Courthouse Reporter Series: Nebraska Court of Appeals Vacates Arbitration Award for Misconduct
November 18, 2024 —
Brendan J. Witry - The Dispute ResolverVacating an arbitration award is often seen as an uphill battle. Indeed, the U.S. Supreme Court has stated that “courts may only vacate an arbitrator’s decision ‘only in very unusual circumstances.’” Oxford Health Plans, LLC v. Sutter, 569 U.S. 564, 568 (2013). The Federal Arbitration Act provides limited grounds to seek the vacatur of an arbitration award. In Lund-Ross Constructors v. Duke of Omaga, LLC, ___ N.W.3d ___, 33 Neb.App.73, the Nebraska Court of Appeals found that an arbitrator’s conduct warranted the partial vacatur of the award, which granted relief to a subcontractor who filed a counterclaim after the arbitration hearing had closed.
Lund-Ross contracted with Duke of Omaha to build an apartment complex in Omaha. Lund-Ross, in turn, sub-contracted with A Raymond Plumbing. Following completion of the building, Owner withheld payment from Lund-Ross, who in turn, withheld payment from Raymond. Both Lund-Ross and Raymond filed mechanics liens and initiated suits; Raymond’s suit ultimately was dismissed for want of prosecution. Lund-Ross proceeded to arbitration with Owner, naming Raymond as a respondent. Raymond did not participate in the arbitration as a claimant at the time of the hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Expert Can be Questioned on a Construction Standard, Even if Not Relied Upon
August 07, 2022 —
Garret Murai - California Construction Law BlogIt’s not uncommon in construction defect litigation for each side retain one or more experts to give their opinion as to whether something was constructed in accordance with the standard of care. This usually results in what we legal practitioners call a “battle of the experts.”
The California Code of Civil Procedure and Evidence Code include specific provisions applicable to experts including when they must be disclosed, when and how they can be deposed, and what opinions they can render. When attempting to challenge an expert it is not uncommon for one side to argue that the other side’s expert did not consider a certain fact or certain standard in reaching his or her opinion, therefore, allowing that party to argue at trial that the expert’s opinion is somehow flawed.
However, there are also certain limitations, including a limitation restricting a party from cross-examining an expert on any scientific, technical, or professional test, treatise, journal or similar publication if the witness did not rely on such publication in arriving at or forming his or her opinion. The next case,
Paige v. Safeway, Inc. (2021) 74 Cal.App.5th 1108, involved a case of first impression: Namely, whether an expert who did not rely on a publication in forming his or her opinion can nevertheless be questioned on a publication (in this case an ASTM standard) because the publication is a “reliable authority.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Los Angeles Is Building a Future Where Water Won’t Run Out
February 28, 2022 —
Brian Eckhouse & Laura Bliss - BloombergA helicopter whisks off a rooftop in downtown Los Angeles, climbs above a thin layer of haze and soars over barren mountains past the city’s edge. Soon, scars of climatic stress are evident to L.A. Mayor Eric Garcetti and Martin Adams, general manager and chief engineer of the city’s water and power department, as they peer out the windows. Trees torched years ago by wildfire. Flats parched by sun and little precipitation.
It’s another July scorcher, days after California Governor Gavin Newsom asked residents to conserve amid one of the worst droughts on record. The crisis spans across the southwestern U.S. Outside Las Vegas, the enormous Lake Mead reservoir that feeds the Golden State as well as Nevada and Arizona plunged in June to its lowest level since 1937. In August, federal officials ordered the first-ever water cuts on a Colorado River system that sustains about 40 million people. Even after pounding holiday storms, 64% of the land in Western states was still experiencing severe to exceptional drought in January, which is on track to be the driest on record in some parts.
Reprinted courtesy of
Brian Eckhouse, Bloomberg and
Laura Bliss, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
NY Court Holds Excess Liability Coverage Could Never be Triggered Where Employers’ Liability Policy Provided Unlimited Insurance Coverage
February 28, 2018 —
Theresa A. Guertin and Samantha M. Martino - SDV Blog In a potentially significant development in New York insurance law, a recent appellate level decision held that an excess liability policy was not obligated to provide coverage where the underlying employer’s liability policy provided unlimited coverage pursuant to New York regulations.
The
Arthur Vincent & Sons Construction, Inc. v. Century Surety Insurance Co.1 case arose out of an underlying wrongful death claim. Fordham University hired Arthur Vincent and Sons Construction, Inc. (“AVSC”) to install a new roof on its Lewis Calder Center. As is typical of most construction contracts, AVSC agreed to indemnify the University against any claims arising out of its negligence, and to name the University as an additional insured on its commercial general liability policy. AVSC was insured by three policies: (1) a worker’s compensation and employer’s liability policy issued by Commerce and Industry Insur¬ance Company (“CIIC”); (2) a primary CGL policy issued by Century Surety Insurance Company (“Century”); and (3) an excess liability policy issued by Admiral Insurance Company (“Admiral”).
Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita, P.C. and
Samantha M. Martino, Saxe Doernberger & Vita, P.C.
Ms. Guertin may be contacted at tag@sdvlaw.com
Ms. Martino may be contacted at smm@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Stop by BHA’s Booth at WCC and Support the Susan G. Komen Foundation
May 12, 2016 —
Beverley BevenFlorez-CDJ STAFFIf you’re attending the annual West Coast Casualty Seminar at the Disneyland Hotel today and tomorrow, be sure to stop by the Bert L. Howe & Associates, Inc., booth and
Sink a Putt for Charity. This year, participant’s efforts
on the green will help benefit the Susan G. Komen Race for the Cure. As in years past, sink a putt in the BHA golf challenge and win a $25 Best Buy gift card, and for every successful putt made, BHA will make a $25 cash donation in the golfer’s name to the Susan G. Komen Foundation.
New this year, BHA is hosting three
Championship Rounds and during those periods BHA will double their charitable contributions. For every ATTEMPTED (sink or miss), BHA will make a $50 donation to Susan G. Komen, and for every putt MADE (sunk), the golfer will also win a $50 Best Buy gift card.
Championship rounds are going on today between the times of 10:30am-10:45 am, 3:00pm-3:30pm, and 5:30pm-6:30pm. So be sure to get over to the BHA booth for your chance to support important cancer research as well as possibly taking home a nice gift card for yourself.
BHA also wishes to thank Dave Stern for all of his hard work for the construction defect community in putting together this
must go to seminar and for promoting such worthwhile charities each year.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Interpleader Dealing with Competing Claims over Undisputed Payable to Subcontractor
September 28, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhat do you do if you are holding undisputed money owed to a subcontractor? Well, you make an effort to pay it or tender it! Right? I am never a fan of a client holding undisputed sums without a legitimate contractual basis.
There are circumstances, however, where the effort to pay an undisputed payable is not so easy. In fact, it is challenging, as in the below case example where the subcontractor filed for an Assignment for the Benefit of Creditors (referred to as an “ABC”). An ABC, in a nutshell, allows an insolvent entity to file an insolvency action in state court governed by state law and choose its assignee (versus a federal bankruptcy action governed by federal law where a trustee is appointed). One major difference is that there is no automatic stay in an ABC as there is in a federal bankruptcy action. Thus, the insolvent entity can still be sued, but, while that entity is in an ABC, there are many creditors that will not be able to enforce a judgment. (See Florida Statute Ch. 727).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Takeaways From Schedule-Based Dispute Between General Contractor and Subcontractor
September 09, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., Case 1:19-cv-23059-KMW (S.D.Fla. July 22, 2024), provides valuable takeaways on schedule-based disputes between a general contractor and subcontractor on a high-rise project.
In a nutshell, the general contractor’s original project schedule was abandoned due to project delays and the project wasn’t being built by any updated project schedule. The subcontractor claimed the general contractor was mismanaging the schedule putting unreasonable manpower and supervision constraints on it, i.e., it was working inefficiently. A bench trial was conducted and the Court found in favor of the subcontractor’s arguments. The Court found the general contractor had unrelated delays and that work activities were no longer methodical but, simply, piecemeal demands. The Court also rejected any inadequate manpower arguments finding the subcontract did not place any manpower requirements on the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Holds That One-Year SOL Applies to Disgorgement Claims Under B&P Section 7031
November 23, 2020 —
Garret Murai - California Construction Law BlogWe’ve talked before about Business and Professions Code section 7031 which courts have referred to as “harsh[ ],” “unjust[ ]” and even “draconian.” Under Section 7031, a contractor performing work requiring a contractor’s license, but who doesn’t: (1) is prohibited from suing to recover payment for work performed; and (2) is required to disgorge all money paid by the project owner for work performed. This is true even if the project owner knew that the contractor was unlicensed, the contractor was only unlicensed during part of the time it performed work requiring a license, and even if the work performed by the contractor was free of defects. In short, it’s the nuclear bomb of remedies against a contractor.
However, until now, no court has addressed when a project owner is permitted to raise a Business and Professions Code section 7031 claim against a contractor. In the next case, Eisenberg Village of the Los Angeles Jewish Home for the Aging v. Suffolk Construction Company, Inc., Case No B297247 (August 26, 2020), the 2nd District Court Appeal finally answers this question.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com