Claim Preclusion: The Doctrine Everyone Thinks They Know But No One Really Knows What it Means in Practice
April 25, 2023 —
Garret Murai - California Construction Law BlogGenerally, I think restraint in litigation is a good thing. Don’t go crazy on your claims, don’t go nut-so in your discovery, and don’t present your case at trial in a way that causes the judge and/or jury to raise their eyebrows or shake their heads in disbelief. But, as with nearly everything, there’s always an exception. One of which is: don’t hold back on a claim because you “think” you might be able to bring it later, because you might not be able to as the next case, 5th and LA v. Western Waterproofing Company, Inc., 87 Cal.App.5th 781 (2023), demonstrates.
The 5th and LA Case
At the outset, let me first say how much I enjoyed reading this case based on the writing alone. The case, as the 2nd District Court of Appeals states, involves “a second lawsuit about an increasingly leaky roof.”
In 2012, property owner 5th and LA hired roofing contractor Western Waterproofing Company, Inc. to remove and recoat a parking lot that served also served as the roof over retail and office space below. Western completed its work in July 2012 and almost immediately 5th and LA noticed water that the coating was failing causing water leaks to the interior of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Hake Law Attorneys Join National Law Firm Wilson Elser
April 02, 2014 —
Beverley BevenFlorez-CDJ STAFFIn a press release published on PRWEB, the national law firm Wilson Elser announced “that Bill Hake, founder of Bay Area–based Hake Law, and 15 members of his team, including attorneys, paralegals and staff, have joined the firm’s San Francisco office effective April 1.”
Specifically, “Wilson Elser has added a total of four partners from Hake Law, including Bill Hake, Melissa Ippolito, Nicolas Martin and Lucy Hoff, and four associates, including Gardiner McKleroy, Jeremy Berla, Molly Friend and Whitney Barnecut, bringing the total attorney headcount in Wilson Elser’s San Francisco office to 40.”
According to the release, “Hake Law was primarily a defense litigation firm focused on product liability, construction defects, D&O, catastrophic injury, toxic tort, white collar criminal, class action and complex litigation defense.” Wilson Elser is a “full-service and leading defense litigation law firm… with nearly 800 attorneys in 25 offices in the United States, one in London and through a network of affiliates in key regions globally.”
Read the court decisionRead the full story...Reprinted courtesy of
Compliance with Contractual and Jurisdictional Pre-Suit Requirements is Essential to Maximizing Recovery
November 27, 2023 —
Michael S. Levine, Geoffrey B. Fehling & Charlotte Leszinske - Hunton Insurance Recovery BlogTimely notice is an important first step in a successful insurance recovery. But insurance policies are not always straightforward in identifying how, when, and to whom notice must be provided. Some states may also impose additional procedural hurdles, including requiring policyholders to contact their insurers before filing suit (the idea behind this requirement is that it may avoid litigation). Failing to comply with pre-suit requirements can hurt the policyholder’s recovery, as illustrated in a recent decision from the Northern District of Texas.
In NewcrestImage Holdings, LLC v. The Travelers Lloyds Insurance Company, No. 2:23-cv-039-BR (N.D. Tex. Oct. 17, 2023), the court considered whether NewcrestImage had forfeited its right to recover attorneys’ fees by failing to give Travelers pre-suit notice. NewcrestImage had filed suit against Travelers to obtain coverage for damage to its hotel property arising out of Winter Storm Uri. In its answer, Travelers asserted that NewcrestImage failed to provide the insurer with pre-suit notice as required under the Texas Insurance Code, and that if NewcrestImage successfully proved it was entitled to coverage, NewcrestImage’s failure to provide pre-suit notice precluded it from recovering attorneys’ fees. Travelers later moved to strike the claim for attorneys’ fees on that basis.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 09, 2011 —
CDJ STAFFConstruction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Residential Construction Surges in Durham
October 30, 2013 —
CDJ STAFFThird quarter residential construction permits in Durham, North Carolina were up 72% over the third quarter of last year, for a total of 1,770 new residential units. There was a large increase in the value of the construction contracts as well, with construction contracts reaching $151.3 million, more than $42 million over the same period in 2012.
Ted Conner of the Greater Durham Chamber of Commerce said that he didn’t “think we’re going to continue to see that frenetic, high level of activity, but it’s still very active.” One reason for increased residential construction is a lack of available apartment spaces, which is also sending rents up in the area. Although much of the new construction will be middle- to upper-end, the greater availability should help all renters.
Read the court decisionRead the full story...Reprinted courtesy of
The California Legislature Passes SB 496 Limiting Design Professional Defense and Indemnity Obligations
June 15, 2017 —
Mark Himmelstein & Jenny Guzman – Newmeyer & Dillion LLPSince 2008 when the California legislature limited subcontractor indemnity obligations, the design professional community has been shouting “what about us?” Well, the legislature finally responded and a new law that limits design professional’s defense and indemnity obligations to their percentage of fault goes into effect on January 1, 2018.
THE NEW LAW – SB 496
SB 496 amends California Civil Code section 2782.8 and states that indemnity agreements must be limited to the negligence, recklessness or willful misconduct of the indemnitee (i.e. no more Type I indemnity with design professionals). The amendment also provides that “in no event shall the cost to defend charged to the design professional exceed the design professional’s proportionate percentage of fault”, with a limited opportunity for reallocation in the event another defendant is judgment proof.
However, the duty to defend still remains and still arises at the time of the tender of the defense (both issues that were unsuccessfully targeted by the design professional lobbyists).
WHAT CAN BE DONE NOW?
Developers and Owners should strongly consider reviewing and revising the indemnity provisions in their consultant contracts to comply with the new legislation before the first of the year. This includes master agreements because project addenda entered into after January 1 are subject to the new law. The statute does not apply to current contracts, so these do not need to be amended.
Questions? Newmeyer & Dillion is happy to assist in navigating the process to ensure you are compliant prior to January’s deadline. Please let us know how we can help.
Mark Himmelstein is a partner focused in the areas of construction, real estate, business and insurance litigation. He has an in-depth experience in drafting and negotiating construction and real estate contracts. You can reach him at mark.himmelstein@ndlf.com.
Jenny Guzman is a litigation associate in the Newport Beach office, focusing her practice in the areas of business and real estate litigation and transactions. You can reach her at jenny.guzman@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit http://newmeyeranddillion.com/
Read the court decisionRead the full story...Reprinted courtesy of
When Customers Don’t Pay: What Can a Construction Business Do
June 06, 2022 —
Patrick Hogan – Handle.comLate payments are not unusual in construction. From general contractors to subs and material suppliers, every construction project participant has dealt with delayed payments as part of business. However, there’s the issue of clients who refuse to pay. Not late--just no payment. For businesses big and small, a client who refuses to pay can make a significant impact financially and operationally. Many construction transactions are made on trust, and when a client doesn’t pay, some contractors and suppliers may make poor decisions. Yet, to get out of a project going sideways--with payment in hand or lessons learned--you need to be smart and proceed with your business interest in mind.
Why is the customer not paying?
This is where it begins. You must first identify the reasons why a customer refuses to pay. Were they unsatisfied with the quality of work? Do they feel that what was delivered was not aligned with what’s contractually obligated? Do they feel like the work was rushed or the materials used inferior? Was the job finished later than agreed? All these are possibilities that need to be investigated.
If the customer has not volunteered any of this information, it’s best to personally visit the project or set a meeting with the customer to discuss issues in person. If the problems the customer has raised are valid, plan how to resolve them right away. Suppose, after the discussion, you’ve determined that the customer demands things beyond what’s contractually obligated, and you cannot resolve them without incurring unreasonable time and costs. In that case, you might have a delinquent customer in your hands.
Let the customer know your decision. If you’ve decided to proceed and fix the issues they’ve raised, send the invoice for the unpaid work immediately upon commencing the remedial work. Of course, there is no guarantee that addressing their concerns will result in swift payment, so exercise your best judgment. If you think you’ve exhausted all the cordial means to get them to pay as the contract requires, you might need to consider your legal options.
A legal option to recover payments: Filing a mechanics lien
State laws protect construction providers like contractors and material suppliers from non-payment through lien laws. Mechanics liens work by placing a hold on the property where the work or materials were provided as a security in case of non-payment. Mechanics liens can result in a sale of the property where the lien is attached, and the proceeds will be used to pay unpaid vendors.
When a client fails to pay after a good-faith pursuit to resolve the payment issue, filing a mechanics lien becomes the smartest next move. However, note that to file a mechanics lien, you must have fulfilled the requirements of lien laws specific to the state where the project is located. For many states, the main requirement is sending a preliminary or pre-lien notice to secure your right to file liens. It’s only good business practice to
file preliminary notices for every project you work on. It’s not an indication of distrust in the client’s ability to pay–and that is mentioned in the wording of many statutory statements included in preliminary notices. It’s just industry standard to file prelim notices.
Filing a mechanics lien includes a period where the client still has the opportunity to pay arrears before the lien is enforced. Suppose the client fails to pay in this period. You are now allowed to enforce the mechanics lien through a lawsuit. This is a complex process, but it presents itself as the last resort to recover payments. As long as all your documents are in check, you’ve filed the necessary notices in the time and manner required by law, and you’ve fulfilled your contractual obligations to the client, a ruling in your favor is the likely outcome.
Promoting timely payments
It’s in your best interest to promote timely payments from your customers. While construction contracts are primarily reliant on trust, there are many things you can do to encourage and facilitate timely payments from your clients. Here are some ideas:
- Use detailed contracts and progress billing
- Vet clients through background research, credit history, references, and public financial records
- Send regular on-time invoices
- Ensure your invoices are aligned with the formats used by your client’s payables department
- Provide multiple payment methods
- File the necessary preliminary notices throughout the project
In the case of construction payments, the adage prevention is better than cure applies. There are many reasons why payments get delayed or skipped, some malicious, some not. It’s in your best interest to ensure that you are doing everything from your end to promote timely payments and that you’re fully protected by rights granted to construction businesses by law.
About the Author:
Patrick Hogan is the CEO of
Handle.com, where they build software that helps contractors and material suppliers with lien management and payment compliance. The biggest names in construction use Handle on a daily basis to save time and money while improving efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Sierra Pacific v. Bradbury Goes Unchallenged: Colorado’s Six-Year Statute of Repose Begins When a Subcontractor’s Scope of Work Ends
November 03, 2016 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation BlogIt’s official: the October 20, 2016 deadline to petition for certiorari to the Colorado Court of Appeals on its decision in Sierra Pacific Industries, Inc. v. Bradbury has passed, so it appears that decision will stand.
In Sierra Pacific, the Court of Appeals held as a matter of first impression that the statute of repose for a general contractor to sue a subcontractor begins to run when a subcontractor’s scope of work is substantially complete, regardless of the status of the overall project. Sierra Pac. Indus., Inc. v. Bradbury, 2016 COA 132, ¶ 28, ___ P.3d ___. The Court of Appeals interpreted the statute of repose in C.R.S. section 13-80-104, which requires that “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of any improvement to real property” must be brought within six years of substantial completion of that improvement. C.R.S. § 13-80-104(1)(a). Recognizing that “an improvement may be [to] a discrete component of an entire project” under Shaw Construction, LLC v. United Builder Services, Inc., 296 P.3d 145 (Colo. App. 2012), the Court of Appeals determined that “a subcontractor has substantially completed its role in the improvement at issue when it finishes working on the improvement.” Sierra Pac., 2016 COA at ¶¶ 20, 28. In doing so, it rejected Sierra Pacific’s argument that the statute could be tolled under the repair doctrine “while others worked to repair [the subcontractor’s] ‘improper installation work and flawed repair work.’” Id. at ¶ 29. Because six years had undisputedly passed since the subcontractor completed its scope of work when Sierra Pacific filed suit against it, the Court of Appeals affirmed the trial court’s order granting the subcontractor’s motion for summary judgment under Section 13-80-104(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & Wilmer Real Estate Litigation BlogMr. Mecklenburg may be contacted at