Contractual Assumption of Liability Does Not Bar Coverage
August 27, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Michigan Court of Appeals rejected the insurer's argument that coverage was barred for the insured's contractual assumption of liability of another. Travelers Prop. Cas. Co. of Am v. Peaker Serv., Inc., 2014 WL 3605680 (Mich. Ct. App. July 22, 2014).
The contractor was hired to install an "electronic over-speed system" at the University of Michigan. The hope was that the new system would prevent the steam turbines at the central power plant from turning too quickly. The parties' contract provided,
“Section 15.18. Supplier Damage to University Property. Without regard to any other section of the Agreement, Supplier shall be responsible for the costs to return to ‘as was’ condition from any damage caused to the building, grounds, or other equipment and furnishings caused in whole or part by Supplier Personnel while performing activities arising under this Agreement.”
The contractor improperly calibrated the system, causing one of the university's turbines to operate at twice the safe operational speed, causing significant damage to the generator equipment. The university sued the contractor for more than $3 million in damages. Travelers defended, but filed a declaratory judgment action, contending that coverage did not exist because the "contractual liability" exclusion applied. Section 15.18 of the contract purportedly constituted an "assumption" of the insured's own liability, and was therefore not covered under the CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Contingency Fee Multiplier (For Insurance Coverage Disputes)
September 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe contingency fee multiplier: a potential incentive for taking a case on contingency, such as an insurance coverage dispute, where the insured sues his/her/its insurer on a contingency fee basis.
In a recent property insurance coverage dispute, Citizens Property Ins. Corp. v. Agosta, 43 Fla.L.Weekly, D1934b (Fla. 3d DCA 2018), the trial court awarded the insured’s counsel a contingency fee multiplier of two times the amount of reasonable attorney’s fees. The insurer appealed. The Third District affirmed the contingency fee multiplier.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
South Carolina School District Investigated by IRS and FBI
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFThe IRS and FBI are investigating operations of the Jasper County School District in South Carolina. According to The Post and Courier, “Assistant U.S. Attorney James May sent a letter to district officials asking them to keep financial documents, the minutes of school board meetings, employment files for top officials and all letters and emails between district employees.”
Some of the problems the school district has dealt with are “legal challenges.” One of the disputes, involved a “multi-million dollar” construction defect claim for “facilities built in 2007.” The Post and Courier reported that this made up twenty percent of the more than half a million dollars paid in legal fees by the district.
South Carolina “lawmakers are considering the Parent Empowerment Act, a bill that would allow the state's Education Department to take over districts that are mismanaged or need improvement if a majority of parents call for it,” according to The Post and Courier.
Read the court decisionRead the full story...Reprinted courtesy of
PA Superior Court Provides Clarification on Definition of CGL “Occurrence” When Property Damage Is Caused by Faulty Building Conditions
September 30, 2019 —
Anthony L. Miscioscia & Konrad R. Krebs - White and Williams LLPThe standard for an “occurrence” under a commercial general liability (CGL) insurance policy has been addressed on several occasions by Pennsylvania courts when an insured has allegedly performed faulty workmanship on a construction project. Specifically, in Pennsylvania, a claim for damages arising from an insured’s performance of faulty workmanship pursuant to a construction contract, where the only damage is to property supplied by the insured or worked on by the insured, does not constitute an “occurrence” under the standard commercial general liability insurance policy definition. But what about the circumstance when the insured has failed to perform contractual duties where the claim is for property damage to property not supplied by the insured or unrelated to the service the insured contracted to provide? The Pennsylvania Superior Court recently addressed this question in Pennsylvania Manufacturers Indemnity Co. v. Pottstown Industrial Complex LP, No. 3489 EDA 2018, 2019 Pa. Super. 223, 2019 Pa. Super. LEXIS 729* (Pa. Super. 2019).
Pottstown Industrial Complex arose out of an underlying dispute between a landlord and a commercial tenant who had leased space to store its product inventory. The tenant alleged that the landlord was responsible under the lease for keeping the roof “in serviceable condition in repair.” Notwithstanding this responsibility, the tenant alleged that the landlord failed to properly maintain and repair the roof, resulting in leaks and flooding during four separate rainstorms, destroying over $700,000 in inventory. The tenant specifically alleged that the floods were caused by poor caulking of the roof, gaps and separations in the roofing membrane, undersized drain openings, and accumulated debris and clogged drains.
The insurer filed a declaratory judgment action, seeking a determination that there was no coverage under a commercial general liability policy issued to the landlord. Following a motion for judgment on the pleadings, the trial court entered an order in favor of the insurer, holding that allegations of inadequate roof repairs were claims for faulty workmanship and were not covered under Kvaerner Metals Division of Kvaerner U.S., Inc. v. Commercial Union Insurance Co., 908 A.2d 888 (Pa. 2006) and Millers Capital Insurance Co. v. Gambone Brothers Development Co., 941 A.2d 706 (Pa. Super. 2007).
Reprinted courtesy of
Anthony Miscioscia, White and Williams LLP and
Konrad Krebs, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Krebs may be contacted at krebsk@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Unthinkable Has Happened. How Should Contractors Respond?
