Carrier Has Duty to Defend Claim for Active Malfunction of Product
October 19, 2020 —
Tred R. Eyerly - Insurance Law HawaiiRejecting that the underlying claim was based solely on faulty workmanship, the Third Circuit held the insurer had a duty to defend allegations of a malfunctioning product. Nautilus Ins. Co. v. 200 Christina Street Partners LLC, 2020 U.S. App. LEXIS 22118 (3d Cir. July 16, 2020).
The insureds were sued by homeowners in two separate suits alleging defects in the construction of their homes. Nautilus defended under a reservation of rights. Nautilus filed suit in District Court and moved for judgment on the pleadings. The District Court denied the motion, finding Nautilus had a duty to defend because the underlying claims sufficiently alleged product--related tort clams that could fall within the scope of coverage under the relevant policies.
The Third Circuit affirmed. There was a distinction between a claim of faulty workmanship, for which the insurer did not have a duty to defend, and a claim of "active malfunction" of a product, for which an insurer did have such a duty. An active malfunction was sufficiently fortuitous as to constitute an "occurrence."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Clarifies Sequence in California’s SB800
December 20, 2012 —
CDJ STAFFAs California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery. “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the court decisionRead the full story...Reprinted courtesy of
Late Notice Kills Insured's Claim for Damage Due to Hurricane
December 27, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment was granted based upon the insured's late notice nearly two years after a hurricane caused property damage. Ramirez v. Scottsdale Ins. Co., 2021 U.S. Dist. LEXIS 209716 (S.D. Fla. Oct. 29, 2021).
Plaintiff alleged he suffered property loss due to wind and water damage from Hurricane Irma on September 10, 2017. The roof, exterior, and interior of the home were damaged.
On May 20, 2019, twenty months after the hurricane, plaintiff first notified Scottsdale of his claim for damages. An adjuster inspected and observed wind, wear and tear, and deterioration damage to the roof tile, as well as interior water damage to portions of the home. The claim was denied based upon wind, wear and tear, and deterioration exclusions in the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Give Way or Yield? The Jurisdiction of Your Contract Does Matter! (Law note)
March 05, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaHave you ever been to England? If so, you’ve likely seen their version of our “Yield” sign– the “Give Way” sign. It is a bit jarring to those from this side of the “big pond”.
Similarly, contracts can be worded differently– and, interpreted differently– depending on the state that you are in. This is why it is always a good idea to have your contract or proposal vetted for the state(s) where you provide professional services.
When confronted with a “give way” sign you have the general idea of yielding, but might be confused by that whole “left side of the road” thing in some countries, where if you are turning right, you must give way to all vehicles coming towards you including those turning left. Likewise, you might have a good understanding of your construction contract in one state, but not how it would be interpreted in another state.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Summary Judgment in Favor of General Contractor Under Privette Doctrine Overturned: Lessons Learned
March 27, 2023 —
Garret Murai - California Construction Law BlogIt seems like we’ve been seeing a lot of Privette doctrine cases recently. Here’s another,
Brown v. Beach House Design & Development, 85 Cal.App.5th 516 (2002), which provides a cautionary tale for general contractors to watch what they include in their scope of work and how they manage projects.
The Beach House Case
Kyle Brown was a carpenter employed by subcontractor O’Rourke Construction, Inc. who contracted with general contractor Beach House Design and Development to provide finish carpentry on a construction project. A&D Plastering Co., another subcontractor on the project, had erected scaffolding on the project.
