LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 06, 2011 —
Douglas Reiser, Builders Council BlogApparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Former Mayor Arrested for Violating Stop Work Order
October 30, 2013 —
CDJ STAFFThe former mayor of Springfield, Florida has been arrested on charges of insurance fraud. More than a year ago, an investigator for the Bureau of Workers’ Compensation found that an employee of Walker’s construction company was working without workers’ compensation and issued a stop work order. Walker’s employees continued work.
The charges were delayed because Walker challenged the stop work order. Once it was determined that the stop work order was issued properly, Walker was charged with a third-degree felony.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Reform Bill Passes Colorado Senate
April 15, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Denver Business Journal reported that a construction defect reform bill has “passed the Colorado Senate by a 24-11 vote Tuesday, with six Democrats joining all 18 Republicans in the chamber in backing the measure.”
The bill now moves to the House. According to the Denver Business Journal, the bill “faces a tougher path in the House, where Speaker Dickey Lee Hullinghorst, D-Gunbarrel, has said she was not going to support a bill that does not include a provision giving aggrieved condominium owners the right to take their disputes with builders to court. No such amendment was added in the Senate.”
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations Devin Brunson on His Promotion to Partner!
April 26, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is very proud to announce Devin Brunson has been promoted to the position of partner with the firm!
Mr. Brunson came to BWB&O from another civil litigation firm and helped start the Denver, Colorado office along with partners Lucian Greco, John Toohey and Peter Brown. He has taken on a significant leadership role within the firm over the past several years and has been integral in growing the office to its current footprint.
He is licensed to practice law in Colorado, District of Colorado, and in the U.S. District Court. His practice is focused in the areas of civil and business litigation, construction litigation, and employment law. Mr. Brunson has a diverse practice background that includes complex civil litigation and intellectual property disputes and has had the privilege of representing business owners, contractors, corporate executives, and professional athletes during the course of his career.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
D&O Insurer Must Cover Mortgage Broker’s $15 Million Settlement of Alleged False Claims Act Violations
November 15, 2022 —
Michael S. Levine, Geoffrey B. Fehling & Matthew J. Revis - Hunton Insurance Recovery BlogA Delaware court recently
granted summary judgment to a mortgage broker targeted in a federal government investigation for alleged False Claims Act violations, holding that the company’s directors and officers liability (“D&O”) insurer was required to indemnify more than $15 million in settlement costs with the U.S. Department of Justice. Guaranteed Rate, Inc. v. ACE American Insurance Company, No. N20C-04-268 MMJ CCLD (Del. Super. Ct. Sept. 6, 2022). We
previously reported on the policyholder’s earlier victory in this case, in which the court held that a Civil Investigative Demand (“CID”) from federal authorities triggered the insurer’s obligation to pay defense costs under the D&O policy.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Matthew J. Revis, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Revis may be contacted at mrevis@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Delaware Supreme Court Won’t Halt Building
June 28, 2013 —
CDJ STAFFThe Delaware Supreme Court has rejected arguments made by Dewey Beach homeowners over the construction of a new building. The Supreme Court agreed with the Chancery Court which had dismissed the complaint as it was filed more than 60 days after exception to the zoning rules had been voted on. A builder had been granted leave to build higher than thirty-five feet in exchange for public space, public restrooms, and other amenities for the public.
Read the court decisionRead the full story...Reprinted courtesy of
CA Supreme Court Permits Insurers to Bring Direct Actions Seeking Reimbursement of Excessive Fees Against Cumis Counsel Under Limited Circumstances
August 19, 2015 —
David W. Evans & Valerie A. Moore – Haight Brown & Bonesteel LLPThe California Supreme Court held in Hartford Casualty Insurance Company v. J.R. Marketing, L.L.C. (Squire Sanders) (8/10/2015 - #S211645) that if Cumis counsel, operating under a court order which such counsel drafted and which expressly provided that the insurer would be able to recover excessive fees, sought and received fee payments from the insurer that were fraudulent or otherwise manifestly and objectively useless and wasteful when incurred, Cumis counsel have been unjustly enriched at the insurer’s expense and the insurer will be permitted under such limited circumstances to seek reimbursement directly from Cumis counsel.
Certain Hartford insureds who had been issued commercial general liability policies were sued in multiple proceedings for a variety of claims, including unfair competition, defamation and intentional misrepresentation. Hartford disclaimed a duty to defend or to indemnify the defendants on the grounds that the acts complained of occurred prior to Hartford’s policy, and that some of the defendants were not Hartford insureds. A coverage action was filed by some of the insureds against Hartford; they were represented by the Squire Sanders law firm. Although Hartford subsequently agreed to defend several of the defendants subject to a reservation of rights, it declined to pay defense expenses incurred prior to the date of such agreement. Some months later, the trial court entered a summary adjudication order, finding that Hartford had a duty to have defended the liability action on the date it was originally tendered; the order required Hartford to fund the insured’s defense with independent counsel (i.e., so-called “Cumis” counsel; see San Diego Federal Credit Union v. Cumis Insurance Society, Inc. (1984) 162 Cal.App.3d 358). The insureds retained Squire Sanders as their Cumis counsel.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of