Owners Bound by Arbitration Clause on Roofing Shingles Packaging
December 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesIn today’s age, you are probably familiar with terms such as a shrinkwrap contract (terms and conditions), which is a boilerplate contract included with a retained product, or a clickwrap contract (terms and conditions), which is generally a boilerplate contract that is digitally accepted when purchasing software or an electronic product. These are are boilerplate terms from manufacturers or vendors of products or software. Arbitration provisions in these types of agreements have generally found to be enforceable.
In the recent ruling by the Eleventh Circuit Court of Appeals in Dye v. Tamko Building Products, Inc., 2018 WL 5729085 (11th Cir. 2018), the court held that an arbitration provision included in a product-purchase limited warranty agreement on the package of every roofing shingles binds a homeowner to arbitrating disputes over the opened and retained product with the manufacturer, irrespective of whether the shingles were purchased by an owner’s roofer. The shingles do not have to be purchased and opened by the owner for the arbitration provision to apply. If the roofer uses or retained the shingles for purposes of the owner’s home, such knowledge of the product-purchase limited warranty agreement on the packaging of the shingles is imputed to the owner (end-user of the shingles).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Remodel Leads to Construction Defect Lawsuit
October 16, 2013 —
CDJ STAFFThe Sacramento, California law firm Anderson Shoech has announced that it will be filing a construction defect lawsuit concerning a single-family home in Sonora, California. The remodel is alleged to have lead to roof leaks and mold growth. Anderson Schoech will have the home inspected by a general contractor who will be retained as an expert witness.
Read the court decisionRead the full story...Reprinted courtesy of
Second Circuit Court Differentiates the Standard for Determining Evident Partiality for a Neutral Arbitrator and a Party-Appointed Arbitrator
August 07, 2018 —
Celia B. Waters - Saxe Doernberger & Vita, P.C.On June 7, 2018, the Second Circuit Court in Certain Underwriting Members of Lloyds of London v. Fla., Dep’t of Fin. Servs.,1 held that a party-appointed arbitrator should not be held to the same standard as a neutral arbitrator. The Court vacated a district court’s order vacating an arbitral award in a reinsurance dispute between Insurance Company of Americas (“ICA”) and Certain Underwriting Members of Lloyds of London (“Underwriters”). The case was one of first impression for the Second Circuit on how to determine the standard of evident partiality challenged to a party-appointed arbitrator.
Underwriters reinsured ICA under a series of treaties. The treaties each contained an arbitration clause requiring that disputes be adjudicated by an arbitration panel consisting of three members: one party-appointed arbitrator for each party, and a neutral. The clause required only that the arbitrators “be active or retired disinterested executive officers of insurance or reinsurance companies or Lloyd’s London Underwriters.”
Read the court decisionRead the full story...Reprinted courtesy of
Celia B. Waters, Saxe Doernberger & Vita, P.C.Ms. Waters may be contacted at
cbw@sdvlaw.com
New Safety Requirements added for Keystone Pipeline
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAfter learning about construction defects on the “southern leg of the Canada-to-Texas project,” safety regulators have added two additional conditions “on construction of TransCanada Corp.’s Keystone XL oil pipeline,” according to Claims Journal. The defects, which have been fixed, included “high rates of bad welds, dented pipe and damaged pipeline coating.”
The first condition requires “TransCanada to hire a third-party contractor chosen by the pipeline safety agency to monitor the construction” and report to the U.S. government, while the second condition requires “TransCanada to adopt a quality management program.”
Both conditions were “buried near the end of the 26 appendices in a voluminous environmental impact statement on Keystone XL released by the State Department on Jan. 31.”
Read the court decisionRead the full story...Reprinted courtesy of
Pulte Home Corp. v. CBR Electric, Inc.
August 24, 2020 —
Michael Velladao - Lewis BrisboisIn Pulte Home Corp. v. CBR Electric, Inc., 50 Cal.App.5th 216 (June 10, 2020), the California Court of Appeal reversed the trial court’s entry of judgment in favor of six subcontractors with respect to an equitable subrogation lawsuit filed by St. Paul Mercury Insurance Company (“St. Paul”). St. Paul filed the lawsuit after defending Pulte Home Corp. (“Pulte”) against two construction defect lawsuits. The lawsuit contended that St. Paul was entitled to seek recovery of defense costs incurred on behalf of Pulte based on equitable subrogation. St. Paul relied on the indemnity clauses in each of the subcontracts, and argued that the subcontractors had breached their contracts with Pulte. As such, each subcontractor was obligated to pay an equitable share of the defense of the construction defect lawsuits relating to their work on the homes at issue in such lawsuits. The trial court ruled against St. Paul and held that the subcontractors’ failure to pay defense costs did not “cause” the homeowners’ claims, such that there was no causal connection supporting a claim for equitable subrogation. In addition, the trial court found that “equitable subrogation was an all-or-nothing claim, meaning it required a shifting of the entire amount of defense costs to the subcontractors on a joint and several basis and did not allow for an apportionment of costs among the defendant subcontractors.”
In reversing the trial court’s decision, the Court of Appeal reasoned that St. Paul stood in the shoes of Pulte and was limited to pursuing recovery from the subcontractors based on the same rights as afforded to Pulte under the subcontracts. The Court of Appeal noted that St. Paul was seeking reimbursement of defense costs from the subcontractors based on the theory that they were contractually liable for paying an equitable share of defense costs. The Court of Appeal also noted that St. Paul’s claim was not premised on the contention that the subcontractors’ failure to pay defense costs caused the homeowners’ claims. Rather, St. Paul’s claim was premised on the subcontractors’ breach of their defense duty owed to Pulte under the indemnity clauses in their subcontracts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
New York Revises Retainage Requirements for Private Construction Contracts: Overview of the “5% Retainage Law”
January 22, 2024 —
Levi W. Barrett, Patrick T. Murray, Skyler L. Santomartino & Mark A. Snyder - Peckar & Abramson, P.C.On November 17, 2023, the State of New York enacted the “5% Retainage Law.” This legislation effectively limits the amount of retainage that can be held from general contractors and subcontractors to no more than 5%. It applies to many but not all construction contracts. In addition, the new law revises late stage billing requirements, enabling contractors to invoice for retainage at substantial completion. Previously, the parties to a construction contract were free to negotiate any retainage amount, limited only by an unspecified “reasonable amount” that would be released as the parties contractually set forth.
Summary
The new law amends Sections 756-a and 756-c of the General Business Law (part of Article 35E of the GBL, known as the “Prompt Pay Act”), and applies to private construction contracts “where the aggregate cost of the construction project, including all labor, services, materials and equipment to be furnished, equals or exceeds one hundred fifty thousand dollars.”
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Patrick T. Murray, Peckar & Abramson, P.C.,
Skyler L. Santomartino, Peckar & Abramson, P.C. and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Murray may be contacted at pmurray@pecklaw.com
Mr. Santomartino may be contacted at ssantomartino@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Gilbane Project Exec Completes His Mission Against the Odds
January 19, 2017 —
Debra K. Rubin - Engineering News-RecordAfghanistan’s new Ministry of Defense headquarters in Kabul was supposed to symbolize the nation’s future—and U.S. support in that effort—as a self-sustaining, sophisticated structure akin to the Pentagon. But U.S. funding shortfalls stretched an anticipated 18-month project, which began in 2009, into years. While experienced in running projects in an underdeveloped country in which terror attacks and unstable regional politics are routine, Gilbane Building Co. Project Executive Michael P. Sousa wanted no part of this one in 2013, when he first toured it. “The structure was in a severe state of disrepair and riddled with poor construction,” he says, terming it “an embarrassment” to the U.S. government.
Read the court decisionRead the full story...Reprinted courtesy of
Debra K. Rubin, ENRMs. Rubin may be contacted at
rubind@enr.com
Limiting Liability: Three Clauses to Consider in your Next Construction Contract
June 25, 2019 —
Tara Lynch - Gordon & Rees Construction Law BlogIn your next contract, consider including some (or all!) of the following clauses to limit your liability and maximize your profits.
Waiver of Consequential Damages
While a proven breach of contract will leave a design professional or contractor exposed to direct or compensatory damages, a waiver of consequential damages will help “stop the bleeding” and protect the design professional or contractor from paying every damage that might flow from the breach. Consequential damages include those damages which indirectly flow from the breach of contract, for example, lost rents, lost profits, lost use, lost opportunity, loss of employee productivity, and damages to reputation.
The American Institute of Architects (AIA) has included a mutual waiver of consequential damages in its sample A201 for over 20 years. The AIA provision includes a definition of consequential damages which are waived, including many of the examples cited above. However, the AIA waiver of consequential damages clause carves out an exception for liquidated damages to the owner. Prudent design professionals and contractors will strike this exception so as not to render the clause meaningless. A well-drafted waiver clause will be mutual, will define which damages are consequential versus direct, and will not contain exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
Tara Lynch - Gordon & Rees Scully MansukhaniMs. Lynch may be contacted at
tlynch@grsm.com