Like Water For Chocolate: Insurer Prevails Over Chocolatier In Hurricane Sandy Claim
November 08, 2017 —
Afua S. Akoto - Saxe Doernberger & Vita, P.C.Recently, a New Jersey Magistrate ruled that an insurer did not have to provide coverage for a chocolatier’s property damage and business interruption losses due to Hurricane Sandy.
Madeline Chocolate Novelties Inc. (Madeline), a family-owned chocolatier in Queens Rockaway Beach, held a one-year all-risk policy with Great Northern Insurance (Great Northern). The policy contained a flood exclusion and a windstorm endorsement. When Hurricane Sandy hit in October 2012, Madeline suffered extensive damage and ceased operations during the ensuing holiday season. The chocolatier claimed $40 million in property damage and $13.5 million in business interruption losses and sought coverage under its policy. Great Northern paid just under $4 million and denied the remainder of the claim, citing the policy’s flood exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Afua S. Akoto, Saxe Doernberger & Vita, P.C.Ms. Akoto may be contacted at
asa@sdvlaw.com
Angela Cooner Appointed Vice-Chair of Arizona’s Inaugural Board of Legal Specialization Construction Defect Law Advisory Commission
June 20, 2022 —
Angela Cooner - Lewis BrisboisPhoenix, Ariz. (May 17, 2022) - Phoenix Partner Angela Cooner has been appointed as the vice-chair of the State Bar of Arizona’s inaugural Board of Legal Specialization Construction Defect Law Advisory Commission. The commission was created pursuant to the Arizona Supreme Court’s recent administrative order recognizing construction defect law as a new area of specialization.
The commission will, among other things, create the application, examination, and interview process that Arizona attorneys will be required to complete to earn the construction defect law specialized certification. Ms. Cooner will serve a two-year term that will end on January 31, 2024.
Read the court decisionRead the full story...Reprinted courtesy of
Angela Cooner, Lewis BrisboisMs. Cooner may be contacted at
Angela.Cooner@lewisbrisbois.com
Social Engineering Scams Are On the Rise – Do I Have Insurance Coverage for That?
June 01, 2020 —
Jeffrey Dennis & Heather Whitehead - Newmeyer DillionCyber attackers all know that the majority of organizations are currently working from home due to the ongoing COVID-19 (commonly referred to as the Coronavirus) pandemic. And, as would be expected, social engineering scams are on the rise. Nonetheless, there may be limitations in your cyber liability insurance policy for these types of claims. It is advisable to take the initiative to review such insurance policies in detail for coverage considerations prior to the occurrence of any cyber incident. And, of course, protect your business from attacks by engaging in precautious cyber safety efforts.
What Is Social Engineering?
Social engineering refers to various means to manipulate individuals in the online environment so that they divulge sensitive, personal information, such as banking information, which may include account numbers and passwords. This can also take the form of receiving a request to transfer funds to what the victim believes is another employee, trusted financial information or other party with whom the person has a business relationship with. Unfortunately, however, those funds ultimately are received by the engineer of the cyber attack.
Reprinted courtesy of
Jeffrey M. Dennis, Newmeyer Dillion and
Heather Whitehead, Newmeyer Dillion
Mr. Dennis may be contacted at jeff.dennis@ndlf.com
Ms. Whitehead may be contacted at heather.whitehead@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?
January 27, 2020 —
Ted R. Gropman & Christine Z. Fan - ConsensusDocsConstruction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.
Courts are split as to whether damages for a contractor’s “acceleration” efforts are distinguishable from “delay” damages such that they may be recovered under an enforceable no-damage-for-delay clause. See, e.g., Siefford v. Hous. Auth. of Humboldt, 223 N.W.2d 816 (Neb. 1974) (disallowing the recovery of acceleration damages under a no-damage-for-delay clause); but see Watson Elec. Constr. Co. v. Winston-Salem, 109 N.C. App. 194 (1993) (allowing the recovery of acceleration damages despite a no-damage-for-delay clause). The scope and effect of a no-damage-for-delay clause depend on the specific laws of the jurisdiction and the factual circumstances involved.
There are a few ways for a contractor to circumvent an enforceable no-damage-for-delay clause to recover acceleration damages. First, the contractor may invoke one of the state’s enumerated exceptions to the enforceability of the clause. It is helpful to keep in mind that most jurisdictions strictly construe a no-damage-for-delay clause to limit its application. This means that, regardless of delay or acceleration, courts will nonetheless permit the contractor to recover damages if the delay is, for example, of a kind not contemplated by the parties, due to an unreasonable delay, or a result of the owner’s fraud, bad faith, gross negligence, active interference or abandonment of the contract. See Tricon Kent Co. v. Lafarge N. Am., Inc., 186 P.3d 155, 160 (Colo. App. 2008); United States Steel Corp. v. Mo. P. R. Co., 668 F.2d 435, 438 (8th Cir. 1982); Peter Kiewit Sons’ Co. v. Iowa S. Utils. Co., 355 F. Supp. 376, 396 (S.D. Iowa 1973).
