San Francisco Bay Bridge Tower Rod Fails Test
May 20, 2015 —
Beverley BevenFlorez-CDJ STAFFThe San Francisco Chronicle reported that “[o]ne of the steel rods anchoring the tower of the new Bay Bridge eastern span has failed a key integrity test, suggesting it became corroded and broke during years when it was soaking in water.” Hundreds of other rods have also been steeped in water, which raises concerns about how stable the bridge might be during a major earthquake.
Gareth Lacy, a Transportation Agency spokesperson, told the Chronicle that “[t]hey are investigating why one seismic rod at the base at the tower moved when it was pulled by the machine,” Lacy said. “It did not carry the expected load, and the next step is to remove it to fully investigate its condition.”
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Trench Collapse Kills Two
July 30, 2019 —
Engineering News-RecordFederal safety officials are investigating the April 16 collapse of a trench that killed two construction workers in northern Colorado. The two men—Cristopher Lee Ramirez, 26, and Jorge Baez Valadez, 41—were installing utilities at a site being developed by D.R. Horton Express Homes in Windsor, Colo., when they were trapped by soil and rocks in the 15-ft-deep trench. The rescue attempt lasted seven hours and involved small shovels because of fears of a second collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
NJ Supreme Court Declines to Review Decision that Exxon Has No Duty to Indemnify Insurers for Environmental Liability Under Prior Settlement Agreement
November 29, 2021 —
Patricia B. Santelle & Laura Rossi - White and WilliamsOn November 1, 2021, in a single-sentence Order, the Supreme Court of New Jersey denied a request for review of a decision that ExxonMobil Corporation (Exxon) did not have to indemnify certain of its insurers over environmental liabilities as required by a previous settlement agreement. The case, entitled Home Insurance Company v. Cornell-Dubilier Electronics Incorporated, et al., has a unique and convoluted procedural history but, in short, the denial of review leaves standing a holding by the intermediate appellate court that the insurers’ “untimely notice actually prejudiced Exxon, violated the no-prejudice rule, and breached the covenant of good faith and fair dealing.” The court declined to consider the question framed by the insurers: whether the importance of enforcing settlement agreements outweighs New Jersey’s entire controversy doctrine.
The matter dated back almost thirty years, when the New Jersey Department of Environmental Protection notified the Appearing London Market Insurers (ALMI) of the potential liability of Cornell-Dublier Electronics (CDE), a former indirect subsidiary of Exxon, for pollution at a site in New Jersey. Coverage litigation followed in New Jersey, which ALMI defended under policies issued to CDE. Exxon was not named in the CDE suit nor were the policies which ALMI issued to Exxon at issue in that case; Exxon instead had its own pollution coverage case pending in New York. In June 2000, Exxon and its insurers, including ALMI, entered into a settlement agreement which (a) required Exxon to indemnify the insurers for any environmental liability claims involving its subsidiaries, and (b) provided for application of New York substantive law and litigation in New York City court for any dispute between the parties under it.
Reprinted courtesy of
Patricia B. Santelle, White and Williams and
Laura Rossi, White and Williams
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Ms. Rossi may be contacted at rossil@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Executives Should Be Dusting Off Employee Handbooks
January 03, 2022 —
Adam E. Richards & Andrew Zelman - Construction ExecutiveFor most businesses—large and small—the importance of maintaining and updating an employee handbook that sets forth a uniform set of company policies cannot be understated. The construction industry, which is seemingly plagued by a never-ending labor shortage, necessitating construction executives having to grapple with pandemic-related workplace issues and challenges, is not exempt from the benefits of a thorough, well-formed handbook.
The employee handbook should be a window into the soul of a business. Even though annual updates are appropriate, they seldom occur. To say a lot has happened over the last few years barely begins to scratch the surface. Particularly, during the COVID-19 pandemic, construction executives and human resources professionals within construction-related businesses throughout the country have been forced to evaluate business models, values and cultures in furtherance of deciding where and how to evolve.
Once those decisions are made, the employee handbook is deserving of time and attention. Reflecting the evolution of your construction business is only part of the overall plan; however, demonstrating compliance with new laws is equally important.
Reprinted courtesy of
Adam E. Richards & Andrew Zelman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Court Determines Duty to Defend Construction Defect Claims
March 22, 2021 —
Tred R. Eyerly - Insurance Law HawaiiGiven the underlying allegations of damage to personal property, the court determined the insurer had a duty to defend. Certain Underwriters at Lloyd's London v. Metropolitan Builders, Inc., 2019 Ill. App. LEXIS 979 (Ill. Ct. App. Dec. 18, 2019).
Metropolitan was hired as the general contractor for construction, renovation and demolition at contiguous properties - the 1907 Property, 1909 Property, and 1911 Property. During construction activities, the structures on the 1907 Property and 1909 Property collapsed. The existing structures on the properties were later deemed unsafe and were demolished by the city of Chicago.
AIG insured the owner of the buildings and paid over $1.8 million for repairs and associated expenses arising from the collapse. AIG then invoked its rights of subrogation against Metropolitan by filing suit. Metropolitan tendered the suit to its insurer, Lloyd's, who denied coverage and filed for a declaratory judgment. The trial court found the underlying complaint alleged property damage, but not an occurrence. Summary judgment was awarded to Lloyd's.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contrasting Expert Opinions Result in Denial of Cross Motions for Summary Judgment
February 27, 2023 —
Tred R. Eyerly - Insurance Law HawaiiGiven the opposing experts' contradictory reports, the court denied both the insured and insurer's motions for summary judgment regarding coverage for a pipe leak. Pronti v. Hanover Ins. Co., 2022 U.S. Dist. LEXIS 222306 (W.D. N. Y. Dec. 9, 2022).
The insured had a swimming poll and spa, which functioned using a subsurface plumbing system, covered with concrete decking. A subsurface pipe began to leak, preventing the pool from properly functioning. The insureds gave notice under their homeowners' policy and contended that significant portions of the pool, spa, concrete decking and other landscaping had to be torn out to do repairs. The insurer retained an expert, Sarah G. Byer, a structural engineer, to investigate. The parties agreed that the pipe had a leak, but disputed if the location of the leak was specifically identified.
The parties also disputed the cause of the leak. Byer found that the most likely cause was deterioration incurred over the pipe's lifetime based on the age of the plumbing system and Byer's personal observation of the pipe. Byer further stated that the physical qualities of flexible PVC piping made it susceptible to damage from chlorine and water over time.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Maryland Contractor Documents its Illegal Deal and Pays $2.15 Million to Settle Fraud Claims
January 07, 2015 —
Craig Martin- Construction Contractor Advisor BlogWhy would a contractor create a contract for illegal work? I really don’t know.
Late last year, the FBI announced that a Maryland contractor, Forrester Construction Company, agreed to pay $2.15 million dollars to resolve a criminal investigation into alleged fraud in connection with the use of disadvantaged business enterprises involving more than $145 million of District of Columbia government contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com