Receiving a $0 Verdict and Still Being Deemed the Prevailing Party for Purposes of Attorney’s Fees
May 24, 2018 —
David Adelstein - Florida Construction Legal UpdatesLow and behold, a party can be the prevailing party for purposes of attorney’s fees even if that party is awarded $0. That’s right, even if the party is awarded a big fat zero, they can still be the prevailing party for purposes of being entitled to attorney’s fees. This is because a party is the prevailing party if they prevail on the significant issues in the case. A party can prevail on the significant issues even if that party is awarded $0. Whoa!
For example, in Coconut Key Homeowner’s Association, Inc. v. Gonzalez, 43 Fla.L.Weekly D1045a (Fla. 4th DCA 2018), a homeowner sued her homeowner’s association claiming the association breached its governing documents. There was a basis for fees under Florida’s homeowner’s association law (and there likely was a basis under the governing documents). At trial, the jury held that the association breached its governing documents, but awarded the homeowner nothing ($0). The trial court also issued injunctive relief in favor of the homeowner. The homeowner claimed she should be deemed the prevailing party for purposes of attorney’s fees; however, this was denied by the trial court based on the $0 verdict and no fees were awarded to the homeowner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Should a Subcontractor provide bonds to a GC who is not himself bonded? (Bonding Agent Perspective)
May 03, 2017 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back, and for this week, Construction Law Musings welcomes Steve Moore. Steve has been the Construction & Surety Manager for Towne Insurance Agency-Invincia, in Chesterfield, VA since 2010. Steve’s experience in the Virginia surety bonding marketplace started in 1985 with USF&G. His underwriting travels took him from USF&G to starting National Grange Mutual’s mid-Atlantic bond department over Virginia, Maryland, Delaware, North & South Carolina, to being Reliance Surety’s “Firemark” bond manager in Virginia. Reliance was purchased by Travelers, where Steve continued to grow the surety book of business and build expertise and relationships. Experience with Travelers and Zurich had Steve handling surety bonds for some of Virginia’s largest and best-of-class contractors. Recently, he was contracted by the Commonwealth’s Attorney’s office to serve as a contract surety expert witness on behalf of the state. He is a 1985 graduate of Virginia Tech with double-major B.S. degrees in Finance and Marketing.
Today, Steve has business and relationships with Travelers, The Hartford, Westfield, CNA, CBIC, Selective, Liberty Mutual, Ohio Casualty, Cincinnati, and many other companies. Steve’s strong foundation of insurance knowledge and in bonding principles and practices allow him to serve as a great resource for his clients.
An old Aesop fable comes to mind when I am asked whether a Sub should bond to an unbonded GC:
"A woodsman entered the forest and asked the trees to give him a handle made of the best wood. After giving the woodsman a stave of hickory, the forest watched the woodsman fashion an axe onto the handle. In a flash, the woodsman began to chop down the various oaks and maples in the forest. The oak then said to a pine, “It serves us right, since we gave our adversary the very thing that contributes to our doom…"
When a subcontractor client of mine asks about bonding to an un-bonded general contractor, a number of questions immediately come to mind. Why isn’t the GC bonded? What is the existing relationship between the GC and Sub? How well is the job financed? While wanting to help my subcontractor procure work, and surely enjoying the commissions from writing a bond, I also want to help my sub client manage unforeseen risk. What are the risks to a sub, when posting a bond to an unbonded GC?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Congratulations to Las Vegas Partner Jeffrey W. Saab and Associate Shanna B. Carter on Obtaining Another Defense Award at Arbitration!
January 14, 2025 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPThe case arose from an incident at Plaintiff’s residence where she alleged that a failure to properly diagnose an issue with her HVAC unit led to its destruction, displacement from her home, and damage to her roof and kitchen, resulting in a diminution of value to her house. Jeff and Shanna represented the HVAC contractor, who denied any wrongdoing during the two-day arbitration at which a total of six witnesses were examined. Jeff and Shanna utilized Plaintiff’s own experts’ testimony to successfully challenge liability and bring forth a motion for spoliation, resulting in a complete defense award for Jeff and Shanna’s client, which included an award of costs.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
ConsensusDOCS Updates its Forms
October 21, 2015 —
Christopher G. Hill – Construction Law MusingsAs reported recently in ENR Magazine, among other publications, the ConsensusDOCS folks have updated their contract forms. Why is this news?
