Understand the Dispute Resolution Provision You Are Agreeing To
September 20, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen negotiating a contract, do not overlook the dispute resolution provision. It is one of the more important provisions in your construction contract. This provision will come into play and have ramifications if there is a dispute, which is certainly not uncommon on a construction project.
In dispute resolution provisions in subcontracts on federal projects, it is not unusual for that provision to include language that requires the subcontractor to STAY any dispute that concerns actions or inactions of the owner pending the resolution of any dispute between the owner and prime contractor relating to that action or inaction. A provision to this effect should be included for the benefit of the prime contractor. For instance, the provision may say the subcontractor agrees to stay any such claim against the prime contractor or prime contractor’s surety pending the outcome of any pass-through claim (or otherwise) submitted under the Contract Disputes Act.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Understanding the Details: Suing Architects and Engineers Can Get Technical
November 02, 2017 —
Steven M. Cvitanovic & Stephen M. Tye - Haight Brown & Bonesteel LLPBefore suing an architect or engineer for professional negligence, a plaintiff must obtain a “certificate of merit” (“Certificate”) under Code of Civil Procedure section 411.35. Boiled down to the basics, the Certificate declares that the attorney consulted with and received an opinion from an expert that a reasonable and meritorious case exists against said design professional. The Certificate must be filed before serving the complaint on any defendant, but can be filed within 60 days under certain circumstances. This rule was recently analyzed against another long-standing rule in California, known as the “relation-back doctrine.” Under the relation-back doctrine, a court will deem a later-filed pleading, such as an amended complaint, to be deemed filed at the time of an earlier complaint.
In Curtis Engineering Corp. v. Superior Court of San Diego County, No. D072046, (Cal. Ct. App. 10/23/17), the Fourth Appellate Court considered the interplay between section 411.35 and the relation-back doctrine, holding that a Certificate filed more than 60 days after filing the original pleading does not relate back to the filing of the original pleading.
Reprinted courtesy of
Steven Cvitanovic, Haight Brown & Bonesteel LLP and
Stephen Tye, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction-Industry Clients Need Well-Reasoned and Clear Policies on Recording Zoom and Teams Meetings
June 19, 2023 —
Stu Richeson - The Dispute ResolverThe use of Zoom, Microsoft Teams, and similar communication platforms has become increasingly common in the construction industry. While these platforms can greatly facilitate communication between project participants, they potentially create a source of ESI – electronically stored information – that must be understood and considered by the businesses using those systems.
Businesses using Zoom, Microsoft Teams, and similar platforms should have policies in place to address whether and why to record video conferences, how long to preserve any recorded meetings, and retention policies for instant messaging systems. The failure to adopt appropriate policies could prove quite costly in any future litigation or criminal investigation.
Federal Rule of Civil Procedure 37(e) sets out the duty to preserve ESI and provides significant penalties for failing to do so once litigation is anticipated. It is important to note: there is generally no obligation to create ESI, such as recording Zoom or Teams meetings. At the same time, if the ESI is created but litigation is not anticipated, businesses are generally free to establish their own retention policy for that ESI. However, once litigation is anticipated, potential litigants have the obligation to preserve the ESI and, in connection therewith, to conduct a reasonable search for relevant information (to ensure its proper preservation).
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Revisiting OSHA’s Controlling Employer Policy
December 21, 2017 —
Wally Zimolong - Zimolong LLCThe United States Court of Appeals for the 5th Circuit has been asked to review OSHA’s twenty year old “controlling employer” policy. As many contractors are surprised to learn, under OSHA’s controlling employer policy, you can be given an OSHA citation even when your own employee is not exposed to the alleged hazard.
A. The Controlling Employer Policy
OSHA’s current controlling employer policy has been effective since 1999. That policy applies to multi-employer worksites, which means virtually all construction sites. Under the policy, OSHA can cite the creating, exposing, correcting, or controlling employer. A creating employer is one who creates the hazard to which workers are exposed. The exposing employer is one who permits his employees to be exposed to the hazard, whether it created the hazard or not. The correcting employer is one who is responsible with correcting known hazards. Finally, the controlling employer is one “who has general supervisory authority over the worksite, including the power to correct safety and health violations itself or require others to correct them.” Most general contractors and CM’s are controlling employers.
