Serving the 558 Notice of Construction Defect Letter in Light of the Statute of Repose
November 06, 2018 —
David Adelstein - Florida Construction Legal UpdatesFlorida Statutes Chapter 558 requires a Notice of Construction Defect letter (“558 Notice”) to be served before a construction defect lawsuit is commenced. This is a statutory requirement unless contractually waived for a completed project when latent defects or post-completion construction or design defects are pursued.
A recent Florida case held that this statutory requirement is NOT intended to bar a lawsuit based on Florida’s ten-year statute of repose for construction defects IF the 558 Notice is timely served within the statute of repose period. After the expiration of the statute of repose period, a construction defect lawsuit can no longer be commenced.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Haight Expands California Reach – Opens Office in Sacramento
October 21, 2015 —
Haight Brown & Bonesteel, LLPHaight Brown & Bonesteel LLP is excited to announce that the firm has opened an office in Sacramento with the addition of two new attorneys – Elizabeth W. Lawley has joined as Managing Partner for the Sacramento office and Gino Cano as Senior Counsel. Lawley and Cano bring their thriving practices to Haight with expertise in construction law and general liability matters. With the addition of Sacramento, Haight now has six offices throughout the State of California. Our footprint and ability to provide exceptional service is greatly expanded.
Haight Brown & Bonesteel LLP
2485 Natomas Park Drive
Suite 450
Sacramento, CA 95833
www.hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
“Details Matter” is the Foundation in a Texas Construction Defect Suit
March 01, 2012 —
CDJ STAFFThe Court of Appeals of Texas has ruled in the case of Barzoukas v. Foundation Design. Mr. Barzoukas contracted with Heights Development to build a house. He subsequently sued Heights Developments and “numerous other defendants who participated in the construction of his house.” Barzoukas eventually settled with all but two defendants, one who went bankrupt and Foundation Design, the defendant in this case. In the earlier phase, Barzoukas made claims of “negligence, negligent misrepresentation, fraud, fraudulent inducement, conspiracy, and exemplary damages in connection with the foundation.”
Foundation Design had been hired to install 15-foot piers to support the foundation. The engineer of record, Larry Smith, sent a letter to Heights Development noting that they had encountered hard clay stone when drilling. Smith changed the specifications to 12-foot piers. Initially, the City of Houston called a halt to work on the home when an inspector concluded that the piers were too shallow. Heights Development later convinced the city to allow work to continue. Subsequently, experts concluded that the piers were too shallow.
Foundation Design filed a motion for summary judgment. The trial court granted this, “without specifying the basis for its ruling.” Barzoukas contends the court was in error. Foundation Design contends that “Barzoukas failed to proffer competent evidence establishing that their conduct proximately caused damages.” Further, they did not feel that Smith’s letter gave “rise to viable claims for fraud and fraudulent inducement.”
One problem the court had was a lack of evidence. The court noted that “the purported subcontract is entirely missing” in the pleadings. The court has no contract between Bazourkas and Heights Development, nor one between Heights Development and either Foundation Design or Smith. The court underscored the importance of this, writing, “details matter.” They found that “the details are largely missing here.” Without the contract, the court found it impossible to determine if “Smith or an entity related to him agreed to indemnify Heights Development for damages arising from Smith’s negligent performance.”
As the material facts are in dispute, the appeals court found that there were no grounds for a summary judgment in the case. “Pointing to the existence of a contract between Heights Development and Barzoukas, or to the existence of a subcontract, is the beginning of the analysis ? not the end.”
Foundation Design and Smith also claimed that Barzoukas’s expert did not proffer competent evidence and that the expert’s opinions were conclusory. The trial court did not rule on these claims and the appeals court has rejected them.
Finally, Barzoukas made a claim that the trial court should not have rejected his argument of fraud and fraudulent inducement. Here, however, the appeals court upheld the decision of the lower court. “Barzoukas did not present evidence supporting an inference that Smith or Foundation Design made a purposeful misrepresentation.
The court remanded the case to the trial court for reconsideration. One member of the panel, Judge Charles Seymore, upheld the entire decision of the trial court. He dissented with the majority, finding that the economic loss rule foreclosed the claim of negligence.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Condo Building Increasing in Washington D.C.
