of this decision and urged that they “DEMAND LIVE MUSIC!” Their protests were not directed at the property owner, who denied them access to its property.
Reprinted courtesy of
John Baker, White and Williams LLP and
Robert Pettigrew, White and Williams LLP
Mr. Baker may be contacted at bakerj@whiteandwilliams.com
Mr. Pettigrew may be contacted at pettigrewr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado’s New Construction Defect Law Takes Effect in September: What You Need to Know
September 07, 2017 —
Jesse Witt - The Witt Law FirmColorado’s new construction defect law officially takes effect this month. Although HB 17-1279 was passed in May, the statutory text provides that it only applies “with respect to events and circumstances occurring on or after September 1, 2017.” With that date now upon us, practitioners should be mindful of the law’s new requirements.
The law applies to any lawsuit wherein a homeowner association files a construction defect action on behalf of two or more of its members. “Construction defect action” is defined broadly to include any claims against construction professionals relating to deficiencies in design or construction of real property. Before an association may commence such an action, its board must follow several steps.
First, the board must deliver notice of the potential construction defect action to all homeowners and the affected construction professionals at their last known addresses. This requirement does not apply to construction professionals identified after the notice has been mailed, or to construction professionals joined in a previously-approved lawsuit. The notice must include a description of the alleged construction defects with reasonable specificity, the relief sought, a good-faith estimate of the benefits and risks involved, and a list of mandatory disclosures concerning assessments, attorney fees, and the marketability of units affected by construction defects. The notice must also call a meeting of all homeowners. The notice should be sent to the construction professionals at least five days before the homeowners.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Resilience: Transforming the Energy Sector – Navigating Land Issues in Solar and Storage Projects | Episode 3 (11.14.24)
December 17, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn the latest
episode of the Resilience podcast, colleague
Shellka Arora-Cox and Laura Pagliarulo, CEO and founder of SolaREIT, get down to the nitty-gritty in a discussion of the interplay of solar power capacity, generation and land use.
(Editor’s note: The following transcript has been edited for clarity.)
Welcome to Resilience, the vodcast where we talk about the most pressing challenges and the biggest opportunities in the energy sector. I’m your host, Shellka Arora-Cox, a partner at Pillsbury Winthrop Shaw Pittman. I’m thrilled to have Laura Pagliarulo, the CEO and founder of SolaREIT, with me today.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Montana Federal District Court Finds for Insurer in Pollution Coverage Dispute
October 24, 2021 —
Melanie A. McDonald - Saxe Doernberger & VitaApplying Louisiana law, a recent federal court decision exemplifies why policyholders should thoroughly read claims-made policies to understand when notice is due to insurers and truthfully complete policy applications. In Admiral Insurance Company v. Dual Trucking, Inc.,1 the Court determined the insurer, Admiral Insurance Company (“AIC”), owed no duty to defend or indemnify Dual Trucking and Transport, LLC (“DTT”), Dual Trucking of Montana, LLC (“DTM”), and Dual Trucking, Inc. (“DTI”) (collectively, the “Dual Entities”) under two Environmental Impairment Liability Policies (“EIL Policies”) and four Contractor Pollution Liability Policies (“CPL Policies”). The Court justified its decision because the Dual Entities: 1) did not give notice during the 2012-2013 EIL Policy period; 2) had discovered or knew of, but did not disclose, potential pollution conditions before the inception of the 2013-2014 EIL Policy and before the expiration of the extended reporting period of the 2012-2013 EIL Policy; 3) failed to provide AIC with notice during the extended reporting period of the 2013-2014 EIL Policy of claims for which the Dual Entities were seeking coverage; and 4) materially misrepresented known facts on the CPL Policy applications.
I. Factual Background.
The Dual Entities were Louisiana-based companies that provided oilfield equipment rental services. In 2011, the Dual Entities leased land in Montana under three leases, collectively referred to as “the Bainville site.” Shortly afterward, the Dual Entities applied for, and AIC issued, an EIL Policy and two CPL Policies with a policy period of October 1, 2012, to October 1, 2013. AIC renewed all three policies for the October 1, 2013, to October 1, 2014, policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Melanie A. McDonald, Saxe Doernberger & VitaMs. McDonald may be contacted at
MMcDonald@sdvlaw.com
Buyer's Demolishing of Insured's Home Not Barred by Faulty Construction Exclusion
June 21, 2017 —
Tred R. Eyerly - Insurance Law HawaiiLoss of the insured's home caused by a renter who demolished the home was covered under the homeowner's policy. Fisher v. Garrison Prop. & Cas. Ins. Co., 2017 Idaho LEXIS 143 (Idaho May 26, 2017).
The insured, Shammie L. Fisher, entered a Purchase Agreement to sell her home to Ron Reynoso. The purchase of the property was contingent upon Reynoso obtaining financing. Before completing the purchase, he would lease the property. The Agreement stated, "Buyer intends to make certain improvements to the property upon possession, with the intent to sell the property for a profit."
Within two months of renting the property to Reynoso, Fisher learned that he had demolished the entire house down to the foundation. He then ceased work and left. Fisher made a claim under her policy, but Garrison Property and Casualty Insurance Company denied coverage based upon the exclusion for faulty, inadequate or defective work. When Fisher sued, the trial court granted summary judgment to Garrison.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
60-Mile-Long Drone Inspection Flight Points to the Future
January 15, 2019 —
Tom Sawyer - Engineering News-RecordBlack & Veatch announced in December the successful conclusion of a 60-mile-log, non-stop, proof-of-concept drone-based inspection flight conducted by a remote pilot in a command center miles away in rural Illinois.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Sawyer, ENRMr. Sawyer may be contacted at
sawyert@enr.com