Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses
October 24, 2022 —
Amanda L. Marutzky - ConsensusDocsSince October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.
The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.
Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda L. Marutzky, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Ms. Marutzky may be contacted at
amarutzky@watttieder.com
Reconciling Prompt Payments and Withholding of Retention Payments
March 30, 2016 —
Eric J. Rollins, Esq. – Newmeyer & Dillion, LLPIt is common in California for the owners of a project to make monthly payments to a contractor for work as it is completed, but withhold a certain percentage as a guarantee of future satisfactory performance. Contractors almost always pass these withholdings on to their subcontractors. Unsurprisingly, disputes can arise regarding when the withheld retentions must be paid.
Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after receiving all or part of a retention payment. However, an exception exists -- a direct contractor may withhold from the retention paid to a subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount, whenever a “good faith dispute exists between the direct contractor and a subcontractor.” (See Cal. Civ. Code, § 8814, subd. (c).) The problem with the statute is that it offers no help in defining a “good faith dispute,” and the California courts have historically not provided much guidance either. Can a “good faith dispute” be any dispute between the contracting parties, e.g., a dispute regarding change orders, mismanagement, etc.? Or must the dispute relate specifically to the retention? Unfortunately for California litigants, the answer may depend on the appellate district in which the parties find themselves.
Read the court decisionRead the full story...Reprinted courtesy of
Eric J. Rollins, Esq., Newmeyer & Dillion, LLPMr. Rollins may be contacted at
eric.rollins@ndlf.com
Haight’s John Arbucci and Kristian Moriarty Selected for Super Lawyers’ 2020 Southern California Rising Stars
July 20, 2020 —
T. Giovanni “John” Arbucci & Kristian B. Moriarty - Haight Brown & BonesteelCongratulations to attorneys T. Giovanni “John” Arbucci and Kristian Moriarty who were selected to the Super Lawyers 2020 Southern California Rising Stars list. Each year, no more than 2.5% of the lawyers in the state are selected by the research team at Super Lawyers to receive this honor.
Reprinted courtesy of
T. Giovanni “John” Arbucci, Haight Brown & Bonesteel and
Kristian B. Moriarty, Haight Brown & Bonesteel
Mr. Arbucci may be contacted at jarbucci@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Effective Strategies for Reinforcing Safety Into Evolving Design Standards
July 02, 2024 —
Ethan Harris - Construction ExecutiveFrom design/build condos to built-to-suit warehouses, one factor remains the highest priority regardless of the project type—the approach to upholding the highest level of safety. Safety exists as a core value across all areas of the construction industry, but the increased risk of serious injuries or fatalities persists. Ranked fourth on the United States Bureau of Labor Statistics’ list of occupations with the most fatality rates, construction workers put their lives in danger each time they step onto the jobsite.
Considering this risk, it’s important for every team member—from subcontractors to superintendents—to take responsibility for safety compliance, empowering their workforce to take ownership of their own actions and hold others accountable for theirs. To help enhance safety efforts from start to completion, safety leaders are focusing on ways to implement safety standards within each component of a building’s design. Although this approach requires more comprehensive planning and strategizing on the front end, it is intended to reduce and mitigate hazards before they become larger issues. Keeping this idea in mind, here are a few actionable methods for managing projects designed around safety compliance.
ASSESS FIRST
No two jobsites are the same. From crowded pedestrian walkways to dangerous existing infrastructure, each project requires specific layouts, materials and processes to be fully functional both during and after construction. Given the unique nature of each site, a detailed risk assessment must be conducted before any other design and/or building activities begin. During this initial assessment, careful consideration should be placed on the overall flow as it relates to the people, processes and equipment located on or near the construction site.
Reprinted courtesy of
Ethan Harris, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Recent Federal Court Decision Favors Class Action Defendants
October 26, 2020 —
Amber Karns & Dan Pipitone - Construction ExecutiveThe commercial construction contracting and subcontracting industry in general is unique under the law for industry professionals, as they’re typically limited to wage and hour litigation under provisions of the Fair Labor Standards Act.
The majority of FLSA cases seek class action status or collective classification, while other FLSA litigation is initiated by individuals seeking damages. For the former, past and current employees can opt into class action litigation and seek collective damages against a construction company. The looming financial burden of class action or collective litigation against construction companies consume time, money and resources to the extent it’s often advisable for Defendants to negotiate an unfair settlement.
Yet, thanks to a recent federal court decision on March 27, 2020, the legal maneuvering behind unreasonable Plaintiff demands may soon be counter-balanced by the class action Defendants’ right to due process review. A recent legal opinion in a recent FLSA case has potentially wide-ranging implications for Defendant employers mired in future class action litigation. Moreover, as the FLSA applies to all employers, this decision potentially applies to all ownership groups representing the commercial construction industry, extending to partners, contractors and subcontractors.
Reprinted courtesy of
Amber Karns & Dan Pipitone, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Pipitone may be contacted at dpipitone@munsch.com
Ms. Karns may be contacted at akarns@munsch.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Refusal to Consider Supplemental Claim Found Improper
June 17, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventy Circuit reversed the district court's finding that the insurer had properly rejected the insured's supplemental claim. Great Lakes Ins. SE v. Concourse Plaza A Condomiium Association, Inc., 2024 U.S. App. LEXIS 8958 (11th Cir. April 15, 2024).
On September 10, 2017, Hurrican Irma struck Concourse Plaza's building, causing wind and water damage. Great Lakes sent a adjuster to inspect the property. The adjuster found damages to the building were $31,035.21, well below the policy's deductible. Accordingly, Great Lakes advised that the net amount of the claim was zero.
Concourse Plaza responded on September 4, 2020, just shy of three years after the cliam accured. Concourse Plaza disputed the damages estimate, but did not include a competing estimate. The letter said an estimate was being prepared and Great Lakes should consider the letter as notice of the intent to pursue additional benefits for the loss pursuant to the policy's notice provisions and Florida law.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
Spencer Mayer Receives Miami-Dade Bar Association's '40 Under 40' Award
March 04, 2024 —
Lewis Brisbois NewsroomMiami, Fla. (February 23, 2024) – Miami Associate Spencer Mayer received the 2024 Miami-Dade Bar Association Young Lawyers Section’s '40 under 40' Award at the association's annual "Miami Nights" event on February 22.
Mr. Mayer serves on the Board of Directors of the Miami Dade Bar Association’s Young Lawyers Section. Lewis Brisbois was a proud sponsor of this event, which raised funds for the organization's community service initiatives and pro bono programming.
Mr. Mayer is a member of the General Liability Practice. His practice focuses on all aspects of civil litigation, including complex commercial litigation, products liability, premises liability, wrongful death, catastrophic injury, and insurance coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois