A jury in Manhattan on Thursday found the developer, billionaire Ng Lap Seng, guilty of all six charges he faced, including conspiracy, bribery and money laundering, in the biggest UN corruption scandal since the oil-for-food program in the early 2000s. Prosecutors claimed Ng funneled hundreds of thousands of dollars to former UN General Assembly President John Ashe and other officials.
Read the court decisionRead the full story...Reprinted courtesy of
Bob Van Voris, Bloomberg
Assembly Bill 1701 Contemplates Broader Duty to Subcontractor’s Employees by General Contractor
August 17, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. – Chapman Glucksman Dean Roeb & BargerAB 1701 recently passed the Assembly and is pending in the Senate’s Labor and
Industrial Relations and Judiciary Committees. The Bill, if signed by the Governor, would
create a new section in the California Labor Code (Section 218.7) making “direct contractors” –
defined as a contractor “making or taking a contract in the state for the erection, construction,
alteration, or repair of a building, structure, or other private work” – liable for wages a
subcontractor or sub-subcontractor fails to pay to its employee for work included in the general
contractor’s contract with the project owner.
Under the new law, direct contractors would be liable for up to one year from the date of
completion of the work for unpaid wages, fringe benefits, health and welfare benefits, and
pension fund contributions, including interest and state tax payments owed to a subcontractor’s
employee. The employee, however, would not be able to recover penalties or liquidated
damages from the general contractor.
AB 1701 would give the employee, Labor Commissioner, or a joint labor-management
cooperation committee the right to enforce the direct contractor’s liability through a civil action.
It would also extend to third parties who are owed fringe or other benefit payments or
contributions on the employee’s behalf. Pursuant to the proposed language of the new statute, a
prevailing plaintiff in such an action would be entitled to their reasonable attorneys’ fees and
costs, including expert witness fees.
Although Labor Code § 218.7 would impose certain obligations on the subcontractor to
provide the direct contractor with relevant project and payroll records, the subcontractor’s failure
to comply with those obligations does not relieve the direct contractor from liability.
Impact
AB 1701’s apparent purpose is to protect employees, an undeniably important legislative
goal. However, if passed, the bill could greatly increase general contractors’ exposure when
subcontracting work and their cost of doing business. Especially because the new law would not
impact existing laws requiring a direct contractor to timely pay a subcontractor.
As a result, many coalitions against AB 1701 stress the halting effect this could have on
the construction industry as a whole, particularly private construction, which is not as heavily
regulated as public works.
CGDRB will continue to monitor this Bill and provide updates as developments occur.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
General Contractor Supporting a Subcontractor’s Change Order Only for Owner to Reject the Change
December 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe opinion in Westchester Fire Ins. Co, LLC v. Kesoki Painting, LLC, 260 So.3d 546 (Fla. 3d DCA 2018) leads to a worthy discussion because it involves a common scope of work occurrence on construction projects involving a general contractor and subcontractor. The contractor submits a subcontractor’s change order request to the owner and the owner rejects the change order. What happens next is a scope of work payment dispute between the general contractor and subcontractor. Yep, a common occurrence.
In this case, a general contractor hired a subcontractor to perform waterproofing and painting. A scope of work issue arose because the specifications did not address how the window gaskets should be cut and then sealed. The owner wanted the window gaskets cut at a 45-degree angle and the subcontractor claimed this resulted in increased extra work. The general contractor agreed and submitted a change order to the owner to cover these costs. The owner rejected the change order claiming it was part of the general contractor’s scope of work even though the cutting of window gaskets at a 45-degree angle was not detailed in the specifications.
After the subcontractor filed a suit against the general contractor’s payment bond surety, the project architect further rejected the change order because gasket cutting was part of the specification requirements. (Duh! What else was the architect going to say? It was not going to concede there was an omission that resulted in a change order to the owner, right?)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida trigger
August 04, 2011 —
CDCoverage.comIn Mid-Continent Casualty Co. v. Siena Home Corp., No. 5:08-CV-385-Oc-10GJK (M.D. Fla. July 8, 2011), insured residential real estate developer Siena was sued by homeowners seeking damages for moisture penetration property damage resulting from exterior wall construction defects. Siena’s CGL insurer Mid-Continent filed suit seeking a declaratory judgment of no duty to defend or indemnify in part on the basis that the alleged “property damage” did not manifest during the Mid-Continent policy period.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Do We Really Want Courts Deciding if Our Construction Contracts are Fair?
