Florida District Court Finds That “Unrelated” Design Errors Sufficient to Trigger “Related Claims” Provision in Architects & Engineers Policy
March 02, 2020 —
Jason Taylor - Traub LiebermanMost professional liability polices include some form of a “related claims” provision that generally provides where two or more claims or wrongful acts are causally or logically related, they will be deemed to constitute a single claim. Importantly, these provisions typically provide that those “claims” are then deemed to have been “first made” at the time the first claim or act was committed for purposes of the policy’s claims-made and reporting requirements. Understandably, these provisions provide insurers and insureds with some clarity over the number and timing of claims that could involve multiple errors or omissions, and potentially aggregate all related claims or acts into a single policy period. While reasonable in principle, application of such provisions, especially involving large scale design and construction projects, is not always so easy.
Nova Southeastern University, Inc. v. Continental Cas. Co., 18-cv-61842 (S.D. Fla. Dec. 27, 2019), involved such an insurance coverage dispute with a design project gone wrong. DeRose Design Consultants, Inc. (“DeRose”) was hired as a structural engineer to design “ice tanks” to store and chill water for an energy efficient air conditioning facility constructed on the campus of Nova Southeastern University (“NSU”). An early water test on one of the tanks determined the walls of the ice tank deflected, leaked, and cracked when the tank was filled with water. DeRose later discovered that the problems with the ice tank were caused by a structural design error.
The first errors were discovered in early 2009, and reported under DeRose’s professional liability policy with Evanston. DeRose then created a remedial design to repair the tanks, which involved strengthening repairs. Additional leaking and an early indication of corrosion involving the Remedial Design arose as early as October 25, 2009. Several field investigation reports were prepared in 2011 and 2012 confirming these issues with the Remedial Design. A third report in February 2012, however, identified a new error involving the concrete slab under the ice tanks also designed by DeRose. The third report concluded that the concreate slab was overstressed and could not handle the loads of the ice tanks. The report also concluded, however, that the design defects in the concrete slab were “unrelated” to the original design defect of the ice tank walls or Remedial Design.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Is an Initial Decision Maker, Project Neutral, or Dispute Resolution Board Right for You?
July 14, 2016 —
David Adelstein – Florida Construction Legal UpdatesRecently, I participated in a roundtable hosted by JAMS with experienced South Florida construction lawyers and retired circuit court judges to discuss the pros and cons of utilizing an initial decision maker (“IDM” and also referred to as a project neutral) or a dispute resolution board (“DRB”) to resolve disputes on construction projects. The IDM and DRB are designed to resolve disputes, specifically claims (whether for time, money, or both), during construction to keep the project progressing forward without being bogged down by the inevitable claim. There are numerous avenues to resolve disputes without resorting to filing a lawsuit or a demand for arbitration. The thought is that dispute resolution will be facilitated by techniques designed to assist the parties with the resolution of claims during construction. While direct discussions between the parties, meetings with the executives for business decision purposes, mediations, etc., are certainly helpful, sometimes these avenues are simply not enough to truly resolve a complex claim on a construction project that occurs during construction.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Foundation Arbitration Doesn’t Preclude Suing Over Cracks
March 28, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has reversed the decision of a lower court, allowing a construction defect case to go through. In Greer v. Town Construction Company, the Greers hired Town Construction to build a home in Baton Rouge. The business relationship went sour, with disputes over “costs, change orders, workmanship, and timeliness issues.”
Town Construction filed an arbitration claim for the unpaid contract balance. In the counterclaim, the Greers made claims of mold and mildew problems, and wall cracks that they attributed to a “structural defect in the foundation.” In arbitration, Town Construction was awarded the full contract balance plus extra costs and interest, while the Greers were awarded for their structural claims.
Three years later, the Greers found additional cracks and filed a suit against Town Construction. Town Construction argued that the Greer’s lawsuit should be dismissed, as the claims had already been through the arbitration process. The district court agreed with Town Construction and dismissed the suit.
The appeals court noted that the Greers would have no ground for a suit if the arbitration was a “valid and final judgment,” and went on to note that there was no evidence in the trial record that the arbitration met this qualification. The court noted that although it was clear that both parties had agreed to the decisions of the arbiter, under Louisiana law, arbitration is not final until it has been “rendered by a court with jurisdiction over subject mater and over parties.”
The court remanded the case to the lower court, noting that “the district court is obligated to first determine whether a valid arbitration award is in existence and had been confirmed before considering the merits of the exception. The court noted that their decision “should not be read to express any opinion as to the merits of the claims or as to the propriety of damages sought in the Greer’s lawsuit.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction and Contract Issues Blamed for Problems at Anchorage Port
August 27, 2013 —
CDJ STAFFA third-party audit of the construction at the Port of Anchorage has found fault with the design provided by the engineers. In response, PND, the engineering firm involved, has claimed that it was not their design, but faulty construction of it that lead to an interruption in the construction project.
Separately, the Office of the Inspector General has called into question how MARAD, the agency which oversaw the port construction, handled the planning and contracts for the project.
Control of the project has been taken over by the Municipality of Anchorage, and they have called into question PND’s open cell sheet pile design and PND’s design of the dock infrastructure. Simpson, Gumpertz and Heger reviewed the design, comparing it to a design provided by CH2M Hill, and found that the PND design was inadequate. A contract was subsequently awarded to CH2M Hill.
