Do Engineers Owe a Duty to Third Parties?
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorA Texas Court of Appeals, in USA Walnut Creek, DST v. Terracon Consultants, Inc., recently ruled that an engineer owed a duty to the buyer of an apartment complex, even though the engineer had no contractual relationship with the buyer. This is an expansion of the duty professionals owe on construction projects and could signal a change in the law.
In the case, Walnut Creek purchased a three year old apartment complex. A few years after taking possession, Walnut Creek noticed problems with the apartments, including cracking foundations, walls, breaking windows, and out of square door frames. Walnut Creek sued the developer and general contractor, alleging construction defects. The developer claimed that the engineer, Terracon, was at fault and Walnut Creek added Terracon to the lawsuit, asserting that Terracon was negligent in performing engineering services during construction. Terracon asked the court to dismiss the claim, arguing that it did not owe a duty to Walnut Creek. Walnut Creek in turn argued that engineers do owe a duty to subsequent owners. The trial court dismissed the case against the engineer and Walnut Creek appealed.
The appellate court reversed the trial court, finding that the engineer did owe a duty to subsequent purchasers. The court seemed persuaded by the allegations that the engineer actually created the construction defects which were the basis for the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Mediating Contract Claims and Disputes at the ASBCA
December 20, 2021 —
Brian Waagner - Construction ExecutiveThe Contract Disputes Act establishes the formal process for resolving nearly all claims and disputes that arise under federal government contracts. It is the source of the requirement that contractors certify claims in excess of $100,000, the contracting officer’s final decision and the deadlines for bringing a dispute to the court of federal claims or an agency board of contract appeals.
It is also the source of the federal government’s authority to use mediation and other forms of alternative dispute resolution. Here are six key factors contractors should know about mediating contract claims and disputes at the Armed Services Board of Contract Appeals (ASBCA).
1. The Parties Control the Parameters of ADR Proceedings
Many commercial contracts and court rules require mediation of every dispute. There is no settlement meeting, mediation or any other type of mandatory ADR proceedings in cases brought to the ASBCA. The parties control the process, and they may adopt any approach to ADR that they believe will be effective. Mediation is nevertheless voluntary. Without the agreement of both parties, it won’t happen.
Reprinted courtesy of
Brian Waagner, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
3D Printing Innovations Enhance Building Safety
October 07, 2019 —
Mahmut Ekenel & Melissa Sanchez - Construction ExecutiveThe mention of 3D printing alone is enough to get people excited, often conjuring images of a desktop console that can download and create three dimensional objects such as prototypes, or mechanical parts. And yet, in recent years the technology has given way to a slight impatience, as people begin to wonder how and when it will have a direct impact on both their lifestyles and their businesses.
The construction industry has been quick to take advantage of these innovations, and the effects are tangible, especially regarding building safety. The 3D construction technology allows for several key advantages in terms of faster construction times, uncompromised quality of construction and lower costs—allowing for affordable dwellings to be quickly built for people in need.
These advantages also lead to safety improvements during the building process. The ability to accelerate construction time without requiring an increase in labor results in a fewer construction-related workplace injuries and a reduction in material waste, making it an environmentally friendly construction method as well.
ICC-Evaluation Service (ICC-ES), a subsidiary of the International Code Council (ICC) which develops model codes and standards (i.e. International Building Code, International Residential Code) and delivers a wide array of building safety services, has taken the lead on developing acceptance criteria to address building code compliance of 3D printed construction. Currently, 3D construction technology is not within the provisions of the International Building Code (IBC) or International Residential Code (IRC). The acceptance criteria introduces new compliance measures for interior and exterior 3D printed concrete walls (with and without structural steel reinforcement), load-bearing and non-load-bearing walls, and shear walls in one-story, single-unit, residential dwellings. The 3D walls are constructed by printing two outer layers of 3D concrete and then filling the core with 3D concrete to form a solid wall.
Reprinted courtesy of
Mahmut Ekenel & Melissa Sanchez, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Ekenel may be contacted at mekenel@icc-es.org
Ms. Sanchez may be contacted at msanchez@icc-es.org
Read the court decisionRead the full story...Reprinted courtesy of
Montrose III: Vertical Exhaustion Applies in Upper Layers of Excess Coverage
May 18, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Montrose Chemical Corp. of Cal. v. Superior Court (No. S244737, filed 4/6/20) (Montrose III), the California Supreme Court held that, as between excess insurers at differing levels of coverage, a rule of “vertical exhaustion” or “elective stacking” applies, whereby the insured may access any excess policy once it has exhausted other excess policies with lower attachment points in the same policy period. The Court limited the rule to excess insurance, stating that “[b]ecause the question is not presented here, we do not decide when or whether an insured may access excess policies before all primary insurance covering all relevant policy periods has been exhausted.”
