Michigan Court of Appeals Remands Construction Defect Case
February 14, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter its prior decision holding there was no coverage for faulty workmanship was remanded by the Michigan Supreme Court, the Court of Appeals remanded to the trial court. Skanska United States Bldg. v. M.A.P. Mech. Contrs., 2021 Mich. App. LEXIS 7336 (Mich. Ct. App. Dec. 28, 2021). The post summarizing the Supreme Court decision is here.
Skanska USA Building was the construction manager on a renovation project at a medical center. Skanska subcontracted the heating and cooling portion of the project to defendant M.A.P. MAP held a CGL policy from Amerisure. Skanska and the medical center were named as additional insureds.
MAP installed a steam boiler and related piping for the heating system. When completed, the heating system did not function properly. MAP installed some of the expansion joints backwards, causing damage to concrete, steel, and the heating system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Supreme Court Building Opening Delayed Again
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFSI Live reported that the opening of the new state Supreme Court building in St. George, New York is delayed again due to problems with the air-conditioning and elevator systems. Delay, however, is not new to this project, which was originally expected to be completed over a decade ago.
Initial delay was introduced “with the finding of remains from a 19th-century burial ground at the site, a former municipal parking lot, and more recently, with construction set-backs and other tie-ups,” according to SI Live.
When completed, the new “building will boast 14 courtrooms, jury assembly, hearing and deliberation rooms, judges' chambers and court offices. There will also be holding cells for prisoners.”
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Information and Resources
May 04, 2020 —
Richard H. Glucksman, Esq. & Brian D. Kahn, Esq. – Chapman Glucksman Dean & Roeb BulletinINTRODUCTION
The current COVID-19 health crisis has greatly impacted nearly every aspect of our business and personal lives. The constant flow of rapidly evolving, and often contradictory information creates its own challenges for those who are responsible for ensuring compliance with relevant regulations and best practices while still moving forward with their business and family activities.
This bulletin differs from most Chapman, Glucksman, Dean & Roeb bulletins in that it does not highlight a recent case, statute or a single development, but rather acts as a resource and “links” to provide you with needed information and to simplify your search for critical information during this unusual and challenging time.
CIVIL LITIGATION: CLOSURES AND RESTRICTIONS
The State and Federal Court systems in California have drastically reduced their operations. The Governor issued Executive Order N-38-20, this suspends certain limitations on the Chief Justice’s authority, making it possible for orders to be issued adapting the Court’s operations to address the COVID-19 health crisis. As of this time, the most recent statewide order from the Chief Justice is the March 30, 2020 Order which allows Courts to utilize remote technology when possible. The March 30, 2020 Order also clarifies a prior Order suspending all trials for 60 days. As many of you are aware, civil trials in California must commence within five years of the initiation of the action, this is commonly referred to as the “five year rule”. While the five year time period was initially extended by the Chief Justice for 60 days, the Judicial Council subsequently adopted a series of Emergency Rules, including one which extends this to six months for all civil actions filed on or before April 6, 2020. The Judicial Council also adopted rules tolling the statutes of limitation for civil causes of action are tolled from April 6, 2020 to 90 days after the state of emergency has ended.
In addition to the statewide orders and rules, counties have enacted their own rules. Los Angeles Superior Court, for instance, has closed some locations while others remain open on a limited basis. On March 17, 2020 an Order was issued limiting the Court to “essential functions” through April 16, 2020. However, on April 15, 2020, a further Order extended the closure through May 12, 2020. While truly urgent Ex Partes may go forward, all regularly set hearings will be continued until after June 22, 2020. Trials will begin after June 22, 2020 with non-priority trials anticipated to start in later August or September. Notably, any deadlines imposed by current trial or hearing dates still stand until the specific dates are continued.
As with other aspects of the COVID-19 health crisis, the impact upon Civil Litigation continues to evolve, for the most up to date information we include the following links to the California Courts. The first page includes links to all the State and County Orders, the second page is for the Judicial Council Rules.
Links:
https://newsroom.courts.ca.gov/news/court-emergency-orders-6794321
https://newsroom.courts.ca.gov/news/judicial-branch-emergency-actions-criminal-civil-and-juvenile-justice
STATE AND LOCAL STAY AT HOME ORDERS
The State of California declared a state of emergency on March 4, 2020. On March 13, 2020 the President declared a national state of emergency. On March 19, 2020 Governor Newsom issued Executive Order N-33-20, also known as the “Stay at Home” order. This orders all Californian’s to stay at home, unless they are part of an essential businesses are exempt which generally includes construction and insurance. Generally, Californians are allowed to run essential errands, but they are not to congregate with those outside of their household.