Read the court decisionRead the full story...Reprinted courtesy of
Mortgagors Seek Coverage Under Mortgagee's Policy
July 19, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe mortgagor homeowners survived a motion to dismiss their claim for coverageunder the lender's property policy after their home suffered hurricane damage. Gary v. Am. Sec. Ins. Co., 2021 U.S. Dist. LEXIS 100010 (W.D. La. May 26, 2021).
Plaintiffs' home was mortgaged by Pennymac Loan Services, LLC. Pennymac held a property policy with American Security to insure its interest in the home. Plaintiffs were not named as insureds or additional insureds under the policy. Plaintiffs were identified as the borrowers under the policy on the Declarations page.
After hurricane damage to their home, plaintiffs sued American Security for coverage for the losses. American Security moved to dismiss, arguing plaintiffs were neither additional insureds nor third party beneficiaries. Lender-placed policies were designed to insure the lender's collateral whenever the borrower failed to maintain adequate insurance. The Loss Payment provisions in the policy stated that "Loss will be made payable to the named insured [Pennymac]. No coverage will be available to any mortgagee other than that shown as the named insured on the Declarations."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Texas and Georgia Are Paying the Price for Sprawl
March 15, 2021 —
Conor Sen - BloombergCities in the Sun Belt South have been needing a more modern development model for a while. That's created tensions, both economically and politically, that have only accelerated during the past year's pandemic. My colleague Noah Smith wrote a column about this specific to Texas, but it's broader than any one state and it's useful to think about how we got to this point and why these issues are relevant in 2021 in a way they weren't a generation ago.
There's an institutional reluctance to pivot away from the Sun Belt model defined by low taxes and cheap land because of how successful it was for key constituencies for decades. Coming out of World War II, there was a scramble nationwide to build more housing in response to soldiers coming home from war and pent-up demand for family formation.
The combination of the automobile as the nation's now-dominant form of transportation and the passage of the Federal Highway Act of 1956 made building out the suburbs of less-populated southern states an irresistible growth model for politicians and economic development interests alike. If it required tax breaks and fewer regulations to lure jobs and people from northern states to accelerate the process, so be it.
Read the court decisionRead the full story...Reprinted courtesy of
Conor Sen, BloombergMr. Sen may be contacted at
csen9@bloomberg.net
Waiving The Right to Arbitrate Under Federal Law
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf there is an arbitration provision in your contract that you want to enforce, you do not want to take action inconsistent with those rights as this could give rise to a waiver argument, i.e., that you waived your rights to arbitrate, particularly if the other party has been prejudiced.
Under federal policy and law, establishing waiver requires the party arguing waiver to “bear a heavy burden of proof.” U.S. f/u/b/o John Wayne Construction, G.S.A. Division, LLC v. Federal Ins. Co., 2021 WL 4526727 (M.D.Fla. 2021) quoting Stone v. E.F. Hutton & Co., 898 F.2d 1542, 1543 (11th Cir. 1990).
“To determine whether the right to arbitrate has been waived, courts apply a two part test: i) whether, “‘under the totality of the circumstances,’ the party ‘has acted inconsistently with the arbitration right’”; and ii) “whether, by doing so, that party ‘has in some way prejudiced the other party.’” Id. quoting Ivax Corp. V. B. Braun of Am., Inc., 286 F.3d 1309, 1315-16 (11th Cir. 2002). Substantial participation in litigation prior to invoking the right to arbitrate supports a party acting inconsistent with the right to arbitrate. Id. And, “‘[p]rejudice has been found in situations where the party seeking arbitration allows the opposing party to undergo the types of litigation expenses that arbitration was designed to alleviate.’” Id. quoting Morewitz v. W. of Eng. Ship Owners Mut. Prot. & Indem. Ass’n (Luxembourg), 62 F.3d 1356, 1366 (11th Cir. 1995).
Hence the heavy burden for a party to support to prove waiver– establishing both substantial participation in litigation that is inconsistent with the right to arbitrate AND prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Dog Ate My Exclusion! – Georgia Federal Court: No Reformation to Add Pollution Exclusion
September 28, 2017 —
Philip M. Brown-Wilusz - Saxe Doernberger & Vita, P.C.While schoolchildren know that the classic “the dog ate my homework” excuse doesn’t work, insurance companies are willing to try a variation of that excuse. Ace American Insurance Company (Ace), sold a property policy (the Policy) to Exide Technologies, Inc. (Exide). Exide sought coverage under the Policy for acid damage at its former battery factory. Ace denied coverage, citing to the pollution exclusion. The only problem? The Policy contained no pollution exclusion!
Exide had procured policies from other insurers for several years prior to the inception of the Policy, all of which contained pollution exclusions. Exide instructed Marsh USA Inc. (Marsh), its broker, to procure insurance “on the same or better terms and conditions.” The resulting policy contained no pollution exclusion, and Exide sought coverage under the Policy for pollution-related losses.
Read the court decisionRead the full story...Reprinted courtesy of
Philip M. Brown-Wilusz, Saxe Doernberger & Vita, P.C.Mr. Brown-Wilusz may be contacted at
pbw@sdvlaw.com