On June 16, 2017, while using A&D’s scaffolding, Brown fell onto a concrete walkway where he suffered severe injuries. Following the accident, Beach House and A&D inspected the scaffolding and found that some of the scaffolding was not properly secured to the building and that planks, crossbars, ties and guardrails had been cut or were missing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
COVID-19 Response: Recent Executive Orders Present Opportunities for Businesses Seeking Regulatory and Enforcement Relief and Expedited Project Development
June 15, 2020 —
Karen C. Bennett, Jane C. Luxton & Amanda L. Tharpe - Lewis BrisboisWashington, D.C. (June 8, 2020) - Two recent Executive Orders (EO) aimed at promoting economic recovery from the COVID-19 crisis offer regulatory and enforcement relief and encourage agencies to expedite infrastructure project approvals. The May 19, 2020 EO 13924, “Regulatory Relief to Support Economic Recovery,” directs agencies to determine whether previous regulatory reforms would promote economic recovery if made permanent and encourages compliance assistance through exercising enforcement discretion, including declining enforcement. And the June 4, 2020 EO 13927, “Accelerating the Nation’s Economic Recovery from the COVID-19 Emergency by Expediting Infrastructure Investments and Other Activities,” aims to speed up the permitting process for infrastructure projects to strengthen the national economy. As businesses look to move forward and recover from the COVID-19 pandemic, they should closely review these EOs for opportunities to take advantage of streamlined treatment and faster project approvals.
EO 13294 supplements the Administration’s efforts to address the economic crisis brought on by the COVID-19 pandemic by encouraging federal agencies to rescind, modify, waive, or provide exemptions from federal regulations that may inhibit economic recovery and to provide guidance to businesses, particularly small businesses, on what is required of them under federal law for reopening. Specifically, the EO directs agency heads to identify regulatory standards that may inhibit economic recovery and consider rescinding or waiving those regulations, exempting regulated entities from compliance, exercising enforcement discretion, or extending regulatory compliance and enforcement deadlines. It also allows for compliance assistance through accelerated regulatory procedures to receive a pre-enforcement ruling and directs agencies to assess previous regulatory reforms to determine whether making them permanent would promote economic recovery. Since taking office, the Trump Administration has made regulatory reform a cornerstone of its agenda. This Executive Order is a continuation of the aggressive steps taken by the Administration to reduce the regulatory burden faced by American businesses that many argue increases operating costs, inhibits job creation, and stifles economic growth.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Jane C. Luxton and
Amanda L. Tharpe
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Tharpe may be contacted at Amanda.Tharpe@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
City Drops Impact Fees to Encourage Commercial Development
November 08, 2013 —
CDJ STAFFThe Orvido, Florida city council wants to encourage commercial development, and they’re willing to do it by discouraging residential development. The impact fees for commercial buildings have dropped sharply, the Orlando Sentinel notes that for a 50,000 square-foot office building, the city is reducing the impact fee from $2,890 to $1,575, a drop of $1,313, nearly half.
Meanwhile, the impact fee for single-family homes has seen an increase of seven percent, going from $3,195 to $3.433. The city is clear about its reasons. “We’re very heavy on the residential side. We want to have more high-paying jobs come into the city,” said Keith Britton, a member of the council.
Read the court decisionRead the full story...Reprinted courtesy of
Rancosky Adopts Terletsky: Pennsylvania Supreme Court Sets Standard for Statutory Bad Faith Claims
September 28, 2017 —
John Anooshian & Sean Mahoney - White & Williams LLPEarlier today, in a case of first impression, the Pennsylvania Supreme Court adopted the Terletsky two-part test for proving a statutory “bad faith” claim under 42 Pa. C.S.A. § 8371, which requires that a plaintiff present “clear and convincing evidence (1) that the insurer did not have a reasonable basis for denying benefits under the policy and (2) that the insurer knew of or recklessly disregarded its lack of a reasonable basis.” Rancosky v. Washington National Insurance Company, No. 28 WAP 2016 (Pa. Sept. 28, 2017). The court further ruled that proof of an insurer’s “subjective motive of self-interest or ill-will,” while potentially probative of the second prong of the test, is not a requirement to prevail under § 8371. Evidence of an insurer’s “knowledge or reckless disregard for its lack of a reasonable basis” for denying a claim alone, according to the court, is sufficient even in cases seeking punitive damages.
Reprinted courtesy of
John Anooshian, Saxe Doernberger & Vita, P.C. and
Sean Mahoney, Saxe Doernberger & Vita, P.C.