Construction Defects Are Occurrences, Says South Carolina High Court
December 20, 2012 —
CDJ STAFFThe South Carolina Supreme Court has left the legislature’s new, expanded definition of “occurrence” in place, declining to declare it unconstitutional. South Carolina included faulty workmanship as an occurrence in response to a Supreme Court decision, which the court later reversed. One of the parties in that earlier decision, Harleysville Insurance, challenged the new law, claiming that the legislature didn’t have the power to pass a law to overturn a court ruling. The court did not concur.
However, the court did determine that the law was not retroactive and covered only claims filed after the law became effective in May 2011. The Chief Justice of South Carolina noted that “insurance coverage for construction liability lacks clarity, particularly with respect to whether construction defects constitute ‘occurrences’ under construction general insurance policies.”
Read the court decisionRead the full story...Reprinted courtesy of
Some Coastal Cities Are Sinking Even Faster Than Seas Are Rising
June 20, 2022 —
Ditas B Lopez - BloombergRising seas have long been a threat to coastal cities. New research suggests that cities—particularly in Asia—are sinking as well, compounding the risks of frequent and severe flooding.
In Karachi, land is sinking five times as fast as the sea level is rising, according to the study published this month in Geophysical Research Letters. Manila and Chittagong, Bangladesh’s second-largest city, are sinking at 10 times the rate of the rising waters.
In China’s Tianjin, a coastal city about 150 kilometers southeast of Beijing, the ground is giving way at 20 times that speed.
In those four cities alone, the phenomenon could affect roughly 59 million residents.
Read the court decisionRead the full story...Reprinted courtesy of
Ditas B Lopez, Bloomberg
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (8/6/24) – Construction Tech Deals Surge, Senators Reintroduce Housing Bill, and Nonresidential Spending Drops
September 16, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, cybersecurity attacks target contractors, U.S. banks report weaker profits, additional commercial real estate is distressed, and more!
- Spending dropped in almost half of nonresidential subcategories in June, with the decrease stemming from higher interest rates, tighter credit conditions and a softening economy. (Sebastian Obando, Construction Dive)
- Despite the decline in investment dollars for construction technology, the number of deals surged by 18% year-over-year, indicating sustained interest and activity in the sector. (Sebastian Obando, Construction Dive)
- As cybersecurity attacks on U.S.-based businesses ramp up, general contractors are not immune. (Jen A. Miller, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
State Farm Too Quick To Deny Coverage, Court Rules
July 22, 2011 —
CDJ STAFFOn July 13, 2011, Judge Sarah S. Vance of the US District Court issued a rule in the case of Travelers Cas. & Surety Co. of Am. v. Univ. Facilities, Inc. (E.D. La., 2011). In this case, Stanley Smith Drywall was contracted by Capstone Building Corporation to “perform undisclosed work at the facility believed to involve the installation of drywall.” The project involved the design and construction of student residences for the Southeastern Louisiana University in Hammond, Louisiana. In May, 2009, University Facilities, Inc. (UFI) sued Capstone Development Corporation and Capstone On-Campus Management.
State Farm insured Stanley Smith Drywall and they sought a declaration that they have no duty: “(1) to insure Stanley Smith or CBC, or (2) to defend or indemnify any party against UFI's claims in the pending arbitration.” State Farm contends “(1) there is no "occurrence" to trigger coverage under the policy; (2) only breach of contract claims are asserted; (3) there is no property damage alleged; and (4) various coverage limitations and exclusions apply to prevent coverage.’
The court concluded that “whether State Farm has a duty to defend in the arbitration must be determined by considering the claims asserted in the arbitration.” However, the arbitration claims were not made part of the record. There, “, the Court cannot determine as a matter of law State Farm's duty to defend on the present record.” The same was true of State Farm’s duty to indemnify. “Stanley Smith and CBC assert that State Farm's motion for summary judgment was filed before any discovery was conducted in the arbitration proceeding or in this case. The Court finds that State Farm has failed to develop the record sufficiently to establish that there is no genuine issue of material fact as to its duty to indemnify Stanley Smith or CBC in the arbitration.’
