Affirmed: Nationwide Acted in Bad Faith by Failing to Settle Within Limits
July 19, 2017 —
Bethany Barrese – Saxe Doernberger & Vita, P.C.The Eleventh Circuit recently affirmed that Nationwide acted in bad faith by refusing to settle a claim against its insured for the policy limits, exposing the policyholder to an excess verdict.1
The case arose out of a 2005 automobile accident where Seung Park, who was insured by Nationwide, struck and killed another driver, Stacey Camacho. Shortly after the accident, Ms. Camacho’s estate issued a time-limited demand for the full limits of the policy Nationwide issued to Mr. Park, $100,000, to settle the case. After the deadline to respond to the demand expired, Nationwide rejected the demand and made a counteroffer. A settlement could not be reached and a wrongful death suit was filed against Mr. Park, resulting in a massive jury verdict of $5.83 million.
Following the jury verdict, Mr. Park assigned his rights against Nationwide to Ms. Camacho’s estate, which then filed claims for negligence and bad faith failure to settle against Nationwide. The case was tried to a jury, which found in favor of the estate.
Read the court decisionRead the full story...Reprinted courtesy of
Bethany Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
blb@sdvlaw.com
Connecticut Court Finds Anti-Concurrent Causation Clause Enforceable
March 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiCanvassing both case law and scholarly authority, the court determined that the anti-concurrent cause (ACC) provision barred coverage for loss caused by Tropical Storm Irene. Lombardi v. Universal N. Am Ins. Co., 2015 Conn. Super. LEXIS 138 (Conn. Super. Ct. Jan. 21, 2015).
Tropical Storm Irene caused the insured's home to shift and move from its concrete pier foundation. The house later had to be demolished.
The insurer's expert concluded that the house was removed from the foundation by storm surge and not by wind. The damage caused by wind was limited to 24 feet of trim missing from the roof and about 70 square feet of shingles that were blown away. The insured's expert concluded the house was removed from its foundation due to a combination of wind and water forces. The insured's expert reported that "the water wave action most probably caused most damage to the dwelling support pilings, with wind conditions contributing to the wave action."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Supply Chain Delay Recommendations
August 07, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by supply chain delays.
Contract Protection Tips:
The construction industry is being impacted substantially by inability to obtain necessary construction products due to supply chain issues. Most construction contracts do not accommodate time extensions due to supply chain impacts. To address this gap in contract terms, we recommend including language such as: “lack of or failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers” as part of the defined force majeure event under the contract.
This provision can be included in the Change Order section of the contract as well by including a provision such as: “If the Work is delayed by the failure of or other inability to obtain necessary transportation, fuel, power, materials, machinery, equipment or facilities, delays caused by other contractors, subcontractors or their subcontractors of any tier, or any materialmen or suppliers, contractor shall be entitled to a change order for its costs and time associated with the delay.”
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Savannah Homeowners Win Sizable Judgment in Mold Case against HVAC Contractor
August 10, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPTwo Savannah homeowners filed a complaint against a local air conditioning contractor and its insurer, asserting claims of professional negligence and fraud. The couple alleged that in March 2009, the contractor replaced the duct system of their home’s air conditioning unit. The following June, the couple discovered mold growth on the vent covers. They hired an independent contractor who upon inspection concluded that the duct system, which contained holes, gaps, loose connections and insufficient mastic, had been defectively installed in violation of the applicable city ordinances, resulting in excessive moisture and mold contamination throughout the residence. The homeowners alleged that they grew ill with respiratory problems as a result and were subsequently forced to vacate the residence and abandon their personal belongings. Their complaint sought to recover repair costs, moving costs, expenses associated with rental property, costs of living, costs related to the replacement of personal property, medical expenses, punitive damages, attorney’s fees, and costs of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Virtual Jury Trials: The Next Wave of Remote Legal Practice
July 13, 2020 —
David R. Zaslow & Mark Paladino - White and WilliamsOne of the most obvious and unavoidable results of the COVID-19 crisis has been the postponement of jury service and, by extension, all jury trials. Given the inherent difficulties of convening juries in a world of social distancing, it is likely that multiple jurisdictions will be unable to conduct live jury trials for at least the next several months.
