No Prejudicial Error in Refusing to Give Jury Instruction on Predominant Cause
November 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's judgment after the jury determined there was no coverage for a leaking pipe. Mendoza v. Pacific Spec. Ins. Co., 2024 Cal. App. Unpub. EXIS 5477 (Cal. Ct. App. Aug. 20, 2024).
The Mendoza's third amended complaint alleged their home was damaged "by overflow of water from the dwelling's plumbing system resulting from a broken pipe, which overflow undermined the structural integrity of the dwelling."
The Mendozas insured their home under a policy issued by Pacific. The policy insured the property against "sudden and accidental direct physical loss" except where expressly excluded. The Mendozas submitted a claim Pacific paid approximately $1800 for the loss and closed the claim. The amount paid did not include payment for any structural damage to the home. The Mendozas alleged that Pacific's failure to conduct a full and fair investigation into the structural damage and its inadequate payment of benefits was a breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Resolving Subcontractor Disputes with Pass-Through Claims and Liquidation Agreements
May 13, 2024 —
Stephanie Cooksey - Peckar & Abramson, P.C.Imagine a project where you are unable to reach final completion due to an unresolved subcontractor claim. If the project owner is responsible for the claim, and both the owner and subcontractor are entrenched in their positions, how would you resolve this dispute?
The default option is a three-party lawsuit where the subcontractor sues you in your capacity as general contractor. By denying the claim, you bring the owner into the lawsuit as a liable party to the subcontractor’s claim. This option is efficient from the judicial system’s perspective, as it means one lawsuit instead of two. The subcontractor cannot sue the owner since the two have no contract between them. Thus, the subcontractor’s recourse is limited to suing the contractor. In the three-party lawsuit, you argue that if the subcontractor prevails in its claim against you, the owner is liable. If the owner successfully defends against the claim, the subcontractor takes nothing.
Putting judicial economy aside, it may not make economic sense for contractors to have a lawyer involved in litigating a case where they have no skin in the game. Fortunately, there is a better option than the three-party lawsuit on multi-party construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Cooksey, Peckar & Abramson, P.C.Ms. Cooksey may be contacted at
scooksey@pecklaw.com
How the Science of Infection Can Make Cities Stronger
November 13, 2023 —
Carlo Ratti & Michael Baick - BloombergEarlier this year, a group of European researchers published a study with a scorching conclusion: As climate change makes heat waves more prevalent across the continent, the city most vulnerable to excess heat deaths is not a warm southern metropolis, but the relatively cool city of Paris.
Why? In part, the reason is that historically hotter cities have developed adaptations for dealing with extreme heat, from the shady architecture of Palermo to the siestas of Madrid. That leaves Paris at the bottom of a deadly learning curve.
This is just one urgent example of why cities need to talk. The world has an incredible stockpile of effective urban policies, but the best ideas are not being adopted quickly or widely enough. Covid-19 taught us all how to slow the spread of viruses: wear masks, avoid large gatherings and take vaccines. To speed the spread of good ideas, we need to take the opposite tack by making urban solutions go viral.
Reprinted courtesy of
Carlo Ratti, Bloomberg and
Michael Baick, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Bright-Line Changes: Prompt Payment Act Trends
September 16, 2024 —
Stephanie L. Cooksey - Peckar & Abramson, P.C.Untimely payment by the owner for contract work and additional work on construction projects can place an unfair financial burden on contractors and subcontractors. Most states have attempted to eliminate or mitigate this inequity in construction contracting through Prompt Payment Acts that govern payment deadlines and provide remedies for untimely payment. This article addresses the legislative trends aimed at minimizing the risk of non-payment, overdue payment, and withholding retainage in favor of downstream parties to a construction contract.