The court denied State Farm’s motion for a summary judgment on its duty to defend and indemnify.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeal Confirms Privette Doctrine as Applied to Passive Conduct of Property Owner
March 22, 2018 —
Bruce Cleeland and Frances Ma – Publications & InsightsIn
Delgadillo v. Television Center, Inc., 2018 No. B270985, the California Court of Appeal examined and refined the
Privette doctrine.
Mr. Delgadillo worked as a supervisor/window cleaner for a company named Chamberlin Building Services (CBS). Television Center, Inc. (TCI) purchased an existing building and thereafter contracted with CM Cleaning Solutions, Inc. (CMC) to provide cleaning and janitorial services. CMC, on behalf of TCI, solicited a proposal from CBS to wash the building’s windows. CBS and its employees made all decisions about how the window washing would be accomplished. The window washing equipment used on the job was owned, inspected and maintained by CBS. In violation of CBS’ policy, Mr. Delgadillo, attached a safety line to a single connector which was not an acceptable anchor point. The bracket failed and Mr. Delgadillo fell 50 feet to his death.
Survivors of Mr. Delgadillo filed suit against TCI for negligence and negligence per se, alleging that Mr. Delgadillo was fatally injured because TCI failed to install structural roof anchors, as required by several statutes.
Reprinted courtesy of
Bruce Cleeland, Haight Brown & Bonesteel LLP and
Frances Ma, Haight Brown & Bonesteel LLP
Mr. Cleeland may be contacted at bcleeland@hbblaw.com
Ms. Ma may be contacted at fma@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Dog Ate My Exclusion! – Georgia Federal Court: No Reformation to Add Pollution Exclusion
September 28, 2017 —
Philip M. Brown-Wilusz - Saxe Doernberger & Vita, P.C.While schoolchildren know that the classic “the dog ate my homework” excuse doesn’t work, insurance companies are willing to try a variation of that excuse. Ace American Insurance Company (Ace), sold a property policy (the Policy) to Exide Technologies, Inc. (Exide). Exide sought coverage under the Policy for acid damage at its former battery factory. Ace denied coverage, citing to the pollution exclusion. The only problem? The Policy contained no pollution exclusion!
Exide had procured policies from other insurers for several years prior to the inception of the Policy, all of which contained pollution exclusions. Exide instructed Marsh USA Inc. (Marsh), its broker, to procure insurance “on the same or better terms and conditions.” The resulting policy contained no pollution exclusion, and Exide sought coverage under the Policy for pollution-related losses.
Read the court decisionRead the full story...Reprinted courtesy of
Philip M. Brown-Wilusz, Saxe Doernberger & Vita, P.C.Mr. Brown-Wilusz may be contacted at
pbw@sdvlaw.com
New Jersey Law regarding Prior Expert’s Testimony
April 15, 2014 —
Beverley BevenFlorez-CDJ STAFFMary Pat Gallagher writing for the New Jersey Law Journal reported that “[l]awyers who track down an opposing expert's testimony from prior cases must disclose that fact during discovery but need not say whether they plan to use it in cross-examining the expert at trial, a New Jersey appeals court says.” In Dalton v. Crawley, the Appellate Division held that “[d]ecisions about cross-examination ‘involve the attorney's mental processes, so they are inherently work product.’”
The issue began when “one of the defense lawyers, Michael McGann, figured out from the deposition questions Mahoney directed at one of his experts that he had transcripts of testimony from earlier cases,” according to the New Jersey Law Journal. “Hit with a notice to produce the transcripts, [Plaintiff attorney Brian] Mahoney refused, saying they were ‘attorney work product and we will not be telling you what we have developed regarding this expert.’"
The New Jersey Law Journal declared that the “ruling means both sides will have to indicate what transcripts they have gathered for use—giving the name of each expert as well as the name and docket number of the prior cases where those experts testified. “
Read the court decisionRead the full story...Reprinted courtesy of