Homeowners Must Comply with Arbitration over Construction Defects
January 06, 2012 —
CDJ STAFFThe California Court of Appeals has upheld a decision by the Superior Court of Kern County that homeowners must comply with arbitration procedures in their construction defect claim. The California Court of Appeals ruled on December 14 in the case of Baeza v. Superior Court of Kern County, denying the plaintiff’s petition that the trial court vacate its order.
The plaintiffs in the case are homeowners in various developments built by Castle & Cook. The homes were sold with a contract that provided for “nonadversarial prelitigation procedures, including mediation, and judicial reference.” The homeowners made defect claims and argued that Castle & Cooke failed to comply with statutory disclosure requirements and that some of the contracts violate related statutes.
The appeals court found that there was no ground for appeal of the lower court’s order to continue with prelitigation procedures. The court noted that the plaintiffs could not seek a review of the mediation until a judgment was issued, but that then the issue would be moot. The court felt that there were issues presented that needed clarification, and so they reviewed this case. This was cleared for publication.
The court considered the intent of the legislature in passing the Right to Repair Act, noting that “under the statutory scheme, the builder has the option of contracting for an alternative nonadversarial prelitigation procedure,” as established in Chapter 4. The court noted that Chapter 4 “contains no specifics regarding what provisions the alternative nonadversarial contractual provisions may or must include.”
The plaintiffs contended that the builder was in violation of the standards set out in Section 912, however the court responded that these sections set out one set of procedures, but they concluded that “if the Legislature had intended the section 912 disclosure provisions…it could have made the requirements applicable to all builders by locating them in a section outside Chapter 4.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Is a Violation of a COVID-19 Order the Basis For Civil Liability?
April 20, 2020 —
Robert Devine, James Burger & Douglas Weck - White and WilliamsThinking about ignoring your state or local COVID-19 shutdown orders? Think again. Social-distance measures may create a new source of liability for businesses operating during the COVID-19 pandemic. Infection-based litigation is normally limited to businesses operating in the healthcare sector. But, social-distancing measures to stop the spread of infection may expand that litigation to other sectors.
State and local governments across the country are taking extraordinary measures to combat the spread of COVID-19, a novel coronavirus that can cause life-threatening respiratory illness. Those measures encourage and even mandate “social distance” between people to limit physical transmission of the virus.
Hard-hit states like New York, New Jersey, Pennsylvania and California have been aggressive in their responses, shuttering businesses, confining people to their homes, and requiring people to stay six feet apart. Common mandates include: quarantines, business and school closures, stay-home orders, curfews, travel restrictions, occupancy limits and physical-distance mandates, among other things.
Reprinted courtesy of White and Williams attorneys
Robert Devine,
James Burger and
Douglas Weck
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Mr. Weck may be contacted at weckd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Window Manufacturer Weathers Recession by Diversifying
October 28, 2011 —
CDJ STAFFAmerican Openings, a Tuscon-based window manufacturer, has responded to the loss of its sales of windows for new home construction by moving into new markets. The Arizona Daily Star reports that American Openings used to see providing windows for new homes as half their business. Now, Tom Regina, the founder and president says “single family is just dead.”
Their products are insulated windows, designed to comply with Energy Star standards. Without new homes being built, now the company is focusing on homeowners and building owners looking for more energy efficient windows. As the windows have two or three panes and special coatings, homeowners using them are eligible for tax credits.
One of their newer products combines their energy-saving coatings with “break resistant” glass. The article notes that the windows repel “all but the most determined burglars.” However, the company is still awaiting special equipment to cut the glass.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Supreme Court Holding Impacts Allocation of Damages in Cases Involving Successive Tortfeasors
March 28, 2022 —
Thomas Regan & Karley Kamaris - Lewis BrisboisNewark, N.J. (March 21, 2022) - Late in 2021, the Supreme Court of New Jersey addressed the issue of allocating damages in personal injury cases in which the plaintiff asserts claims against successive tortfeasors, such as medical malpractice in the treatment of a slip and fall injury caused by negligence. The decision in Glassman v. Friedel, 249 N.J. 199 (2021) overruled and replaced the long-held principles established in Ciluffo v. Middlesex General Hospital, 146 N.J. Super. 478 (App. Div. 1977) regarding successive liability. Ciluffo held that, when an initial tortfeasor settles before trial, the non-settling defendants in a successive tort were entitled to a pro tanto credit for the settlement amount against any damages assessed against them. The Superior Court of New Jersey Appellate Division in 2020, and the Supreme Court of New Jersey last year, abandoned that framework for one more consistent with statutory contribution law in the Garden State.
