Read Before You Sign: Claim Waivers in Project Documents
July 06, 2020 —
William E. Underwood - ConsensusDocsNot all claim waivers are appropriately titled “Waiver of Claims.” In fact, claim waivers can be found “hiding” without any advertisement or fanfare in a number of project documents, including change orders and applications for payment. So although getting work quickly approved and paid for is important, taking time to read the specific language in your project documents is just as important. Failure to pay close attention to this language could result in the waiver of key, unresolved project claims.
Further, and although it should go without saying, it is also just as important to read all of the terms of your contract. Important waiver language might not exist on the face of form project documents, but rather might be contained in the general and/or supplemental conditions of your contract and automatically incorporated into your form project documents. And these types of incorporated waivers can be just as enforceable.
So it is critically important to understand what you are signing and the implications it might have on future claims. This article will explore some of the common types of claim waivers that can be found in project documents so that you are better positioned to avoid inadvertently waiving claims in the future.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
Ensuring Efficient Arbitration of Construction Disputes Involving Mechanic’s Liens
February 18, 2020 —
Robert G. Campbell & Trevor B. Potter - Construction ExecutiveThere may be tension between the enforcement of statutory mechanic’s lien claims when a contractual dispute resolution provision calls for arbitration. Once the parties are in arbitration, it may not be clear whether the arbitrator has authority to make factual determinations regarding amount and validity of mechanic’s liens, and whether courts are bound by these determinations. This uncertainty stems from the fact that in most states a mechanic’s lien can only be enforced by a court of competent jurisdiction. Indeed, many mechanic’s liens statutes define foreclosure as a “judicial process,” and courts generally have exclusive jurisdiction to issue orders foreclosing on real property1.
The risk for contractors and owners is that they will spend time and money re-litigating factual issues related to proving elements of a mechanic’s lien claim, including the proper lien amount, timeliness and other prerequisites. Without a clear understanding of what issues and elements are arbitrable, the parties run the risk that an arbitrator will rule on certain elements only to find out during post-arbitration lien foreclosure proceedings that the arbitrator lacked authority to make determinations on those elements. Questions therefore arise whether a court will enforce the arbitrator’s determinations and whether the parties must relitigate mechanic’s lien issues creating a further risk of inconsistent rulings.
These risks can be minimized through arbitration provisions which address these issues, express requests in arbitration demands and by ensuring that arbitration awards contain explicit determinations of mechanic’s liens issues.
Reprinted courtesy of
Robert G. Campbell & Trevor B. Potter, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Potter may be contacted at tpotter@coxcastle.com
Mr. Campbell may be contacted at rcampbell@coxcastle.com
Read the court decisionRead the full story...Reprinted courtesy of
MGM Begins Dismantling of the Las Vegas Harmon Tower
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFMGM has begun to dismantle the $8.5 billion, incomplete Harmon Hotel in Las Vegas, Nevada, according to the Las Vegas Review-Journal. The demolition process is expected to take up to a year.
The Las Vegas Review-Journal reported that construction of the tower was halted in 2008 after construction defects were allegedly discovered. Later, “the building was deemed structurally unsound.”
“Instead of blowing the building up in grand fashion, contractors hired by MGM Resorts are now removing scrap metal and other materials from the building, along with taking off the blue-tinged glass that has covered the structure for the last five years,” Howard Stutz wrote in the Las Vegas-Review Journal. “The process also includes installing pedestrian protection systems outside the structure above adjacent sidewalks and walkways.”
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Supreme Court Asked Whether Attorney-Client Privilege Waived When Insurer Denies Bad Faith
September 18, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Fourth Circuit certified the following question to the South Carolina Supreme Court: Does South Carolina law support application of the "at issue" exception to the attorney-client privilege such that a party may waive the privilege by denying liability in its answer? In Re: Mt. Hawley Ins. Co., 2018 U.S. App. LEXIS 17910 (4th Cir. June 28, 2018).
Mt. Hawley insured Contravest Construction Company under an excess commercial liability policy from July 21, 2003 to July 21, 2007. During this period, Contravest constructed a development in South Carolina. In 2011, the Owners Association sued Contravest for alleged defective construction. Mt. Hawley denied tenders to defend or indemnify. Contravest ultimately settled the case.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Illinois Supreme Court Rules Labor Costs Not Depreciated to Determine Actual Cash Value
November 19, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Supreme Court determined that a homeowner insurer may not depreciate labor costs in calculating actual cash value (ACV) after a loss under the policy. Sproull v. State Farm Fire and Casualty Co., 2021 Ill. LEXIS 619 (Ill. Sept. 23, 2021).