Under OSHA’s policy, a contractor’s OSHA safety obligations hinges on whether it is a creating, exposing, correcting, or controlling employer. The creating, exposing, and correcting contractors obligations are fairly straightforward. However, the controlling contractors obligations are more nuisanced.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Another Las Vegas Tower at the Center of Construction Defect Claims
November 07, 2012 —
CDJ STAFFAccusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¼ inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the court decisionRead the full story...Reprinted courtesy of
Strategic Communication Considerations for Contractors Regarding COVID-19
April 06, 2020 —
Sarah Skidmore - Construction ExecutiveThe COVID-19 is a worldwide wildcard. Around the globe, organizations are forced to communicate with a wide variety of audiences. Audiences range from employees to customers and vendors—and more. A pandemic of this nature is new for the modern globalized workforce. Societies realize the breadth of international influence involved in a single supply chain now more than ever before. Domestically based organizations realize their place in the larger global system—and the construction industry is a perfect example.
Here are key questions for leaders to ponder.
1. Who are your audience groups?
In a wildcard situation, organizations are often tasked with communicating to many different audience groups and stakeholders. So, take some time to think beyond the groups that come top-of-mind such as customers, vendors, partners and owners.
- Does the organization have any community-based events on the calendar?
- Does the organization have professional development sessions on the calendar?
- Does the organization have planned maintenance or facilities work scheduled with third parties?
- Does the organization have interns or apprenticeship programs with local colleges?
Reprinted courtesy of
Sarah Skidmore, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Skidmore may be contacted at
sarah@skidmore-consulting.com
War-Torn Ukraine Looks to Europe’s Green Plans for Reconstruction Ideas
July 18, 2022 —
Laura Millan Lombrana - BloombergUkrainian officials and architects are already thinking about how to rebuild cities torn by the Russian invasion in a way that is also respectful to the environment and helps fight climate change.
Mariupol city hall officials have started to assess the damage caused by Russian shelling as a first step to rebuild the city once the war is over, Deputy Mayor Sergei Orlov told an audience in Brussels at the New European Bauhaus festival, running through Saturday in several European cities. A coalition of Ukrainian and international experts in urban planning, heritage, energy and the circular economy are working toward the same goal.
“We will reconstruct Ukraine, we have to do that and we will do that,” European Commission President Ursula von der Leyen said at the festival. “It’s not only in our interest, it’s our moral obligation to do that — but when we are reconstructing Ukraine, let’s do it the right way, let’s do it in the spirit of the New European Bauhaus.”
Read the court decisionRead the full story...Reprinted courtesy of
Laura Millan Lombrana, Bloomberg
California’s Wildfire Dilemma: Put Houses or Forests First?
November 29, 2021 —
Jim Hinch - BloombergAs record-breaking fires blacken millions of acres in California and elsewhere in the West this year, politicians are mostly sticking to a standard script in response. President Joe Biden’s proposed budget this year includes a $500 million boost to what the White House calls “forest management” and other efforts to reduce wildfire risk. In July, California lawmakers approved $1.5 billion in similar prevention spending.
The funds are in addition to the $2 billion the federal government spends each year fighting fires — a figure twice what it was 10 years ago and roughly five times more than in the 1980s and 1990s. A study last year found that in 2018, wildfires in California caused $148.5 billion in economic damage, including $46 billion outside the state.
Roughly one in three American houses is now in what forest scientists call the wildland-urban interface, where growing cities, remote workers, second-home buyers and commuters priced out of other housing markets are often pushing into fire-prone regions. A 2017 study found that 900,000 homes in the Western U.S. worth a combined $237 billion were “at high risk for fire damage.”
Read the court decisionRead the full story...Reprinted courtesy of
Jim Hinch, Bloomberg