How the California and Maui Wildfires Will Affect Future Construction Projects
October 30, 2023 —
Susan Doering - Construction ExecutiveJust like any kind of fire, wildfires are caused by the presence of fuel and a spark. In the case of the
2017 fires in the wine country of California, along with the state's 2018
Camp Fire, the fuel was dry leaf litter, branches and downed trees. And the spark, in some cases, resulted from electric utility lines and, in other cases, due to contractor’s work.
More recently, this summer's Maui fires have taken hundreds of lives—deceased and missing—and burned more than 2,500 acres. Lahaina’s historic sites cannot be replaced, and estimates of the rebuild costs are near $5 billion. In Hawaii, the fuel was the same as in California: dried forest debris. It is alleged that the spark was from a powerline downed by extreme winds from Hurricane Dora. While sparks were present, it is the increased volume of fuel that has been the true source of the disastrous recent wildfires.
The increased presence of fuel is the result of recent changes in forestry-management practices, coupled with accelerated climatic shifts in recent years toward hotter, drier weather from 2011 to 2020 in California and 2022 to 2023 in Maui, increasing both frequency and severity.
Reprinted courtesy of
Susan Doering, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
DRCOG’s Findings on the Impact of Construction Defect Litigation Have Been Released (And the Results Should Not Surprise You)
November 13, 2013 —
Derek Lindenschmidt — Higgins, Hopkins, McLain & Roswell, LLC.The downward trend in attached-housing construction in Colorado is well-known and discussed often within the region’s construction, insurance, finance, and legal communities. In recent years, builders and insurers in particular have striven to bring greater awareness to local governments and lawmakers regarding the impact that construction defect lawsuits have on the builders’ ability to introduce desirable, affordable, yet cost-efficient attached-housing options, such as condominiums and townhomes, into the marketplace. The Denver Regional Council of Governments (“DRCOG”) has been aware of the builders’ and insurers’ plight, largely because of the impact that the scarcity of affordable attached-housing has had on their respective communities.
On October 29th, DRCOG released its long-awaited Denver Metro Area Housing Diversity Study, prepared by Economic & Planning Systems, Inc., which investigated the factors contributing to the recent (downward) attached-housing development trends and conditions. The Study evaluated factors including changing financing and insurance requirements for builders and homebuyers, the impacts of foreclosures, changes in prospective homebuyer demographics, economic conditions which limit options for prospective homebuyers, and the costs and risks associated with construction defect regulations and lawsuits.
Despite the retorts and rebukes of the naysayers, the negative impact of construction defect regulations and lawsuits on Colorado’s housing market is significant.
Read the court decisionRead the full story...Reprinted courtesy of
Derek LindenschmidtDerek Lindenschmidt can be contacted at
lindenschmidt@hhmrlaw.com
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
US Court Questions 102-Mile Transmission Project Over River Crossing
February 07, 2022 —
Mary B. Powers - Engineering News-RecordA federal judge will decide in February whether to stop construction of a $492-million Iowa-to-Wisconsin transmission line, after issuing an opinion in mid-January “declaring” that federal rules preclude the 102-mile Cardinal-Hickory Creek project from crossing the 261-mile Upper Mississippi River National Wildlife and Fish Refuge by right-of-way or land transfer.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Firm Seeks to Squash Subpoena in Coverage CD Case
May 20, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the New Jersey Law Journal, the insurance firm Carroll McNulty & Kull was “subpoenaed in connection with an out-of-state coverage dispute stemming from construction litigation that yielded a $55 million verdict," and "is fighting a demand that it hand over its file.”
Carroll McNulty & Kull told the New Jersey Law Journal that “the subpoena ‘is a transparent attempt to obtain documents ordinarily protected by the attorney-client privilege and work product doctrine.”
The New Jersey Law Journal reported that the subpoena “seeks ‘your entire file for the time period beginning Oct. 1, 2012, and ending June 19, 2014, pertaining in any manner to insurance policies issued by Crum and Forster Specialty Insurance Company.’ Included in the demand are ‘all handwritten or electronically stored notes; electronic and other communications,’ ‘emails and all attachments to those emails, time records, and bills,’ and ‘any documents and materials reviewed.’”
U.S. District Judge Peter Sheridan has been assigned the motion to quash.
Read the court decisionRead the full story...Reprinted courtesy of
Counsel Investigating Coverage Can be Sued for Invasion of Privacy
January 28, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Strawn v. Morris, Polich & Purdy (No. A150562, filed 1/4/19), a California appeals court held that policyholders could state a claim for invasion of privacy against an insurer’s coverage counsel and law firm, where the counsel had disseminated inadvertently produced tax returns to forensic accountants while evaluating coverage.
In Strawn, a couple’s home was destroyed by fire and the husband was prosecuted for arson, but the criminal case was dropped. Notwithstanding, their insurance claim was denied on the ground that the husband intentionally set the fire and fraudulently concealed his actions. In addition to the insurance company, the insureds also named the carrier’s coverage counsel and his firm in the ensuing bad faith lawsuit, alleging causes of action for elder financial abuse and invasion of privacy.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What If Your CCP 998 Offer is Silent on Costs?
March 18, 2019 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogIn California, the “prevailing party” in litigation is generally entitled to recover its costs as a matter of law. See Cal. Code Civ. Proc. § 1032. But under California Code of Civil Procedure section 998, a party may make a so-called “offer to compromise,” which can reverse the parties’ entitlement to costs after the date of the offer, depending on the outcome of the litigation. Cal. Code Civ. Proc. § 998. The potential payoff of a 998 offer is that “If an offer made by a defendant is not accepted and the plaintiff fails to obtain a more favorable judgment or award, the plaintiff shall not recover his or her postoffer costs and shall pay the defendant’s costs from the time of the offer.” Cal. Code Civ. Proc. § 998(c)(1) (emphasis added).
But how do you determine whether a plaintiff obtained a more favorable judgment when the 998 offer is silent with respect to whether it includes costs?
In Martinez v. Eatlite One, Inc. (2018) 27 Cal.App.5th 1181, 1182–83, the defendant made a 998 offer of $12,001 that was silent regarding the treatment of attorneys’ fees and costs. Plaintiff did not respond to the offer, and the jury ultimately awarded plaintiff damages of $11,490. Id. In resolving the parties’ competing memoranda of costs and plaintiff’s motion for attorneys’ fees, the trial court awarded plaintiff her costs and attorneys’ fees. Id. at 1182. The trial court reasoned that plaintiff had obtained a more favorable judgment than the 998 offer because she was entitled to pre-offer costs and attorneys’ fees under the statute, which meant plaintiff’s ultimate recovery exceeded the 998 offer when added to the judgment. Id. at 1183. In other words, the court added plaintiff’s pre-offer costs and attorneys’ fees to the $11,490 verdict for the purposes of determining whether the “judgment” was greater than the 998 offer of $12,001. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com