Montrose manufactured the insecticide DDT in Torrance from 1947 to 1982. In 1990, the state and federal governments sued Montrose for environmental contamination and Montrose entered into partial consent decrees agreeing to pay for cleanup. Montrose claimed to have expended in excess of $100 million doing so, and asserted that its future liability could exceed that amount.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Aarow Equipment v. Travelers- An Update
January 16, 2024 —
Christopher G. Hill - Construction Law MusingsPreviously here at Musings, I discussed the application of pay if paid clauses and the Miller Act. The case that prompted the discussion was the Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co. case in which the Eastern District of Virginia Federal Court determined that a “pay if paid” clause coupled with a proper termination could defeat a Miller Act bond claim. However, as I found out a couple of weeks ago at the VSB’s Construction Law and Public Contracts section meeting, the 4th Circuit Court of Appeals reversed and remanded this case in an unpublished opinion (Aarow Equipment & Services, Inc. v. Travelers Casualty and Surety Co.)
In it’s opinion, the 4th Circuit looked at some of the more “interesting” aspects of this case. One of these circumstances was that Syska (the general contractor) directed Aarow to construct sedimentary ponds and other water management measures around the project (the “pond work”), which both agreed was outside of the scope of the work defined in their subcontract. Syska asked that the government agree to a modification of the prime contract and asked Aarow to wait to submit its invoice for the pond work until after the government issued a modification to the prime contract and Syska issued a change order to the subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Employee or Independent Contractor? New Administrator’s Interpretation Issued by Department of Labor Provides Guidance
August 04, 2015 —
Tanya Salgado – White and Williams LLPThe question of whether a worker should be classified as an independent contractor or an employee is fraught with confusion and misunderstanding for many businesses. Compounding the problem is the fact that there are a number of different tests used to determine employee status, which vary by jurisdiction and by the particular law in question. For example, the Internal Revenue Service uses the common law rules which focus on the degree of control and independence exercised by the worker. In contrast, the United States Department of Labor uses the “economic realities” test which focuses on whether the worker is economically dependent on the employer.
In an effort to help combat the confusion over proper worker classification, the United States Department of Labor (DOL) has issued a new Administrator’s Interpretation that provides a detailed explanation of the test used by the DOL to determine if a worker has been misclassified as an independent contractor. The DOL enforces the Fair Labor Standards Act (FLSA), which mandates that employees (but not independent contractors) be paid minimum wage and overtime. When a business misclassifies non-exempt workers as independent contractors, and those workers are not paid the minimum hourly wage for their labor, or are not paid overtime when they work more than 40 hours in a workweek, this violates the FLSA.
Read the court decisionRead the full story...Reprinted courtesy of
Tanya Salgado, White and Williams LLPMs. Salgado may be contacted at
salgadot@whiteandwilliams.com
Previously Owned U.S. Home Sales Rise to Eight-Month High
July 23, 2014 —
Victoria Stilwell – BloombergSales (ETSLTOTL) of previously owned U.S. homes climbed in June to an eight-month high as more listings helped prices cool, luring buyers into the market.
Sales increased 2.6 percent to a 5.04 million annual rate last month, led by gains in all four U.S. regions, figures from the National Association of Realtors showed today in Washington. The median forecast of 78 economists surveyed by Bloomberg projected sales would rise to a 4.99 million rate. Prices advanced at the slowest pace since March 2012 and inventories rose to an almost two-year high.
Historically low interest rates and smaller price increases are helping bring homeownership within reach for more Americans. A pickup in employment opportunities that lead to faster wage growth would provide an added spark for a residential real-estate market that began to soften in the middle of 2013.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Do We Really Want Courts Deciding if Our Construction Contracts are Fair?
March 19, 2015 —
Christopher G. Hill – Construction Law MusingsAs I posted recently, the Virginia General Assembly has passed, and I can see no reason why the governor won’t sign, a bill that would
essentially invalidate preemptive contractual waivers of lien rights as they relate to subcontractors and material suppliers. It does not apply to General Contractors, but it is a step in what many (including those attorneys that represent subcontractors and suppliers) believe is the right direction.
Of course, as soon as I posted last week, my friend and colleague
Scott Wolfe (@scottwolfejr) commented on that post and then
gave his two cents worth at his Zlien blog. The gist of the comments here at Musings and the post over at his blog was essentially that these contractual provisions were inherently unfair and therefore should be abolished because of both a relative disparity in leverage between the Owner or GC and the Subcontractor when it comes to negotiations and the fact that subcontractors often don’t read their contracts or
discuss them with a construction attorney prior to signing them. I hear this first of his arguments often when I am reviewing a contract after the fact and a client or potential client acts surprised that a provision will be enforced and the courts of the Commonwealth of Virginia will actually enforce them. As to Scott’s second reason, I have always warned here at Musings that
you should read your contracts carefully because they will be the law of your business relationship in the future.
The first of his two points is more interesting and in some ways more easily supported. However, where we are speaking of contracts between businesses where both sides are bound by the terms of the contract, it begs the question of whether in seeking to make contracts more “fair” we could add a layer of uncertainty that could cause more problems than it solves. Do we really want courts stepping in after the fact to renegotiate the terms of a deal that was struck months or possibly years before because one judge believes that the deal was too one sided? Do we really need such “Monday morning quarterbacking?” Is one person’s idea of “fair” better than another’s when both parties to the contract had the full ability to read, negotiate and possibly reject the deal long ago? Personally, I think that the answer to these questions is, in all but the most egregious cases or where the legislatures have stepped in adding certainty (whether to the good or bad), “No.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com