Recognizing the mounting delay and substantial docket backlog that is attendant to several months without jury trials, one court most recently permitted the litigants, upon consent, to try a new innovation – the nation’s first virtual jury trial conducted entirely on the Zoom platform. More than two dozen potential jurors in Collin County, Texas attended jury selection from home by smartphone, laptop, and tablet, a process that was streamed live on YouTube. The presiding judge occasionally provided prospective jurors technical advice on how to best use their devices.
Once selected, the jurors virtually attended a one-day, “summary jury trial” of an insurance dispute in which they heard a condensed version of the case and delivered a non-binding verdict. The parties were then able to gauge how their cases would fare before a jury in a full-scale trial and, with that insight, agreed to proceed to a mediation in an attempt to reach a resolution. Court officials further touted the abbreviated, non-binding experience as an ideal test for the viability of remotely holding jury trials that would result in a final judgment. This real-world test, albeit in a non-binding exercise, may be an indication of things to come, as courts in Indiana and Arizona have already communicated an intention to conduct jury trials remotely once able.
Reprinted courtesy of
David R. Zaslow, White and Williams and
Mark Paladino, White and Williams
Mr. Zaslow may be contacted at zaslowd@whiteandwilliams.com
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Stuck on You”
March 04, 2024 —
Daniel Lund III - LexologyA “contract of adhesion” is referred to as a standard form contract – usually preprinted – “prepared by a party of superior bargaining power for adherence or rejection of the weaker party.” Yet, it is not the nature of the contract alone which determines its enforceability, but, instead, “whether a party truly consented to all of the printed terms.”
A Louisiana plaintiff fighting a forum selection clause in a construction contract sought to have the clause nullified, urging that the clause was “buried” in the agreement and in small font, arguing also that the contractor had “superior bargaining position at the time of entering into the contract… because [plaintiff] needed to repair the hurricane damage” to his home as soon as possible.
In response, the contractor urged that the contract was not executed under rush conditions, and that, in any event, the contract was only two pages long – and the forum selection clause was not hidden and was in the same font as all of the other provisions in the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
“Unwinnable”: Newark Trial Team Obtains Unanimous “No Cause” Verdict in Challenging Matter on Behalf of NYC Mutual Housing Association
May 15, 2023 —
Lewis BrisboisNewark, N.J. (May 8, 2023) – Newark Partner Afsha Noran and New Jersey Managing Partner Colin P. Hackett recently obtained a “no cause” verdict on behalf of multi-unit apartment owners and managers, notwithstanding that the trial judge initially deemed the matter an “unwinnable case” for the defense.
In this matter, Lewis Brisbois represented a large New York City mutual housing association that owned and managed a single multi-unit apartment building in Paterson, New Jersey. The plaintiffs – a mother and her two children – alleged that the housing association failed to maintain the property, which led to defective conditions and mold throughout their apartment. They further contended that the mold caused multiple pulmonary, nasal, and skin injuries. Despite
the shortage of trial judges in New Jersey, this case proceeded to trial, with the plaintiffs’ significant six-figure demand in place.
Over the course of the four-day trial, the plaintiffs presented five witnesses: the plaintiff mother, the plaintiff 18-year-old child, the liability expert, and two medical experts. The client chose not to retain either liability or damages experts to counter those of the plaintiffs. As such, Lewis Brisbois’ trial team was left to defend the matter with an opening statement, a cross-examination of the plaintiffs and their experts, the testimony of the client’s property manager, and a closing argument.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
NYT Points to Foreign Minister and Carlos Slim for Collapse of Mexico City Metro
July 11, 2021 —
Amy Stillman - BloombergThe collapse last month of a section of a Mexico City metro line that killed 26 people was likely due to poor construction by Mexican tycoon Carlos Slim’s Grupo Carso while foreign minister Marcelo Ebrard was mayor, according to a New York Times investigation.
Problems were identified in the original construction by Slim’s company Carso Infrastructure and Construction, and the collapse was probably caused by bad welding of the steel studs that served as linchpins of the structure, the report revealed. The job may have been rushed because Ebrard sought to open the subway before his mayoral term ended in 2012, the Times said.
Read the court decisionRead the full story...Reprinted courtesy of
Amy Stillman, Bloomberg