First of all, it’s only been around three and a half years since these documents were officially released and this release is about 18 months sooner than anticipated (the original revision cycle was to be 5 years). Why the revision? According to my friend and counsel to ConsensusDOCS, Brian Perlberg, one major rationale is that “the economics of the construction industry today looks nothing like it did [in 2007.”
Among the changes are several terminology changes (“constructor” instead of “contractor” for instance), the addition of mandatory green building design as a basic service (these forms already have a Green Building Addendum) if included in the Owner’s plan and the ability to provide for prevailing party attorney fees (before both sides of a dispute bore their own fees).
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Thirteen Payne & Fears Attorneys Honored by Best Lawyers
August 19, 2024 —
Payne & Fears LLPCongratulations to the 13 Payne & Fears attorneys included in the 2025 Edition of “Lawyer of the Year,” The Best Lawyers In America®, and Best Lawyers: Ones to Watch®. Attorneys have been recognized in the following practice areas:
2025 Edition “Lawyer of the Year”
Orange County
Benjamin A. Nix
Daniel F. Fears
- Litigation – Labor and Employment
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP
New York Restrictions on Flow Through Provision in Subcontracts
August 14, 2023 —
Bill Wilson - Construction Law ZoneMost subcontracts include a flow through provision (also called flow down and incorporation clauses) stating that the subcontractor and contractor are bound by the same obligations as set forth in the prime contract between the contractor and owner. Many jurisdictions interpret such provisions narrowly, as illustrated in a recent case out of New York. In Amerisure Insurance Company v. Selective Insurance Group, Inc., 2023 WL 3311879, the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s interpretation of a flow through clause in a construction subcontract. The Amerisure case involved a dispute over insurance coverage for a personal injury to a subcontractor’s employee on a construction project. The owner of the project sought defense and indemnity from the general contractor (GC) and its insurance company, who in turn sought coverage for the owner as an additional insured under the subcontractor’s policy. The GC based its argument for coverage on the flow through provision in the subcontract.
The prime contract required the GC to procure commercial liability insurance including the owner as an additional insured for claims caused by the GC’s negligent acts or omissions. The subcontract likewise required the subcontractor to procure commercial general liability insurance but required only that the GC be named as an additional insured. However, the subcontract also included a flow through clause, binding the subcontractor to the terms of the prime contract and assuming toward the GC all the obligations and responsibilities that the GC assumed toward the owner. However, the subcontract did not expressly require that the subcontractor name the owner as an additional insured, and in order for the owner to qualify as an additional insured under the subcontractor’s insurance policy, the subcontractor must have agreed in the subcontract to name the owner as an additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Unjust Enrichment and Express Contract Don’t Mix
August 23, 2021 —
Christopher G. Hill - Construction Law MusingsI am a huge fan of clearly written construction contracts. Virginia state and federal courts will interpret contract provisions as written and will seek to enforce all of those terms where possible. Where the contract is ambiguous, we construction attorneys make money and the courts are forced to make decisions that the parties may not like.
A recent case out of the Eastern District of Virginia federal court highlights the ways in which a clear contract affects the claims that can be brought and limits the scope of possible litigation. In First Call Environmental LLC v. Murphy Oil USA LLC, the Court looked at a relatively typical Owner, Contractor, Subcontractor set of agreements. In this matter, Murphy Oil entered a contract with National Rapid Response, Inc. (“NRR”) whereby NRR would provide emergency and environmental management and waste disposal services to Murphy Oil. NRR then subcontracted with the Plaintiff First Call to perform the services for Murphy Oil. First Call filed suit against Murphy Oil alleging two counts: breach of contract (based on a third-party beneficiary theory), and unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of