In addition to the State, many cities and counties have enacted additional orders regarding whether certain types of businesses can remain open, use of parks, trails and other public amenities as well as what type of protective measures must be adhered to such as covering your face in public. As with Civil Litigation, the State and Local Government regulations continue to evolve. A link to the State’s COVID-19 page is below and we also encourage you to check your local City and County sites for additional information.
https://covid19.ca.gov/
BUSINESS AND FINANCIAL GUIDELINES
The impact of COVID-19 is unprecedented. While “essential businesses” may remain open for customers, steps must be taken to protect the health of both employees and customers. There are both State and, in many instances, Local Government regulations addressing these precautions. In addition to taking safety measures to protect the health of all involved, there are a multitude of financial concerns to be addressed. While most people have already heard about the moratorium on residential and commercial evictions, this does little to address how property owners will receive funds to pay their financial obligations, how tenants can pay their other obligations, how either can make payroll and most importantly, how employees who can no longer work due to their “non-essential” business being closed can put food on their tables.
The Coronavirus Aid, Relief, and Economic Security Act (the “CARES” act) may provide financial relief for many business by means of loans, some of which may be forgivable, and tax credits. The CARES act also modifies the Family Medical Leave Act (“FMLA”) to provide paid leave for those who cannot work due to COVID-19 as well as other benefits. The IRS has extended the deadline to file and pay taxes to July 15, 2020. Additionally, there are other Federal and State benefits which may be available for those whose jobs are impacted.
The financial impacts of COVID-19 are far reaching and continue to evolve. The Department of Insurance ordered insurance companies to return premiums for at least the months of March and April. This applies to certain lines of insurance where the risk of loss has fallen substantially. However, business interruption, environmental and pollution claims have increased exponentially. While most such policies require some physical damage in order to trigger an occurrence, there has been some discussion of legislation deeming the COVID-19 pandemic to fulfill the physical damage requirement.
If your business has been closed or impacted by COVID-19 we encourage you to review your insurance policies and key contracts to ascertain what your rights and obligations are as well as whether you may have any coverage for your losses. Just as importantly, speak with your business partners including vendors, customers and employees to ascertain their capabilities and willingness to work through this crisis.
US Department of Labor OSHA Guidelines:
https://www.osha.gov/SLTC/covid-19/
California Labor & Workforce Development Agency Resource Page:
https://www.labor.ca.gov/coronavirus2019/
California Employment Development Department:
https://www.edd.ca.gov/about_edd/coronavirus-2019.htm
CONSTRUCTION GUIDELINES
Many of our clients are involved in the construction industry. Construction has been deemed an essential activity and is exempt from many of the “stay at home” orders but certain protections and regulations still apply. In addition to the general workplace guidelines discussed above certain jurisdictions are providing guidance as to how to provide a safe construction site workplace. We have included a link the Los Angeles Department Building and Safety guidelines below.
However, in some instances work on a project may be delayed or may not be able to progress due to the project owner stopping work or the inability of subcontractors or suppliers to continue as originally intended. In this case one should review their contracts to see what justifies delay and inability to perform by either party and the impact thereof. Contracts should also be evaluated to ascertain whether the costs associated with compliance with the new COVID-19 regulations are a recoverable cost under the contract. As with the general business discussion above, contractors should review all available insurance, including builder’s risk to ascertain the existence of possible coverage.
LA DBS guidelines:
https://ladbs.org/docs/default-source/publications/misc-publications/construction-site-guidance.pdf
SUMMARY
The COVID-19 health crisis has had and, for the foreseeable future, will have a broad and severe impact on our society. The variety of evolving regulations on the Federal, State and Local Government levels make it challenging to comply, especially for businesses in operation. There are also a variety of resources available to help ensure compliance with these regulations as well as the financial and physical viability of our communities’ companies and employees. Please do not hesitate to contact us if you need any assistance in navigating these rules and resources.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean & Roeb and
Brian D. Kahn, Chapman Glucksman Dean & Roeb
Mr. Glucksman may be contacted at rglucksman@cgdrlaw.com
Mr. Kahn may be contacted at bkahn@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Expands Policyholders’ Ability to Plead and Seek Consequential Damages
February 27, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a huge win for policyholders, a New York appellate court, in D.K. Property, Inc. v National Union Fire Insurance Company of Pittsburgh, Pa., held that an insured need not provide a detailed factual description or explanation for why consequential damages are recoverable at the pleading stage. Rather, an insured’s complaint must only (i) specify the types of consequential damages claimed; and (ii) allege that those damages reasonably were contemplated by the parties prior to contracting.
