Hybrid Contracts for The Sale of Goods and Services and the Predominant Factor Test
February 15, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Uniform Commercial Code (also known as the UCC) applies to transactions for goods. “Goods” is defined by Article II of the UCC as “all things (including specially manufactured goods) which are movable at the time of identification to the contract for sale other than the money in which the price is to be paid, investment securities (chapter 678) and things in action.” Fla. Stat. s. 672.105(1).
The UCC does NOT apply to transactions for services. Transactions for services are governed by common law.
Oftentimes, transactions or contracts include BOTH goods and services. In this scenario, referred to as a hybrid contract, does the UCC or common law apply? In this scenario, courts apply the predominant factor test to determine whether the UCC or common law governs the transaction:
Whether the UCC or the common law applies to a particular hybrid contract depends on “whether the[ ] predominant factor, the [ ] thrust, the[ ] purpose [of the contract], reasonably stated, is the rendition of service, with goods incidentally involved (e.g., contract with artist for painting) or is a transaction of sale, with labor incidentally involved (e.g., installation of a water heater in a bathroom).” In such instances, the determination whether the “predominant factor” in the contract is for goods or for services is a factual inquiry unless the court can determine that the contract is exclusively for goods or services as a matter of law.
Allied Shelving & Equipment, Inc. v. National Deli, LLC, 154 So.3d 482, 484 (Fla. 3d DCA 2015) (citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
“Families First Coronavirus Response Act”: Emergency Paid Leave for Construction Employers with Fewer Than 500 Employees
March 30, 2020 —
Sidney Lewis & Alex Glaser, Jones Walker LLP - ConsensusDocsCOVID-19 has already taken a toll on construction projects across the nation. Construction industry participants, including general contractors, now face risks and challenges that are exceedingly difficult to anticipate and plan for. The spread of this virus has and will continue to create new labor force issues and amplify existing ones.
On March 18, 2020, the House of Representatives passed H.R. 6021, the “Families First Coronavirus Response Act,” which, contains provisions related to mandatory paid leave for employers with fewer than 500 employees. This legislation and the substantial obligations it imposes apply to the overwhelming number of general contractors in the nation—those with less than 500 full-time employees! The bill mandates up to 80 hours of “emergency paid leave” related to COVID-19, and not just for those who contract the illness. However, contractors with less than 50 employees may seek exemption.
Reprinted courtesy of
Sidney Lewis, Jones Walker LLP and
Alex Glaser, Jones Walker LLP
Mr. Lewis may be contacted at slewis@joneswalker.com
Mr. Glaser may be contacted at aglaser@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Throws Wet Blanket On Prime Contractor's Attorneys' Fees Request In Prompt Payment Case
September 03, 2015 —
Steven M. Cvitanovic & Abigail E. Lighthart – Haight Brown & Bonesteel LLPPrompt payment penalty cases do not come around very often, but when they do, there is bound to be fireworks.
In James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., et al. (No. C072169, filed 8/27/15), the California Court of Appeal for the Third Appellate District upheld the trial court's discretion to not award prevailing party attorneys' fees to the party who won a prompt payment dispute. California Business and Professions Code §7108.5 and Public Contract Code §§7107 and 10262 are the mechanisms for obtaining prompt payment relief in California. As shown by the outcome, it is possible to win and lose at the same time.
West Bay Builders, Inc. (“West Bay”) was the prime contractor on a school construction project for Stockton Unified School District. West Bay entered into a subcontract agreement with James L. Harris Painting & Decorating, Inc. (“Harris”) on the project. During construction there were disagreements between West Bay and Harris regarding the contractual scope of work, and Harris performed work it believed was outside the contract, believing it would be paid for the additional work. After West Bay refused to pay for the additional work, Harris left the project, and West Bay hired another subcontractor to complete the work.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Abigail E. Lighthart, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Defend Additional Insured Though Its Insured is a Non-Party
November 18, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff insurer's motion for partial summary judgment seeking an order that defendant insurer was obligated to defend a non-party as an additional insured was granted. Am Empire Surplus Lines Ins. Co. v. Burlington Ins. Co., 2019 N. Y. Misc. LEXIS 4145 (N. Y. Sup. Ct. July 25, 2019).
Quality Building Construction, LLC was the contractor hired to work on exterior facade of a building owned by Central Park West Corporation. The underlying complaint alleged that Quality caused plastic spacers and pedestals used for the penthouse terrace to fall down the roof drain riser. A clog and rainwater backup resulted in water damage to apartment 8A. The resulting damage was allegedly due to the clogged roof drain riser.
