Need to Cover Yourself for “Crisis” Changes on a Job Site? Try These Tips (guest post)
July 02, 2018 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, we welcome back friend of the blog Christopher G. Hill.
Chris is a LEED AP, a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. Chris authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals.
As construction professionals we’ve all been there. Something happens on a job site that requires immediate attention and possibly a changed sequence of work or possibly a change to a subcontractor’s scope. It could be a buried power line that Miss Utility failed to mark properly or an owner that wants a different HVAC configuration at the last minute. It could also simply be that it rained too much, and work had to slow down.
The above examples are instances of items that are beyond the control of the general contractor or the subcontractors and are the type that require shifts in work schedules and changes in scope that must be dealt with on the fly and require quick decisions and immediate action if the project is to meet any time of completion reasonably close to that which is listed in the contract documents. It can often seem that there is no time to meet the written change order provisions of any well drafted construction contract.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Forget Palm Springs—Santa Fe Is the New Mecca for Modern Architecture
November 19, 2021 —
James Tarmy - BloombergThe writer Helen Thompson had been a lifelong visitor to Santa Fe, but when she arrived at Georgia O’Keeffe’s home at Ghost Ranch 30 years ago, “I was shocked,” Thompson says. “Everything there was modern: Her furniture was modern; her light fixtures were modern; her art, of course, was modern. And in this rustic setting, the landscape is so powerful, it was all so elemental. That shock stayed with me.”
It was an experience, Thompson says, that led her to the conclusion that Santa Fe, long understood as a city filled with vernacular, decorative architecture, was ripe for a rethinking. “I kept wondering, why does something like that look so right here?” she says. “The landscape is so distinctive, and so not-modern, and yet these very precise pieces of furniture looked so right.”
Now, with her new book Santa Fe Modern: Contemporary Design in the High Desert (Monacelli, $50), Thompson has cracked the code. “Modern ideas are site-specific, and tied into what’s right for the landscape and the environment,” she says. Naturally, she continues, this conceptual framework works well in a place like New Mexico, where the dramatic horizon meets an even more dramatic sky.
Read the court decisionRead the full story...Reprinted courtesy of
James Tarmy, Bloomberg
Hunton’s Geoffrey Fehling Confirmed to DC Bar Foundation’s Young Lawyers Network Leadership Council
December 30, 2019 —
Michael S. Levine - Hunton Andrews KurthCongratulations to Hunton Andrews Kurth LLP insurance recovery lawyer,
Geoffrey Fehling, on his confirmation by the DC Bar Foundation’s Board of Directors to the organization’s Young Lawyers Network Leadership Council.
As the leading funder of civil legal aid in the District of Columbia, DCBF awards grants to the District’s legal services organizations that provide free civil legal services to low-income and underserved people in the District. Since its inception, DCBF has awarded more than $80 million in grants.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Expert Medical Science Causation Testimony Improperly Excluded under Daubert; ID of Sole Cause of Medical Condition Not Required
April 15, 2014 —
R. Bryan Martin & Whitney L. Stefko - Haight Brown & Bonesteel LLPOn April 4, 2014, in Messick v. Novartis Pharmaceuticals Corp., the United States Court of Appeals for the Ninth Circuit reversed the district court's summary judgment in favor of Defendant Pharmaceutical Corporation because the district court improperly excluded expert testimony. The three-judge panel held that the district court erred by excluding causation testimony offered by Plaintiff's expert it found to be irrelevant and unreliable.
Plaintiff was diagnosed with breast cancer in 2000. In response to her development of osteoporosis after chemotherapy, Plaintiff treated with the drug Zometa for several months in 2002. Zometa is a bisphosphonate, a class of drug commonly used to treat multiple myeloma. Such drugs are generally used to reduce or eliminate the possibility of skeletal-related degeneration and injuries to which cancer patients are particularly susceptible. Novartis Pharmaceuticals Corporation produces Zometa, which was approved by the FDA in 2001 and 2002. In 2005 after encountering issues with her jaw, it was discovered that Plaintiff had osteonecrosis near three of her teeth. The oral specialists treating Plaintiff did so under the assumption that she was suffering from bisphosphonate-related osteonecrosis of the jaw ("BRONJ"), a condition recognized by the American Association of Oral and Maxillofacial Surgeons ("AAOMS"). Plaintiff's BRONJ healed in 2008 - three years after beginning treatment.