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported that in Washington D.C., "the condo pipeline has increased for the first time since 2005, according to Alexandria, Va.,-based research firm Delta Associates." Supply has grown with "3,100 units either being marketed or sold in around the nation's capital." Furthermore, "condo prices have jumped 12 percent year over year."
“The size of the projects are smaller than they were in the last boom cycle,” William Rich, senior vice president and multifamily practice director at Delta, told Builder.
Read the court decisionRead the full story...Reprinted courtesy of
Property Insurance Exclusion: Leakage of Water Over 14 Days or More
July 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion of Whitley v. American Integrity Ins. Co. of Florida, 43 Fla.L.Weekly D1503a (Fla. 5th DCA 2018), as a follow-up to this article on the property insurance exclusion regarding the “constant or repeated seepage or leakage of water…over a period of 14 or more days,” is a beneficial opinion to insureds.
In this case, the insured had a vacation home. A plumbing leak occurred that caused water damage to the home. The plumbing leak occurred during a period of time that lasted approximately 30 days. For this reason, the property insurer denied the claim per the exclusion that the policy does not cover loss caused by repeated leakage of water over a period of 14 or more days from a plumbing system. Summary judgment was granted by the trial court in favor of the insurer based on this exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Actual Cost Value Includes Depreciation of Repair Labor Costs
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss after determining that benefits paid for actual cost value (ACV) did not include repair or replacement labor costs. Shahan v. Allstate Vehicle & Prop. Ins. Co., 2022 U.S. Dist. LEXIS 135488 (W.D. La. July 29, 2022).
Hurricane Laura damaged the insured's home. She filed a claim with Allstate under her homeowners policy. Allstate issued payment. The insured filed suit alleging Allstate wrongfully withheld amounts by depreciating labor when calculating the ACV of the damaged property. Allstate moved to dismiss.
The policy was a replacement cost policy where the insured would receive the actual cash value of her insured property when it was damaged or destroyed by a covered peril. ACV was calculated by taking the repair/replacment which included both material and labor, and then deducting for depreciation. If no repairs or replacements were made, the insured was paid the ACV. If repairs or replacement was done, Allstate reimbursed the insured for the depreciation deduction. The insured challenged Allstate's refusal to pay 100% of the future labor costs, without any depreciation, even if the insured did not replace or repair the damaged property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Suffolk Stands Down After Consecutive Serious Boston Site Injuries
May 23, 2022 —
Scott Van Voorhis - Engineering News-RecordAfter two serious safety incidents in consecutive days, the Boston-area’s largest contractor voluntarily issued a safety stand down on all projects in Boston through May 6.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Municipal Ordinances Create Additional Opportunities for the Defense of Construction Defect Claims in Colorado
August 22, 2022 —
Ricky Nolen - Colorado Construction Litigation BlogMunicipal ordinances may provide additional defenses for construction professionals where state law does not provide sufficient protection for Colorado’s builders. Colorado state law can be a minefield of potential liability for construction professionals. Even though the state legislature has stated that it must “recognize that Construction defect laws are an existing policy issue that many developers indicate adds to for-sale costs,” the legislature has remained hesitant to provide any meaningful protection from construction defect claims, resulting in almost unlimited exposure for Colorado’s construction professionals.
Given this background of state laws that do not go far enough in protecting Colorado’s construction professionals, it may be fruitful to review municipal ordinances for new defenses and to temper state law developments applicable to construction defect claims. This is an area of law that is only just developing in Colorado. In fact, the ordinances discussed in this article were only passed in the last two years with many cities only adopting the present versions of the ordinances in 2021. The two model ordinances discussed below are potentially helpful in three ways. The first model ordinance gives construction professionals a right to repair defects in the multi-family construction and in the common interest community context. The second model ordinance is helpful in two ways. First, it establishes that homeowners associations may not unilaterally circumvent ADR protections included in the original declarations for such communities.[1] Second, the ordinance reduces the risk that strict liability will be imposed on a construction professional where a building code is violated.
Read the court decisionRead the full story...Reprinted courtesy of
Ricky Nolen, Higgins, Hopkins, McLain & Roswell, LLCMr. Nolen may be contacted at
nolen@hhmrlaw.com