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and Christine Z. Fan, Pepper Hamilton LLP
Mr. Gropman may be contacted at gropmant@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Effective Allocation of Damages for Federal Contract Claims
October 25, 2021 —
Dirk D. Haire, Joseph L. Cohen & Jane Han - ConsensusDocsFederal construction contracts law generally recognizes four basic methods for pricing damages: (1) Actual Cost Method (ACM); (2) Total Cost Method (TCM); (3) Modified Total Cost Method (MTCM); and (4) Jury Verdict Recovery Method (JVRM). In practice, it is difficult to obtain significant recoveries on TCM and JVRM claims, and only marginally easier on MTCM claims. That is because the courts and boards that hear federal government contracts cases have developed a clear preference for the ACM. Despite this preference, many contractors do not have systems in place to maximize their opportunity to recover damages under the ACM. This article introduces various strategies for tracking and allocating damages during project performance in a manner that will support an ACM analysis if a federal construction claim is litigated.
Background: Four Basic Methods for Pricing Damages
The four methods for pricing damages are described, below:
1. Actual Cost Method
The actual cost method claims damages based on records of “actual costs” that were documented during the performance of the contract. All additional costs must be separately recorded from the costs incurred in the normal course of contract performance. Because contractors provide the court or board with documented underlying expenses under the actual cost method, courts and boards prefer this method. However, the actual cost method may not always be feasible where a contractor is confronted with drastic changes early and often in a project.
Reprinted courtesy of
Dirk D. Haire, Fox Rothschild LLP,
Joseph L. Cohen, Fox Rothschild LLP and
Jane Han, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Cohen may be contacted at jlcohen@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Suffolk Stands Down After Consecutive Serious Boston Site Injuries
May 23, 2022 —
Scott Van Voorhis - Engineering News-RecordAfter two serious safety incidents in consecutive days, the Boston-area’s largest contractor voluntarily issued a safety stand down on all projects in Boston through May 6.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Why Is California Rebuilding in Fire Country? Because You’re Paying for It
March 14, 2018 —
Christopher Flavelle – BloombergAfter last year’s calamity, officials are making the same decisions that put homeowners at risk in the first place.
At the rugged eastern edge of Sonoma County, where new homes have been creeping into the wilderness for decades, Derek Webb barely managed to save his ranch-style resort from the raging fire that swept through the area last October. He spent all night fighting the flames, using shovels and rakes to push the fire back from his property. He was even ready to dive into his pool and breathe through a garden hose if he had to. His neighbors weren’t so daring—or lucky.
On a recent Sunday, Webb wandered through the burnt remains of the ranch next to his. He’s trying to buy the land to build another resort. This doesn’t mean he thinks the area won’t burn again. In fact, he’s sure it will. But he doubts that will deter anyone from rebuilding, least of all him. “Everybody knows that people want to live here,” he says. “Five years from now, you probably won’t even know there was a fire.”
As climate change creates warmer, drier conditions, which increase the risk of fire, California has a chance to rethink how it deals with the problem. Instead, after the state’s worst fire season on record, policymakers appear set to make the same decisions that put homeowners at risk in the first place. Driven by the demands of displaced residents, a housing shortage, and a thriving economy, local officials are issuing permits to rebuild without updating building codes. They’re even exempting residents from zoning rules so they can build bigger homes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Flavelle, Bloomberg
Hold on Just One Second: Texas Clarifies Starting Point for Negligence Statute of Limitations
July 11, 2022 —
Lian Skaf - The Subrogation StrategistIn construction or similar ongoing projects, problems often pop up. Sometimes they can pop up again and again. Making things even more complicated, one problem may affect another, seemingly new problem. When these construction problems result in property damage, timelines tend to overlap and determining when a statute of limitation begins to run for a particular claim can be difficult. Especially in states with short statute of limitations for tort claims like Texas, knowing when a statute begins to run is crucial for a subrogation professional.
In Hussion St. Bldgs., LLC v. TRW Eng’rs, Inc., No. 14-20-00641-CV, 2022 Tex. App. LEXIS 2193, 2022 WL 1010313, the Court of Appeals of Texas provided clarity on when the two-year statute of limitations for tort claims begins to run. Reversing the judgment from the lower court, the appellate court denied summary judgment to the defendant, holding that, despite there being existing issues with the ongoing construction project, the negligence cause of action for Hussion Street Buildings, LLC (Hussion) did not begin to run more than two years prior to filing suit.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com