May 11, 2020 —
Bruce Orr - AEC BusinessAny construction veteran expects the economy to contract and expand. However, the global pandemic presents contractors with a challenge unlike any in recent memory.
How should they respond in an environment of such uncertainty? For some perspective, I chatted with Dr. John Killingsworth, a construction management professor at Colorado State University who has conducted extensive research on how contractors can weather economic downturns.
BRUCE ORR: John, let’s say you’re in IT or are a c-suite executive at a contracting firm. This event has occurred. What are some of the questions you should be asking right now?
JOHN KILLINGSWORTH: For starters, we have to acknowledge that the uncertainties are so tremendous that many contractors have no choice but to be reactive in the short term. They’re literally not sure whether particular job sites will be open or closed tomorrow or whether they’ll go to work next week. They’re also looking at predictions—from highly qualified statisticians, public health officials and others—that are just all over the map due to the limited nature of the data we have at hand.
Read the court decisionRead the full story...Reprinted courtesy of
Bruce Orr, AEC BusinessMr. Orr may be contacted at
bruce@pronovos.com
Timely Written Notice to Insurer and Cooperating with Insurer
June 21, 2017 —
David Adelstein - Florida Construction Legal UpdatesI harp on notifying a liability insurer in writing once a claim is asserted against you. As soon as possible. I harp on this because as an insured you want to remove any doubt or argument that the insurer was prejudiced due to a lack of timely notice.
In a recent opinion, Zurich American Insurance Co. v. European Tile and Floors, Inc., 2017 WL 2427172 (M.D.Fla. 2017), the insurer moved for summary judgment in a coverage action arguing that its insured failed to provide it timely written notice. Specifically, the insurer argued that the insured violated the clause in the liability policy that states:
2. Duties in the Event of Occurrence, Offense, Claim or Suit
b. If a claim is made or “suit” is brought against any insured, you must:
- Immediately record the specifics of the claim or “suit” and the date received; and
- Notify us as soon as practicable.
You must see to it that we receive written notice of the claim or “suit” as soon as practicable.
c. You and any other insured must:
- Immediately send us copies of any demands, notices, summonses or legal papers received in connection with the claim or “suit”;
- Authorize us to obtain records and other information;
- Cooperate with us in the investigation, settlement or defense of the claim or “suit”; and
- Assist us, upon our request, in the enforcement of any right against any person or organization which may be liable to the insured because of injury or damage to which this insurance may also apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
New York Signs Biggest Offshore Wind Project Deal in the Nation
August 06, 2019 —
Will Wade, Chris Martin, & Millicent Dent - BloombergNew York has signed the biggest-ever deals for offshore wind power in U.S. history, a key part of the state’s plan to get all of its power from emissions-free sources by 2040.
On Thursday, Governor Andrew Cuomo awarded contracts for two projects off Long Island that will total 1,700 megawatts in capacity. Equinor ASA and a joint venture between Denmark’s Orsted A/S and Massachusetts-based Eversource Energy were chosen to build the farms, which will supply enough power to light up a million homes.
Cuomo is counting on the wind projects to achieve the most aggressive clean energy goal in the U.S., and signed the state’s 100% renewable energy target into law right after announcing the wind contracts. New York’s ultimate plan is to get enough turbines erected off its shores to generate 9,000 megawatts by 2035.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade, Chris Martin, & Millicent Dent, Bloomberg
When Construction Defects Appear, Don’t Choose Between Rebuilding and Building Your Case
October 11, 2021 —
Curtis Martin - ConsensusDocsWhen construction defects occur during construction, they intensify pressure from a schedule that may already be tight. Defects must be analyzed, confirmed, removed, and replaced and this can be time consuming. Or course, a construction schedule rarely anticipates defects, demolition, and rework and the owner will still expect the project to be completed on time; however, pressing forward with immediate remediation may have unintended consequences.
Before starting demolition, consider the evidentiary doctrine of spoliation. Spoilation occurs when a party destroys or unreasonably deprives another party of evidence and courts have imposed sanctions on a party that deprives an opponent of evidence. The doctrine has historically concerned documents, but its application has extended to electronic data, and courts also apply it to building conditions in construction defects cases. So, before tearing out or fixing defective work, consider the need to allow the opposing party to inspect, test and document it.
Imagine this scenario. The concrete in a slab placed by your subcontractor shows low compressive strength results in the 28-day cylinder tests. Tearing out the slab and replacing it will put you at least a month behind schedule and you don’t want to waste any time before removing and replacing it. Nevertheless, while you’re rebuilding the defective slab, be mindful that you are also building a case. If you plan to recover the costs you incur because of the defective concrete from the responsible parties, you should allow the subcontractor (and possibly the concrete supplier and other implicated parties) to examine, preserve, and/or test the work in question. Failure to do so may subject you to spoliation sanctions and jeopardize your right to recover damages.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis Martin, Peckar & AbramsonMr. Martin may be contacted at
cmartin@pecklaw.com