South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Navigating the New Landscape: How AB 12 and SB 567 Impact Landlords and Tenants in California
March 11, 2024 —
Sharon Oh-Kubisch - Kahana FeldThere are various changes in the Landlord-Tenant laws in CA that became effective in 2024.
For the purposes of this article, I wanted to focus on Assembly Bill (AB) 12 and Senate Bill (SB) 567 only.
Governor Gavin Newsom recently signed AB 12 into law, a legislation that limits the amount landlords can charge for security deposits to just one month’s rent for unfurnished apartments. While the law aims to make housing more accessible, it raises several concerns for landlords and tenants alike. AB 12, was authored by Assemblyman Matt Haney, D-San Francisco; it passed both the Senate and the Assembly houses in September. The legislation introduces a notable shift from existing law, under which landlords can charge up to two months’ rent for an unfurnished unit and three months’ rent for a furnished one. This exception does not apply when the prospective tenant is a military service member, however.
Read the court decisionRead the full story...Reprinted courtesy of
Sharon Oh-Kubisch, Kahana FeldMs. Oh-Kubisch may be contacted at
sokubisch@kahanafeld.com
California Contractors: Amended Section 7141.5 Provides Important License Renewal Safety Net
July 25, 2021 —
Amy L. Pierce, Mark A. Oertel, John Lubitz & Adam B. Wiens - Lewis BrisboisUnder California’s Contractors State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., contractors’ licenses expire two years from the last day of the month in which the license was issued or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days in advance of the date the license is set to expire. Even with various controls in place, mistakes happen and a renewal application filing deadline can be missed.
During the August 5-6, 2019 Executive, Licensing, and Legislative Committee Meetings, the CSLB discussed proposed amendments to Section 7141.5 to reduce both the burden on it to review applications for retroactive renewal of a license that had not been timely submitted and to provide contractors with some relief from the high burden to establish “the failure to renew was due to circumstances beyond the control of the licensee.” Not long after, the CSLB’s Board of Directors gave staff approval to seek an author for the bill and, on September 29, 2020, Governor Newsom signed Senate Bill 1474 into law, which includes the CSLB’s proposed amendments to Section 7141.5, effective January 1, 2021.
Reprinted courtesy of
Amy L. Pierce, Lewis Brisbois,
Mark A. Oertel, Lewis Brisbois,
John Lubitz, Lewis Brisbois and
Adam B. Wiens, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Mr. Wiens may be contacted at Adam.Wiens@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Is Holding Back the Economy
February 28, 2018 —
Noah Smith - BloombergChanges in contracts and rules could make the sector a lot more efficient.
The question of whether to
prioritize jobs or economic efficiency is always difficult. Nowhere is this more of a dilemma than in the construction industry.
In a world of rapid technological disruption, construction is a rock of solidity to which many blue-collar workers can cling. The industry still employs about 7 million workers in the U.S.
The job doesn’t change that much from decade to decade. It’s a big broad occupation, unlike social-media marketing or other new niche jobs, so it allows working-class people to minimize the time and effort they spend building for a career. And workers get trained on the job, without years of college.
What’s more, construction workers are
mostly male. To the degree this is a result of sexism, that’s bad. But it also means that the construction industry employs lots of men, at a time when they haven’t been doing so well in the jobs department.
Read the court decisionRead the full story...Reprinted courtesy of
Noah Smith, Bloomberg
Limiting Liability: Three Clauses to Consider in your Next Construction Contract
June 25, 2019 —
Tara Lynch - Gordon & Rees Construction Law BlogIn your next contract, consider including some (or all!) of the following clauses to limit your liability and maximize your profits.
Waiver of Consequential Damages
While a proven breach of contract will leave a design professional or contractor exposed to direct or compensatory damages, a waiver of consequential damages will help “stop the bleeding” and protect the design professional or contractor from paying every damage that might flow from the breach. Consequential damages include those damages which indirectly flow from the breach of contract, for example, lost rents, lost profits, lost use, lost opportunity, loss of employee productivity, and damages to reputation.
The American Institute of Architects (AIA) has included a mutual waiver of consequential damages in its sample A201 for over 20 years. The AIA provision includes a definition of consequential damages which are waived, including many of the examples cited above. However, the AIA waiver of consequential damages clause carves out an exception for liquidated damages to the owner. Prudent design professionals and contractors will strike this exception so as not to render the clause meaningless. A well-drafted waiver clause will be mutual, will define which damages are consequential versus direct, and will not contain exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
Tara Lynch - Gordon & Rees Scully MansukhaniMs. Lynch may be contacted at
tlynch@grsm.com
Traub Lieberman Attorneys Recognized in the 2025 Edition of The Best Lawyers in America®
September 09, 2024 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2025 edition of The Best Lawyers in America®. In addition, seven attorneys have been included in the 2025 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2025 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants, Product Liability Litigation – Defendants
St. Petersburg, FL
- Lauren S. Curtis – Insurance Law
- Scot E. Samis – Appellate Practice
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Requesting an Allocation Between Covered and Non-Covered Damages? [Do] Think Twice, It’s [Not Always] All Right.
October 12, 2020 —
Todd Likman - Colorado Construction LitigationAs is often the case in construction defect and other insurance defense litigation, a plaintiff’s claims for relief typically encompass both covered and uncovered damages. Obviously, it is in the insured’s best interests to have as many damages covered by insurance as possible. From the insurer’s perspective and against the backdrop of owing duty of good faith and fair dealing to its insureds, however, it is generally better to have an allocation of covered vs. non-covered damages. This places the insurer, insured, and insurance retained defense counsel in a difficult position.
A recent opinion from U.S. District Court for the District of Colorado, Rockhill Ins. Co. v. CFI-Global Fisheries Mgmt, Civil Action No. 1:16-CV-02760-RM-MJW, 2020 U.S. Dist. LEXIS 35209 (D. Colo. Mar. 2, 2020), sheds light on the issue, even though some may feel it only further muddies already murky waters.
Rockhill involved review of an arbitration proceeding that property-owner, Heirloom I, LLC (“Heirloom”) filed against CFI-Global Fisheries Management (“CFI”). Rockhill Insurance Company (“Rockhill Insurance”) was asked to defend the arbitration as CFI’s professional and general liability insurer. At issue in the arbitration was Heirloom’s claim that CFI defectively designed and constructed a fisheries enhancement that was destroyed by natural processes four times in three years.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Likman, Higgins, Hopkins, McLain & RoswellMr. Likman may be contacted at
likman@hhmrlaw.com
NTSB Outlines Pittsburgh Bridge Structure Specifics, Finding Collapse Cause Will Take Months
February 21, 2022 —
Tom Ichniowski - Engineering News-RecordOfficials in Pennsylvania are moving forward on building a replacement for the Fern Hollow Bridge in Pittsburgh, which collapsed on Jan. 28, selecting a team of HDR Inc. and Swank Construction to design and construct the new structure, and the approval of $25.3 million in federal funds for the project.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of