How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Attempt to Shift Cost of Defense to Another Insurer Found Void as to Public Policy
June 09, 2016 —
Garret Murai – California Construction Law BlogWhile construction can sometimes be risky, construction litigation is almost always expensive. This volatile mix of risk and expense has made risk shifting, through indemnity and insurance, a primary goal and concern of project owners, contractors and suppliers alike. Construction insurers know this all too well and insurers, even between themselves, seek to shift risk.
As one primary insurer found, however, risk shifting provisions in their policies – specifically, one which sought to shift the cost of defense to another insurer – is not without its limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
New FAR Rule Mandates the Use of PLAs on Large Construction Projects
October 10, 2022 —
Reggie Jones - ConsensusDocsThe Federal Acquisition Regulatory Council recently published a proposed ruled that, once implemented, will require the use of project labor agreements (PLAs) on federal construction projects with a contract value of $35 million or greater. The proposed rule revokes President Obama’s Executive Order 13502 and implements an Executive Order 14063 (E.O. 14063) issued on February 9, 2022. E.O. 14063 addresses the use of PLAs in the government contracts. Under the current Federal Acquisition Regulation (FAR), the use of PLAs on “large-scale construction projects” is discretionary. The new rule proposed by the Department of Defense (DOD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA) revises the FAR contract clauses making the use of PLAs mandatory.
Under the proposed rule, contractors performing “large-scale construction projects” will be required to “negotiate or become a party to a [PLA] with one or more appropriate labor organizations.” FAR 52.222-33. A PLA is in essence a collective bargaining agreement between a local trade union and contractor that governs employment terms, including wages and benefits, for union and non-union workers. Although the PLA mandate only applies to large-scale construction projects with the contract value of $35 million and more, under the proposed rule, agencies have the option to include the PLA requirement for construction projects that are under the $35 million threshold. The proposed rule also sets out a flow-down requirement, which means that subcontractors working on a large-scale project must likewise be familiar with and comply with terms of the PLA negotiated by a prime contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Reggie Jones, Fox Rothschild LLP (ConsensusDocs)Mr. Jones may be contacted at
rjones@foxrothschild.com
Supreme Court’s New York Harbor Case Isn’t a ‘Sopranos’ Episode
August 03, 2022 —
Stephen L. Carter - BloombergThe long-simmering harbor dispute between New York and New Jersey has observers reaching for illustrations from “The Sopranos” and “On the Waterfront.” But now that the US Supreme Court has agreed to adjudicate the spat, I wonder whether a more useful resource might be “The Paper Chase.”
The disagreement stems from New Jersey’s determination to exit the Waterfront Commission of New York Harbor, an entity established by the two states back in 1953 in response to news reports of widespread corruption and violence among those who loaded and unloaded ships. New Jersey argues that as a sovereign state, it can’t be forced to remain in the pact forever. New York replies that the deal has the force of law and neither state can quit without the permission of the other. (And Congress!)
The Supreme Court is now involved because that’s the venue the Constitution prescribes when one state sues another. Four days before New Jersey’s announced departure date of March 28, the justices issued an injunction preventing the move. This week they agreed to adjudicate the dispute and set an accelerated schedule for briefs and oral argument.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen L. Carter, Bloomberg
"Multiple Claims" Provisions on Contractor's Professional Liability Policy Creates a Trap for Policyholders
May 24, 2021 —
Michael V. Pepe - Saxe Doernberger & VitaIn Berkley Assurance Company v. Hunt Construction Group, Inc., 465 F.Supp.3d 370 (S.D.N.Y., 2020), professional liability insurer Berkley sued its insured, Hunt, a construction management firm, seeking a declaration that it did not owe Hunt a duty to defend and indemnify against breach of contract claims. The United States District Court for the Southern District of New York granted Berkley’s motion for summary judgment and denied Hunt’s motion for partial summary judgment. Among other things, the court held that the policy’s automatic extended reporting period did not apply to Hunt’s first claim. The multiple claims provision barred Hunt’s second claim because the claims were related.
The court’s holding creates a potential trap for policyholders who wait to see how a claim develops before reporting it to their insurance carrier. This case demonstrates that waiting to see how a claim develops can result in a loss of coverage. Policyholders need to be aware of this trap and report all claims and circumstances immediately.
Read the court decisionRead the full story...Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & VitaMr. Pepe may be contacted at
MPepe@sdvlaw.com
High School Gym Closed by Construction Defects
October 28, 2011 —
CDJ STAFFThe high school gym in Lake Oswego, Oregon has been shut down because testing has revealed that the construction defects have lead to deterioration of the structural integrity of the roof. The school district noted that there was a chance of collapse if there were a “significant seismic event or heavy rain and winds and snow.” The school district has been in a lawsuit with the builders since 2008, which was recently settled for $600,000.
The school board is still determining whether the original contractor will be asked to correct the defect or if they will bid the job out.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
CGL, Builders Risk Coverage and Exclusions When Construction Defects Cause Property Damage
May 17, 2021 —
Jeffrey Cavignac - Construction ExecutiveDirect damage to property under construction caused by faulty or defective work or defective materials has been a coverage issue for decades. Two specific policies, the Commercial General Liability for the contractors building the structure and the Builders Risk Policy on the project both are sources of potential coverage.
A CGL policy protects the named insured (the contractor in this case) from third party liability arising out of the insured’s operations that results in either bodily injury or property damage. Damage to property caused by poor workmanship or defective materials would qualify as property damage. To understand how the CGL policy might respond to claims such as these, it is necessary to evaluate several exclusions in the CGL policy.
CGL policies cover “property damage,” defined as physical injury to tangible property, including loss of use of such property, and loss of use of tangible property that has not been physically injured.
Reprinted courtesy of
Jeffrey Cavignac, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of