Here, D.K. Property’s building was damaged as a result of construction on an adjoining building, and it timely filed a claim with National Union under a policy that covers “direct physical loss or damage to” the building. National Union neither paid the claim nor disclaimed coverage. Instead, according to D.K. Property, National Union made unreasonable and increasingly burdensome information demands over a three-year period, which it alleges was a “tactic” to make pursuing the claim so expensive that D.K. Property would abandon the claim. As a result of the delay, D.K. Property alleges the structural damage to its building has worsened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
$1.9 Trillion Stimulus: Five Things Employers Need to Know
March 15, 2021 —
Matthew C. Lewis & Rana Ayazi - Payne & FearsOn March 11, 2021, President Biden signed H.R.1319 - American Rescue Plan Act of 2021 (“Rescue Plan”) into law—a $1.9 trillion stimulus bill. Here are five things every employer should know about the bill.
1. FFCRA Tax Credits Have Been Extended
The Rescue Plan extends the Families First Coronavirus Response Act (FFCRA) tax credit provisions—again—through September 30, 2021. (The ability to recoup the cost of FFCRA leave was previously extended in December 2020 through March 31, 2021: See related article here. Employers that opt to voluntarily provide FFCRA leave will be credited 100 percent for all qualifying wages paid under the FFCRA.
Any employer already providing FFCRA-like leave to employees under state, county, and/or local paid sick leave ordinances, especially if their business is located in California (e.g.,
Cal/OSHA’s COVID-19 Prevention Emergency Temporary Standards) should consider opting to voluntarily provide FFCRA-compliant leave, as by doing so they may be able at least partially to recoup the cost of leave they are otherwise already required to provide.
Reprinted courtesy of
Matthew C. Lewis, Payne & Fears and
Rana Ayazi, Payne & Fears
Mr. Lewis may be contacted at mcl@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
Construction Delays: Which Method Should Be Used to Calculate Delay?
July 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf you need to prove and allocate construction project delays, you should engage a scheduling consultant qualified with CPM (critical path method) analysis. You should also engage counsel to assist in preserving your rights, as well as presenting and maximing your arguments for delay.
There are numerous methodologies used to quantify and allocate delay. You want to discuss the most effective analysis for your case and facts including whether you want/should use a forward-looking prospective analysis or a backward-looking retrospective analysis that factors in as-built data. In doing so, you want to make sure you understand the pros and cons of each methodology including the bases to attack the methodology that will be subject to cross-examination. The five primary CPM methodologies are as follows:
- As-Planned Versus As-Built. This methodology compares the as-planned baseline schedule to an as-built schedule reflecting progress to assign delay. An as-built schedule that reflects progress includes actual start dates, finish dates, and durations. The actual dates and durations are compared with the as-planned dates and durations on the baseline schedule to determine delay. Under this methodology, the delay impact is determined retrospectively.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Recommendations and Drafting Considerations for Construction Contingency Clauses Part III
December 27, 2021 —
Samantha Schacht & Josh Levy - Construction ExecutiveThe best contracts provide the parties with a clear allocation of risks and responsibilities, and a process for handling inevitable project challenges. Contract negotiations can enable parties to have the difficult conversations allocating risks before the start of a project. An effective negotiation, in turn, aligns the parties’ expectations and helps avoid costly disputes born out of misunderstandings of the parties’ respective rights and responsibilities on the project.
This final installment of a three-part series on contingencies in construction contracts addresses factors that should be discussed and considered when drafting a contingency clause in a construction contract with the goal of helping to set clear expectations and avoid disputes.
Part I The Best Laid Plans: Contingency in a Construction Contract explained what a construction contingency is and
Part II The Best Laid Plans: Contingency in a Construction Contract discussed the two primary schools of thought on how a construction contingency fund should be used and managed.
Reprinted courtesy of
Samantha Schacht, Construction Executive and Josh Levy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Schacht may be contacted at samantha.schacht@huschblackwell.com
Read the court decisionRead the full story...Reprinted courtesy of