In Glassman v. Friedel, 465 N.J. Super. 436 (App. Div. 2020), the Appellate Division held that the application of the principles in Ciluffo in a negligence case has no support in modern jurisprudence, thus limiting its application. It rejected the holding in Ciluffo in light of the state legislature’s enactment of the Comparative Negligence Act, which requires juries to apportion damages between successive events and apportion fault among the parties responsible for each event. The appellate division went on to hold that a non-settling, successive tortfeasor may present proofs at trial as to the negligence of the settling tortfeasor, and that the burden of proof as to the initial tortfeasor’s negligence being the proximate cause of the second causative event indeed lies on the non-settling defendant. In sum, the appellate division in Glassman established steps the jury can use to determine successive tortfeasor liability, but largely treated it as one, attenuated incident.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Senator Ray Scott Introduced a Bill to Reduce Colorado’s Statute of Repose for Construction Defect Actions to Four Years
January 21, 2015 —
David M. McLain – Colorado Construction LitigationFor those of you reading this blog who are familiar with Colorado’s law as it pertains to construction defect actions, which I assume to be anyone reading this blog as it does not seem to get much random traffic, you are probably aware that the statute of repose applicable to construction defect actions in Colorado is generally thought of as being six plus two years. Specifically, C.R.S. § 13-80-104 states, in pertinent part:
(1)(a) Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Examination of the Product Does Not Stop a Pennsylvania Court From Applying the Malfunction Theory
June 28, 2021 —
Gus Sara - The Subrogation StrategistPennsylvania recognizes the malfunction theory in product liability cases. This theory allows a plaintiff to circumstantially prove that a product is defective by showing evidence of a malfunction and eliminating abnormal use or reasonable, secondary causes for the malfunction. The malfunction theory is available to plaintiffs as an alternative to proving a traditional strict product liability case in those circumstances where direct evidence of a product defect is not found. In Pa. Nat’l Mut. Cas. Ins. Co. v. Sam’s East, Inc., 727 MDA 2020, 2021 Pa. Super. Unpub. LEXIS 752, the Superior Court of Pennsylvania (Superior Court) considered whether the plaintiffs could avail themselves to the malfunction theory if the plaintiffs’ expert was able to examine the product.
The Sam’s East, Inc. case arose from a February 2015 fire at the residence of Gerald and Michelle Thompson (the Thompsons). The fire caused injuries to the Thompsons, as well as significant damage to their residence. Pennsylvania National Mutual Casualty Insurance Company (Insurer) provided homeowners insurance coverage for the property and made payments to the Thompsons as a result of the fire. Insurer retained a fire investigator to investigate the origin and cause of the fire. The fire investigator determined that the fire originated at an electric space heater that was purchased from defendant Sam’s East, Inc. (Sam’s East) in December 2011. Insurer and the Thompsons filed a lawsuit against Sam’s East in early 2017 for their respective damages.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Architects Should Not Make Initial Decisions on Construction Disputes
July 05, 2023 —
Bill Wilson - Construction Law ZoneA common provision often deleted from the standard form AIA documents is the provision in the AIA A201 General Conditions requiring an Initial Decision Maker (IDM) for claims between the contractor and owner. In the A201, the contracting parties have the option of naming their own IDM for the project. If an IDM is not selected (which is typically the case) the architect serves this role by default. While it is in all parties’ best interests to resolve disputes quickly and efficiently, using the architect as the IDM is not the best way to achieve such a resolution.
Several reasons work against using the architect as the IDM. Contractors typically don’t trust architects to be impartial in resolving disputes because the architect is paid by the owner. Most architects don’t have the temperament or any training to facilitate dispute resolution. An architect’s “initial decision” could even drive the parties further apart and lead to further issues later in the project. The architect may also be perceived to be part of the problem that led to the dispute in the first place. Also, many architects simply prefer to avoid serving the thankless role of an IDM altogether. Lastly, inserting the architect into the dispute resolution process as a required IDM adds an additional unnecessary step to dispute resolution, which can delay the overall procedure.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com