Plaintiff was insured under a homeowner's policy that provided replacement cost coverage for structural damage. Under the policy, the insured would initially receive an ACV payment but then could receive replacement cost value (RCV) if repairs or replacement were completed within two years and the insurer was timely notified. The policy did not define "actual cash value."
Plaintiff suffered wind damage to his residence and timely submitted a property damage claim to State Farm. The adjuster determined that the building sustained a loss with RCV of $1711.54. In calculating ACV, State Farm began with the RCV and then subtracted plaintiff's $1000 deductible and an additional $394.36, including taxes, for depreciation. Plaintiff thus received an ACV payment of $317.18. Plaintiff claimed that he was underpaid on his ACV claim because State Farm depreciated labor, which is intangible and thus not subject to wear, tear, and obsolescence. Further, labor should not have been depreciated because it was not susceptible to aging or wearing and its value did not diminish over time.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Legislative Update on Bills of Note (Updated Post-Adjournment)
March 27, 2019 —
Christopher G. Hill - Construction Law MusingsIn two prior posts, one specifically relating to a bill that was introduced to apply a statute of limitatons on state agencies for construction projects and one more general, I discussed some of the legislation pending in the Virginia General Assembly that could be of interest to construction professionals.
This post will update the status of these bills and add one that I neglected to highlight in the prior posts. I’ll begin with the oversight.
HB 2218 Makes the unlawful and unlicensed practice of contracting, real estate brokering, or real estate sales, in connection with a consumer transaction, unlawful under the Virginia Consumer Protection Act. In short, it makes explicit what was implicit, namely that contractors that perform work without a license are in violation of the VCPA. This bill has passed the house by unanimous vote and is in committee at the Senate.
UPDATE– As of February 20, 2019, this bill has passed both houses, all that is left is the paperwork. Post Adjournment Update: This bill passed and awaits Governor’s signature.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Supreme Court Declines Request to Expand Exceptions to Privette Doctrine for Known Hazards
January 17, 2022 —
Garret Murai - California Construction Law BlogFirst things first. Happy New Year! Hope you had a good one.
To start things off in the new year we’ve got an employment-related case for you – Gonzalez v. Mathis, 12 Cal.5th 29 (2021) – a California Supreme Court case involving the Privette Doctrine. For those not familiar with the Privette Doctrine, the Privette Doctrine is named after the case Privette v. Superior Court, 5 Cal.4th 689 (1993), which held that project owners and higher-tiered contractors are not liable for workplace injuries sustained by employees of lower-tiered contractors. Since then, courts have carved out a few exceptions to the Privette Doctrine including the “retained control exception” (also known as the Hooker exception – that’s the name of the case not the occupation of the injured worker) whereby a “hirer,” that is, the higher-tiered party who hired the lower-tiered party whose employee is injured, can be held liable if the hirer: (1) retains control over any part of the lower-tiered party’s work; and (2) negligently exercises that control in a manner that affirmatively contributes to the worker’s injury.
Another exception is the “concealed hazard exception” (also known as the Kinsman exception) whereby a hirer can be held liable if: (1) the hirer knew, or should have known, of a concealed hazard on the property that the lower-tiered contractor did not know of and could not have reasonably discovered; and (2) the hirer railed to warn the lower-tiered contractor of that hazard.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Prolonged Effects on Commercial Property From Extreme Weather
January 29, 2024 —
The Hartford Staff - The Hartford InsightsAs evidenced by the extraordinary heat in the Southwest, a string of tornadoes in South and Midwest, and heavy rains in California and Florida, 2023 was a banner year for extreme weather. However, 2024 may be no different, which means now is the time for businesses to rethink the way they approach volatile weather, as well as the frequency and severity of storms and natural disasters.
The risks and challenges that businesses face as extreme weather becomes stronger and causes more property damage, requires innovative technology with specialized insurance solutions. Through updated building codes, advancements in technology and meaningful infrastructure improvements, businesses can make a difference in protecting their property and reducing losses.
Stronger Building Codes To Withstand Storms
It is not uncommon to see the destruction that a hurricane or tornado leaves behind. However, stronger building codes are one of the best ways to make sure property can withstand catastrophes. Florida for example implemented changes to its building codes after Hurricane Andrew, and then again in 2007 after the Hurricanes of 2004 and 2005. New construction since then has made houses and buildings significantly more hurricane proof. Buildings constructed 30 years ago were likely built with codes that may have neglected the impact of strong winds from an extreme hurricane or significant rainfall that a storm can bring, especially along the Atlantic and Gulf coasts.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights