California Court Broadly Interprets Insurance Policy’s “Liability Arising Out of” Language
December 20, 2017 —
Garret Murai - California Construction Law BlogIn McMillin Mgmt. Servs. v. Financial Pacific Ins. Co., Cal.Ct.App. (4th Dist.), Docket No. D069814 (filed 11/14/17), the California Court of Appeal held that the term “liability arising out of,” as used in an ongoing operations endorsement, does not require that the named insured’s liability arise while it is performing work on a construction project.
In the McMillin case, the general contractor and developer (McMillin) contracted with various subcontractors, including a concrete subcontractor and stucco subcontractor insured by Lexington Insurance Company. Both subcontractors performed their work at the project prior to the sale of the units.
The Lexington policies contained substantively identical additional insured endorsements that provided coverage to McMillin “for liability arising out of your [the named insured subcontractor’s] ongoing operations performed for [McMillin].” Several homeowners filed suit against McMillin, alleging that they had discovered various defective conditions arising out of the construction of their homes, including defects arising out of the work performed by Lexington’s insureds. Lexington argued that there was no potential for coverage in McMillin’s favor under the endorsements because there were no homeowners during the time that the subcontractors’ operations were performing work at the project (the homes closed escrow after the subcontractors had completed their work); thus, McMillin did not have any liability for property damage that took place while the subcontractors’ operations were ongoing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rose Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Coverage Article - To Settle or Not To Settle?
September 20, 2017 —
Tred R. Eyerly - Insurance Law HawaiiMy colleagues Rina Carmel, Karin Aldama and I authored an article entitled, "To Settle or Not to Settle? Bad-Faith Implications in Resolving Underlying Actions." The article appears in the current edition of Coverage, published by the Insurance Coverage Litigation Committee of the ABA. The article is here.
The article addresses the obstacles faced when settling liability claims. The insurer and insured may have fundamental disagreements on whether to settle or how much to pay in settlement. Should the insured contribute to the settlement? Whether the insurer should seek from the policyholder, or the policyholder offers to make, a settlement contribution presents thorny issues, including whether such a contribution can convert an excess demand into a demand within limits—which, in turn, affects the standard for evaluating the insurer’s response to the third-party demand. On the other hand, the policy holder may not want to settle and set a bad precedent.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
"Multiple Claims" Provisions on Contractor's Professional Liability Policy Creates a Trap for Policyholders
May 24, 2021 —
Michael V. Pepe - Saxe Doernberger & VitaIn Berkley Assurance Company v. Hunt Construction Group, Inc., 465 F.Supp.3d 370 (S.D.N.Y., 2020), professional liability insurer Berkley sued its insured, Hunt, a construction management firm, seeking a declaration that it did not owe Hunt a duty to defend and indemnify against breach of contract claims. The United States District Court for the Southern District of New York granted Berkley’s motion for summary judgment and denied Hunt’s motion for partial summary judgment. Among other things, the court held that the policy’s automatic extended reporting period did not apply to Hunt’s first claim. The multiple claims provision barred Hunt’s second claim because the claims were related.
The court’s holding creates a potential trap for policyholders who wait to see how a claim develops before reporting it to their insurance carrier. This case demonstrates that waiting to see how a claim develops can result in a loss of coverage. Policyholders need to be aware of this trap and report all claims and circumstances immediately.
Read the court decisionRead the full story...Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & VitaMr. Pepe may be contacted at
MPepe@sdvlaw.com
Construction Resumes after Defects
June 28, 2013 —
CDJ STAFFWhen inspectors found defective bolts in the construction of the Media Arts Center at L. A. Mission College, the contractor walked off the job. The project had been underway for about eighteen months. After problems were found with welds and bolts, the contractor informed the school that it could not complete the job. The California Division of the State Architect then required inspection of every weld and joint, leading to a dispute as to who was going to pay for it.
At this point, only the first story has been inspected. Although the other two stories must be inspected, the new contractor is about to begin work on the building. James O’Reilly, the executive director for facilities, planning and development, said that “the main focus is on fixing the defective issues and getting construction completed so we can serve the Mission campus.” Still at question is how much SMC Construction received before they walked off the job.
Read the court decisionRead the full story...Reprinted courtesy of
OSHA ETS Heads to Sixth Circuit
December 13, 2021 —
George Morrison - White and Williams LLPOn November 16, 2021, the U.S. Court of Appeals for the Sixth Circuit was selected during the Judicial Panel on Multidistrict Litigation’s lottery to hear the multiple consolidated challenges to the recent COVID-19 Emergency Temporary Standard (ETS) issued by the Occupational Safety and Health Administration (OSHA). OSHA is permitted to issue an ETS if the agency arrives at the conclusion that a “grave danger” to worker safety exists. An ETS does not go through the typical notice-and-comment period that federal regulations usually follow.
Inheriting the Fifth Circuit’s recent nationwide stay on implementation and enforcement of the ETS, the Sixth Circuit will decide whether the stay should be “modified, revoked, or extended” in the short term. Early this morning, OSHA filed an emergency motion to dissolve the Fifth Circuit’s stay of the vaccine mandate with the Sixth Circuit. OSHA argued, among other things:
- The Fifth Circuit erred in holding “that OSHA lacked statutory authority to address the grave danger of COVID-19 in the place on the ground that COVID-19 is caused by a virus and also exists outside of the workplace” because “[t]hat rationale has no basis in the statutory text.”
- The Fifth Circuit erred in finding the ETS both over- and underinclusive because “OSHA recounted extensive empirical data showing that all employees can transmit COVID-19 in the workplace and that COVID-19 has spread in a vast variety of workplace.”
- The “petitioners have not shown that their claimed injuries outweigh the interests in protecting employees from a dangerous virus while this litigation proceeds . . . . These claimed injuries do not justify delaying the [ETS] that will save thousands of lives and prevent hundreds of thousands of hospitalizations.”
Read the court decisionRead the full story...Reprinted courtesy of
George Morrison, White and Williams LLPMr. Morrison may be contacted at
morrisong@whiteandwilliams.com
Independent Contractor v. Employee. The “ABC Test” Does Not Include a Threshold Hiring Entity Test
October 03, 2022 —
Garret Murai - California Construction Law BlogIn 2018, in Dynamex Operations West, Inc. v. Superior Court, 4 Cal.5th 903 (2018), the California Supreme Court overturned nearly thirty years of jurisprudence governing the manner in which workers are classified as employees or independent contractors. The Dynamex decision replaced the “Borello test,” derived from a case of the same name, S.G. Borello & Sons, Inc. v. Department of Industrial Relations, 48 Cal.3d 341 (1989), in which the California Supreme Court at the time set forth a variety of factors to be considered when determining whether a worker was an employee or independent contractor.
The Dynamex decision replaced with the “Borello test” with the “ABC test.” Under the ABC test, a worker can be deemed an independent contractor if three conditions are met:
- The worker is free from the control and direction of the hiring entity in connection with the performance of the work, both under the contract for the performance of the work and in fact;
- The worker performs work that is outside the usual course of the hiring entity’s business; and
- The worker is customarily engaged in an independent established trade, occupation, or business
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Damage Caused Not by Superstorm Sandy, But by Faulty Workmanship, Not Covered
December 10, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court adopted the Report and Recommendations (R&R) of the magistrate judge, finding there was no coverage for faulty workmanship in replacing a roof for an apartment complex. Burlington Ins. Co. v. PCGNY Corp., 2024 U.S. Dist. LEXIS 167814 (S.D. N. Y. Sept. 16, 2024).
Skyline Restoration was hired by the apartment complex to replace the apartments' roofs. Skyline subcontracted with PCGNY Corporation. The roofs were later damaged during Superstorm Sandy. Defendant Affiliated FM Insurance Company ("Affilliated"), a subrogee of the owner of the apartment complex, sued Skyline for defective, faulty and unworkmanlike removal and replacement of the roofs. Skyline filed a Third-Party Complaint against PCGNY.
Plaintiff Burlington Insurance Company filed this coverage action against Skyline, Affiliated, PCGNY and others seeking a declaration that it had no duty to defend and/or indemnify PCGNY and/or Skyline, and that it was permitted to withdraw from the defense of PCGNY. Burlington filed a motion for summary judgment. The motion was referred to the magistrate judge who recommended that Burlington be granted a declaration that it had no duty to defend or indemnify PCGNY or Skyline and that it be allowed to withdraw from the defense of PCGNY in the underlying case.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Do We Really Want Courts Deciding if Our Construction Contracts are Fair?
March 19, 2015 —
Christopher G. Hill – Construction Law MusingsAs I posted recently, the Virginia General Assembly has passed, and I can see no reason why the governor won’t sign, a bill that would
essentially invalidate preemptive contractual waivers of lien rights as they relate to subcontractors and material suppliers. It does not apply to General Contractors, but it is a step in what many (including those attorneys that represent subcontractors and suppliers) believe is the right direction.
Of course, as soon as I posted last week, my friend and colleague
Scott Wolfe (@scottwolfejr) commented on that post and then
gave his two cents worth at his Zlien blog. The gist of the comments here at Musings and the post over at his blog was essentially that these contractual provisions were inherently unfair and therefore should be abolished because of both a relative disparity in leverage between the Owner or GC and the Subcontractor when it comes to negotiations and the fact that subcontractors often don’t read their contracts or
discuss them with a construction attorney prior to signing them. I hear this first of his arguments often when I am reviewing a contract after the fact and a client or potential client acts surprised that a provision will be enforced and the courts of the Commonwealth of Virginia will actually enforce them. As to Scott’s second reason, I have always warned here at Musings that
you should read your contracts carefully because they will be the law of your business relationship in the future.
The first of his two points is more interesting and in some ways more easily supported. However, where we are speaking of contracts between businesses where both sides are bound by the terms of the contract, it begs the question of whether in seeking to make contracts more “fair” we could add a layer of uncertainty that could cause more problems than it solves. Do we really want courts stepping in after the fact to renegotiate the terms of a deal that was struck months or possibly years before because one judge believes that the deal was too one sided? Do we really need such “Monday morning quarterbacking?” Is one person’s idea of “fair” better than another’s when both parties to the contract had the full ability to read, negotiate and possibly reject the deal long ago? Personally, I think that the answer to these questions is, in all but the most egregious cases or where the legislatures have stepped in adding certainty (whether to the good or bad), “No.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at