Fortifying Contractor Protections with “Bright-Line” Language
Over the last decade, states have been tightening prompt payment laws by replacing broad, general statutory language with bright-line rules. What is a bright-line rule? A specific or definite figure, a quantifiable marker—i.e., something owners, contractors, subcontractors, and suppliers should be aware of. Practically speaking, the more bright-line a prompt payment statute is, the greater the likelihood it will affect a construction project in your state.
A standard form construction contract, if not reviewed carefully, can create conflicts or confusion if it gives a party more leeway on payment deadlines than the applicable Prompt Payment Act. For example, consider an owner-issued Construction Change Directive (“CCD”) that requires a contractor to commence additional work immediately while a formal change order is negotiated. Consequently, a CCD can push financial burdens downstream, whether inadvertently or not, and may conflict with statutory payment deadlines. Nevertheless, an owner can be justified in its utilization of a CCD to maintain the project schedule. How should the parties competing interests be resolved?
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson, P.C.
Surfside Condo Collapse Investigators Have Nearly Finished Technical Work
March 11, 2024 —
James Leggate - Engineering News-RecordNewly analyzed evidence in the investigation into the June 2021 partial collapse of Champlain Towers South that killed 98 people in Surfside, Fla., shows that the pool deck collapsed more than four minutes before the tower itself. But investigators are still working to determine the initiating event, and aim to finish their technical work this summer.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Development in CBF Green Building Case in Maryland
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsRemember that case I discussed a while back relating to the Chesapeake Bay Foundation (CBF) building in Annapolis, Maryland? Remember how it was a lawsuit over parallams and failure of those parallams? Do you even remember what a parallam is?
Well, that case was initially dismissed upon the Defendant’s Motion for Summary Judgment because the trial court determined that CBF did not file its lawsuit within the proper time frame after notice of the potential failure of the building materials. Of course, CBF appealed to the Fourth Circuit Court of Appeals under the caption The Chesapeake Bay Foundation, Inc., et. al. v. Weyerhaeuser Company (4th Circuit).
After a great review of the facts of the case, the engineering inspections and reports at issue and the trial court’s ruling, the Fourth Circuit vacated the dismissal and remanded the case for further proceedings. The Court of Appeals reasoned that the district court jumped the gun in dismissing the lawsuit so early in the process because:
a genuine dispute exists as to whether knowledge of the water infiltration problem would have put a reasonable person on notice that the Parallams were susceptible to premature deterioration and that their PolyClear 2000 treatment would not preserve them.
In short, the court ruled that the engineering reports relating to moisture issues would have put CBF on notice of the particular issue of deterioration that was at issue in the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Congratulations to BWB&O’s 2023 Mountain States Super Lawyers Rising Stars!
August 07, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBWB&O is excited to announce Las Vegas Partners Devin Gifford and Madeline Arcellana have been selected in the 2023 Mountain States Super Lawyers list as Rising Stars for their work in Civil Litigation. To read Super Lawyers’ digital publication, please click
here.
SELECTED AS RISING STARS
Devin Gifford: 2023
Madeline Arcellana: 2023
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Avoiding 'E-trouble' in Construction Litigation
September 10, 2018 —
Judah Lifschitz - Construction ExecutiveDuring the 2016 presidential election, the FBI subpoenaed Hillary Clinton's emails after she used a private email server during her time as Secretary of State. Separately, the more recent investigation into Donald Trump’s campaign policy adviser, George Papadopoulos, resulted in scrutiny over both his email and social media.
As shown the above examples, there are damaging effects of electronically stored information in politics, but how does it impact the construction industry?
If not used carefully and properly, emails will serve as “truth serum” in court. Attorneys can simply read an email to know employees’ thoughts or actions, meaning an impulsive email or social media post will most likely come back to haunt the company. Requests for ESI are inevitable in litigation today and the production of inappropriate emails and other ESI open the door for an opposing attorney to argue that a company fosters a culture of uncouth, unprofessional and unfocused project management.
Reprinted courtesy of
Judah Lifschitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lifschitz may be contacted at
lifschitz@slslaw.com