Thereafter, Plaintiff brought suit against Novartis for strict products liability, negligent manufacture, negligent failure to warn, breach of express and implied warranty, and loss of consortium. In support of her claims, Plaintiff offered her expert's testimony on ONJ and BRONJ, and on the causal link between plaintiff's bisphosphonate treatment and later development of BRONJ. Novartis filed a Daubert motion to exclude the specific causation testimony of Plaintiff's experts and a motion seeking summary judgment. The district court granted both motions on the basis that Plaintiff's expert testimony was irrelevant and unreliable.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Supreme Court Construes Designated Premises Endorsement In Insured's Favor
April 01, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Hawaii Supreme Court held that a Designated Premises Endorsement provided coverage for injury and damage that occurred away from a listed location if the injury or damage arose out of the ownership, maintenance or use of the designated premises. C. Brewer and Co., Ltd. v. Marine Indemn. Ins. Co., 2015 Haw. LEXIS 62 (Haw. March 27, 2015). [Disclosure: our office represents C. Brewer].
The case involves coverage for the former owner (C. Brewer) of land under the Kaloko Reservoir. The Reservoir was fronted by an earthen dam. The Dam burst in March 2006, killing seven people and causing extensive property damage downstream.
In 1977, the State of Hawaii and C. Brewer entered an agreement requiring C. Brewer to, among other things, restore and expand the irrigation system that provided water to sugar cane fields in Kilauea, Kauai. C. Brewer formed the Kilauea Irrigation Company (KIC) to satisfy obligations to the State, revitalize the System, and sell System water to local farmers for irrigation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
White House Proposal Returns to 1978 NEPA Review Procedures
November 15, 2021 —
Karen C. Bennett - Lewis BrisboisWashington, D.C. (October 15, 2021) - The Council on Environmental Quality (CEQ) has requested comments, by November 22, 2021, on proposed revisions to the National Environmental Policy Act (NEPA) regulations. The proposal is Phase I in a two-phased approach that will eventually undo a final rule, effective September 2020, that updated NEPA regulations to reflect decades of agency experience and caselaw interpreting the 1969 Act.
Phase I proposes to reinstitute 1978 definitions for key terms used to determine the scope of review and the range of alternatives required when undertaking any major federal action. Phase II is expected to be an extensive rewrite of the 2020 regulations to incorporate climate change and environmental justice objectives. Businesses with projects, now or in the future, that require federal authorizations will need to pay close attention to these regulatory revisions.
The 2020 update rule intended to scale back the time and cost of producing NEPA analyses by focusing agency resources on evaluating effects that are within the agency’s ability to control and studying only those alternatives that would meet the project purpose. CEQ’s proposal eliminates these efficiencies.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Bennett, Lewis BrisboisMs. Bennett may be contacted at
Karen.Bennett@lewisbrisbois.com
Los Angeles Warehousing Mecca Halts Expansion Just as Needs Soar
September 05, 2022 —
Ngai Yeung & Augusta Saraiva - BloombergCommunities in the Inland Empire, the US’s logistics mecca east of Los Angeles, are suspending new warehousing projects to examine the impact from decades of pollution -- putting the industry under pressure when it’s needed most.
This week, the city council for Pomona is set to vote on extending a temporary halt on industrial developments to study the environmental impact, while the nearby city of Norco will decide whether to establish a 45-day moratorium. The actions follow similar freezes by a handful of Southern California cities like Riverside, Colton, Chino and Redlands over the past several years.
Meanwhile, a state-level bill -- which is a long-shot to pass in the legislature but gives a reading of the mood -- proposes banning large industrial construction within 1,000 feet of non-industrial areas such as schools, homes and playgrounds in Riverside and San Bernardino counties, an area that spans 27,000 square miles.
Reprinted courtesy of
Ngai Yeung, Bloomberg and
Augusta Saraiva, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of