March 19, 2015 —
Christopher G. Hill – Construction Law MusingsAs I posted recently, the Virginia General Assembly has passed, and I can see no reason why the governor won’t sign, a bill that would
essentially invalidate preemptive contractual waivers of lien rights as they relate to subcontractors and material suppliers. It does not apply to General Contractors, but it is a step in what many (including those attorneys that represent subcontractors and suppliers) believe is the right direction.
Of course, as soon as I posted last week, my friend and colleague
Scott Wolfe (@scottwolfejr) commented on that post and then
gave his two cents worth at his Zlien blog. The gist of the comments here at Musings and the post over at his blog was essentially that these contractual provisions were inherently unfair and therefore should be abolished because of both a relative disparity in leverage between the Owner or GC and the Subcontractor when it comes to negotiations and the fact that subcontractors often don’t read their contracts or
discuss them with a construction attorney prior to signing them. I hear this first of his arguments often when I am reviewing a contract after the fact and a client or potential client acts surprised that a provision will be enforced and the courts of the Commonwealth of Virginia will actually enforce them. As to Scott’s second reason, I have always warned here at Musings that
you should read your contracts carefully because they will be the law of your business relationship in the future.
The first of his two points is more interesting and in some ways more easily supported. However, where we are speaking of contracts between businesses where both sides are bound by the terms of the contract, it begs the question of whether in seeking to make contracts more “fair” we could add a layer of uncertainty that could cause more problems than it solves. Do we really want courts stepping in after the fact to renegotiate the terms of a deal that was struck months or possibly years before because one judge believes that the deal was too one sided? Do we really need such “Monday morning quarterbacking?” Is one person’s idea of “fair” better than another’s when both parties to the contract had the full ability to read, negotiate and possibly reject the deal long ago? Personally, I think that the answer to these questions is, in all but the most egregious cases or where the legislatures have stepped in adding certainty (whether to the good or bad), “No.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...
Read the full story, March 2014 Article... Read the court decisionRead the full story...Reprinted courtesy of
Gilbane Project Exec Completes His Mission Against the Odds
January 19, 2017 —
Debra K. Rubin - Engineering News-RecordAfghanistan’s new Ministry of Defense headquarters in Kabul was supposed to symbolize the nation’s future—and U.S. support in that effort—as a self-sustaining, sophisticated structure akin to the Pentagon. But U.S. funding shortfalls stretched an anticipated 18-month project, which began in 2009, into years. While experienced in running projects in an underdeveloped country in which terror attacks and unstable regional politics are routine, Gilbane Building Co. Project Executive Michael P. Sousa wanted no part of this one in 2013, when he first toured it. “The structure was in a severe state of disrepair and riddled with poor construction,” he says, terming it “an embarrassment” to the U.S. government.
Read the court decisionRead the full story...Reprinted courtesy of
Debra K. Rubin, ENRMs. Rubin may be contacted at
rubind@enr.com
Revamp to Nationwide Permits Impacting Oil and Gas Pipeline, Utility and Telecom Line Work
March 29, 2021 —
Alex P. Prochaska, Jones Walker LLP - ConsensusDocsTo avoid delay costs and penalties, contractors involved in pipeline and utilities construction maintenance, repair and removal need to understand how the 43 year old Nationwide Permit (NWP) regime has changed specific to the NWP 12 and what is now required for compliance. This change is important for contractors who construct, maintain, or repair pipelines that cross or impact waters of the United States, including wetlands. NWPs are a useful tool to streamline construction of a pipeline project, but it is important for contractors to know when certain terms and conditions still apply to the particular NWP and those that have been eliminated.
On January 13, 2021, the United States Army Corps of Engineers (the Corps) published a final rule that reissued and modified twelve existing NWPs and issued four new NWPs that will take effect on March 15, 2021.1 The remaining 40 NWPs that were not reissued or modified under this rule will continue under the general conditions and definitions of the January 6, 2017 final rule.
Read the court decisionRead the full story...Reprinted courtesy of
Alex P. Prochaska, Jones Walker LLPMr. Prochaska may be contacted at