Preliminary Notice Is More Important Than Ever During COVID-19
June 01, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Construction Law Musings, we welcome Justin Gitelman. Justin is the Content Coordinator at Levelset, where over 500,000 contractors and suppliers connect on a cloud-based platform to make payment processes stress-free. Levelset helps contractors and suppliers get payment under control, and sees a world where no one loses a night’s sleep over payment.
As the construction industry continues to adjust to the coronavirus and an uncertain future, contractors are struggling to get paid. During the COVID-19 pandemic, construction businesses across Virginia need to do everything they can to protect their payments, and get paid faster. One simple action that can help fight payment delays: sending preliminary notice on every job.
Subcontractors and suppliers should send preliminary notices out to the GC, project owner, and/or lender at the start of every single project. These tools allow contractors to make themselves visible on crowded job sites, helping contractors get paid more quickly, and, in some cases, securing their right to file a mechanics lien or bond claim.
Preliminary Notices in Construction
The purpose of a preliminary notice is to allow each member of a construction project to know who you are and what work you’ll be performing. With coronavirus in mind, contractors can use preliminary notices to remind the hiring party of their payment expectations. When you submit a preliminary notice on every project, you’ll have legal protection in your corner while also giving yourself a greater opportunity to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrissghill@constructionlawva.com
ASCE Statement on Devastating Tornado Damages Throughout U.S.
December 20, 2021 —
Tom Smith, Executive Director - American Society of Civil Engineers (ASCE)WASHINGTON, DC. – We are deeply saddened by the tragic tornado storms that ravaged six states across the Midwest and Southeastern portions of the U.S. last Friday evening, resulting in loss of life in five of those six states. Even though warnings were issued throughout the region, storms of this magnitude can be difficult to prepare for. Nevertheless, as civil engineers, our mission is to continually advance the design and construction of safe, reliable, and resilient building structures and infrastructure systems to mitigate the damage caused by storms.
ASCE 7 — a nationally-adopted, consensus-based engineering standard that is the primary reference of structural design requirements in all U.S. building codes — was recently updated to include a new chapter for tornado loads in the 2022 edition. The new tornado provisions in ASCE 7-22 were a result of a decade-long effort in partnership with the National Institute of Standards and Technology following the 2011 Joplin, MO Tornado. ASCE 7-22 provides updated design requirements for a variety of structures, including many of the types impacted by Friday's storms.
In an effort to assist, the Structural Engineering Institute of ASCE is currently offering free access to a report issued after the Joplin, MO tornado in 2011 that killed more than 150 people.
Joplin, Missouri, Tornado of May 22, 2011: Structural Damage Survey and Case for Tornado-Resilient Building Codes presents the observations, findings, and recommendations of an engineering reconnaissance team that surveyed residential structures and schools in the tornado path shortly after the event. The EF 5 tornado cut a seven-mile swath through Joplin, Missouri; it destroyed more than 5,000 buildings and killed more than 150 people.
We will continue to keep those who have been affected in our hearts and thoughts, and we share our heartfelt sympathies.
For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Saudi Prince’s Megacity Shows Signs of Life
September 03, 2019 —
Vivian Nereim & Donna Abu-Nasr - BloombergThe walls are covered with graffiti in the sleepy fishing village of Khurayba. There are supplications to God, advertisements for vacation rentals and house painters. Near the local school, there’s a scribbled plea: “Open the windows of hope and drive out the despair.”
It’s here in northwest Saudi Arabia that Crown Prince Mohammed bin Salman wants investors to put their money to realize his $500 billion vision for the region. Called “Neom,” it promises to be the most freewheeling part of the kingdom, with state-of-the-art resorts and smart technologies run by robots.
But it’s also here where the risks to the 33-year-old prince’s grand plan for his country are writ large. Neom is the boldest pillar of a social and economic transformation that so far has seen at least as many delays as successes. Indeed, the question since the prince announced the vast development at an extravaganza in 2017 has been whether it can become a reality.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim & Donna Abu-Nasr, Bloomberg
Court Dismisses Cross Claims Against Utility Based on Construction Anti-Indemnity Statute
August 14, 2018 —
David R. Cook - Autry, Hall & Cook, LLPWhen a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Plant Owner”), based on claims that transmission lines on Plant Owner’s property were too close to the runways, were too high, and encroached on the airport easements. Plant Owner cross claimed against utility owner, Georgia Power Company (“Utility”). Plant Owner’s claim was based on an easement it granted to Utility, which required Utility to indemnify it for any claims arising out of Utility’s construction or maintenance of the transmission lines.
In defense, Utility argued that the easement’s indemnity provision violated Georgia’s construction anti-indemnity statute.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Providing “Labor” Under the Miller Act
January 28, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Northern District of California discusses the “labor” required to support a Miller Act payment bond claim on a federal construction project. It is a good case that discusses the type of labor required to support a Miller Act payment bond claim.
In Prime Mechanical Service, Inc. v. Federal Solutions Group, Inc., 2018 WL 619930 (N.D.Cal. 2018), a prime contractor was awarded a contract to design and install a new HVAC system. The prime contractor subcontracted the work to a mechanical contractor. The mechanical contractor with its sub-designer prepared and submitted a new HVAC design to the prime contractor and provided 4-5 onsite services to determine the location and layout for the new HVAC equipment, perform field measurements, obtain security passes, and plan site access and crane locations. The mechanical contractor submitted an invoice to the prime contractor and the invoice remained unpaid for more than 90 days, which the prime contractor refused to pay. The mechanical contractor than filed a Miller Act payment bond lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
South Carolina Law Clarifies Statue of Repose
July 11, 2011 —
CDJ STAFFA new law in South Carolina, H 3375, fixes a loophole in that state’s statute of repose. State law puts a cap of eight years on construction defects, but the 2008 law that set that limit had a loophole that would allow for construction defect claims to start thirteen years after construction. The law also provides a cap on punitive damages.
The measure was backed by the Carolinas Association of General Contractors. Their spokesperson said that the legislation “increases our state’s ability to be economically competitive and helps protect our members from frivolous lawsuits.”
Read the full story…
Read South Carolina H 3375…
Read the court decisionRead the full story...Reprinted courtesy of
Appellate Court Endorses Discretionary Test for Vicarious Disqualification of Law Firms Due To New Attorney’s Conflict
February 07, 2018 —
David W. Evans and Stephen M. Tye – Publications & Insights In
California Self-Insurer’s Security Fund et al. v. The Superior Court of Orange County (1/26/2018 – No. G054981), the Fourth Appellate District considered whether vicarious disqualification of a law firm is mandatory or discretionary where an attorney with a conflict joins a firm and the firm enacts an ethical screen to prevent transmission of confidential information between the new attorney and the rest of the firm.
This case arose from an effort by the California Self-Insurer’s Security Fund (the “Fund”) to be reimbursed for workers’ compensation benefits advanced on behalf of the Healthcare Industry Self-Insurance Program (the “Program”). The Fund hired Nixon Peabody LLP (“Nixon Peabody”) to represent it in connection with this matter. In November 2013, represented by members of Nixon Peabody’s San Francisco office, the Fund filed a lawsuit naming 304 members of the Program as defendants. Approximately 170 defendants have since settled.
Two of the non-settling defendants (“Moving Parties”), were represented by Michelman & Robinson, LLP (“M&R”). From approximately 2009 until February 1, 2017, attorney Andrew Selesnick served as Chair of M&R’s Health Care Department at the firm’s Los Angeles office, managing a team of attorneys who represented clients in the healthcare industry. Commencing in 2014, a team of four attorneys at M&R, including Selesnick, represented the Moving Parties and four other defendants, the latter of whom have since settled. Selesnick was actively involved, including participating in a confidential discussion pertaining to Moving Parties’ liability and damages and receiving many e-mails containing communications about the common defense of the remaining 170 defendants.
Reprinted courtesy of
David W. Evans, Haight Brown Bonesteel and
Stephen M. Tye, Haight Brown Bonesteel
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How VR and AR Will Help in Remote Expert Assistance
June 10, 2019 —
Aarni Heiskanen - AEC BusinessThe speed and quality of maintenance and repair are critical in the modern, technology-packed built environment. Consequently, these were considered in an experimental project that tested how remote expert assistance using VR and AR technologies could help improve the productivity of field service.
I’m in a hall overlooking white mountain tops. It’s snowing. In front of me stands an avatar that explains to me what we can do together in this virtual space. He jumps away but I can still hear his voice from behind me. He fetches a chair and hands it to me. I grab it and inspect it. The next moment, a video starts playing on the wall. Later, my host shows me how to draw in three dimensions, how to make sticky notes, how to share a PC desktop, and how to use other collaboration tools.
This experience took place at FAKE Production, a Helsinki-based digital image, animation, and VR/AR studio. With VR glasses and hand-held controllers, I had tried out Glue, their universal collaboration platform. This is a soon-to-be-released service that you can use with VR/AR gear and on mobile and desktop devices.
Glue is also one of the solutions tested in an experimental project called Expert assistance using VR and AR glasses. In this project, Sovelto, a Finnish educational company, wanted to explore the possibilities of using VR and AR solutions for field service. Over ten organizations took part in the project, which received funding from KIRA-digi, the national built environment digitalization program.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at