Quality subcontracted the work to Mega State, Inc. The subcontract required Mega to indemnify and hold Quality harmless against claims in connection with Mega's work, as well as name Quality as an additional insured on a primary, non-contributory bases under Mega's CGL policy. Burlington issued a policy to Mega naming Quality as an additional insured. American Empire issued a CGL policy to Quality.
Quality was sued in the underlying action, but Mega was not. American Empire tendered a demand for coverage to Mega and Burlington, relying on the agreement between Quality and Mega. Burlington responded that Mega was not liable for the alleged damages. American Empire sued Burlington. Subsequently, Burlington accepted the tender to defend Quality in the underlying action, and reserved rights as to whether Burlington's policy was primary and on the question of indemnification. American Empire agreed to withdraw its suit if Burlington would modify its reservation of rights. Burlington refused.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Herman Russell's Big Hustle
May 20, 2024 —
Maggie Murphy - Construction Executive“Any person that I knew of in the city of Atlanta who did anything ran it by Herman before they did anything else.”
These are the words of Anthony Dixon, senior project manager and 47-year veteran employee with H. J. Russell & Company. But ask anyone who knows anything about H. J. Russell, and they’ll say the same thing: The story of the company is the story of Herman J. Russell himself.
From humble beginnings in Atlanta’s Summerhill neighborhood came a young man with an unbreakable entrepreneurial spirit, who used that drive to forge an unlikely path to success in the Jim Crow–era South. What began as a plastering company in 1952 is today one of the largest Black-owned contractors in the United States, with Herman’s children—Donata Russell Ross, H. Jerome Russell and Michael B. Russell Sr.—at the helm (a natural fit for the family-focused firm).
Over its 72-year history, H. J. Russell has grown exponentially, contracted when necessary and persevered through segregation, the turbulence of the Civil Rights Movement and multiple economic downturns. Now, in the next five years, they’re poised to become a billion-dollar company.
But long before any of that, there was just a boy and a dream.
Reprinted courtesy of
Maggie Murphy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Greystone on Remand Denies Insurer's Motion for Summary Judgment To Bar Coverage For Construction Defects
June 28, 2013 —
Tred EyerlyA prior post here discussed the Tenth Circuit's decision in Greystone Constr., Inc. v. National Union Fire & Marine Ins. Co., 661 F. 3d 1272 (10th Cir. 2011). The court found a duty to defend construction defect claims where damage caused by the faulty workmanship was unintentional. The Tenth Circuit remanded for a determination on whether any policy exclusions precluded a defense or indemnity for damage arising from faulty workmanship. On remand, the district court denied National Union's Motion for Summary Judgment, seeking to establish the policy exclusions precluded its duty to defend and to indemnify. See Greystone Constr., Inc. v. v. National Union Fire & Marine ins. Co., 2013 U. S. LEXIS 46707 (D. Colo. March 31, 2013).
Greystone was sued for construction defects in homes it built. The suit alleged that Greystone failed to recognize defects in the soil where the house was built. National Union refused to defend. The district court initially granted summary judgment to National Union because claims arising from construction defects were not covered. As noted above, the Tenth Circuit vacated because the damage in the underlying suit did not categorically fall outside coverage under the policy.
On remand, National Union first argued there was no duty to defend based upon an exclusion precluding coverage for damage arising out of work done by subcontractors unless the subcontractors agreed in writing to defend and indemnify the insured and carried insurance with coverage limits equal to or greater than that carried by the insured. The Tenth Circuit rejected this argument because National Union had to rely on facts outside of the underlying complaint.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
No Choice between Homeowner Protection and Bankrupt Developers?
February 10, 2012 —
CDJ STAFFDonna DiMaggio Berger, writing in the Sun Sentinel argues those may be the only current choices in Florida. A recent court case, Lakeview Reserve HOA v. Maronda Homes has caused a swift response from the legislators. Ms. Berger notes that the construction defect bill, HB 1013, “would take away a homeowner’s rights to pursue a developer for defects to the driveways, roads, sidewalks, utilities, drainage areas and other so-called ‘off-site’ improvements.” The alternative? She notes that applying the Maronda decision would “bankrupt developers who don’t build defect-free roads and sidewalks.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Experts Weigh In on Bilingual Best Practices for Jobsites
February 22, 2018 —
Jim Parsons – ENRIt’s the rare construction firm that doesn’t cite people as its most important resource. And over the past two decades, that asset has become increasingly bilingual. Indeed, more than 27% of workers in construction are Hispanic or of Latino ethnicity, according to the most recent available data from the U.S. Bureau of Labor Statistics (BLS).
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, Engineering News-Record