Mass-Timber Furnished Apartments Fare Well in Fire Tests
August 24, 2017 —
Nadine M. Post - Engineering News-RecordAdvocates for a code change that would allow taller heavy-timber frames are buoyed by the good performance of mass-timber structures in the first U.S. fire tests on full-scale furnished apartments.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. PostMs. Post may be contacted at
postn@enr.com
Courts Take Another Swipe at the Implied Warranty of the Plans and Specifications
December 15, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCImplied warranties are warranties created by law, legislation, or courts. In the construction industry, one of the most prominent implied warranties is that owners who provide plans and specifications to their contractors impliedly warrant the adequacy of their plans and specifications.[i] That implied warranty had its beginning in the 1918 US Supreme Court decision of U.S. v. Spearin[ii] and is, therefore, popularly known as the Spearin Doctrine. Under the Spearin Doctrine, if the contractor completes the work in accordance with the owner’s plans and specifications, but there is a deficiency or failure, the owner, not the contractor, is responsible. When the owner breaches its implied warranty, in most instances, the contractor is entitled to additional compensation for extra work performed, delays experienced, and other additional expense or loss occasioned by the warranty breach. A recent case demonstrates that this implied warranty is not “immunity.” The contractor must still act reasonably and diligently, particularly when the contract provisions so require.
In the recent Fifth Circuit case of Dallas/Ft. Worth International Airport v. INet Airport Systems,[iii] the court, despite the implied warranty that existed, did not grant the contractor summary judgment on claims involving admitted plan deficiencies, since factual issues existed regarding the contractor’s cooperation and participation in the solution to the defects.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Court of Appeals Affirms Dismissal of Owner’s Claims Based on Contractual One-Year Claims Limitations Period
October 04, 2021 —
Cassidy Ingram - Ahlers Cressman & SleightIn a recent unpublished decision – Tadych v. Noble Ridge Construction, Inc.– the Washington State Court of Appeals, Division One, held that a one-year contractual claim limitations clause was valid and enforceable. The Tadych decision is important because it reiterates the strict approach courts will take to a claim limitations clause less than the statutory six years for breach of contract claims prescribed by RCW 4.16.040(1). In other words, when the parties agree to shorten the limitations period, the agreement will be enforced barring any procedural or substantive unconscionability.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract provided a one-year claim limitations clause in which claims could be raised, and that all claims not raised in the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
Real Estate & Construction News Round-Up (02/08/23) – The Build America, Buy America Act, ESG Feasibility, and University Partnerships
February 27, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores President Joe Biden’s recent State of the Union address and plans for the Build America, Buy America Act, the feasibility of real estate companies achieving their ESG goals, and how developers, lenders, and tenants are partnering with universities to solve real estate challenges.
- During his annual State of the Union address, President Joe Biden detailed his Build America, Buy America plans and standard to require all construction materials on federal infrastructure projects to be made in the United States. (Jennifer Goodman & Zachary Phillips, Construction Dive)
- Speculation surrounding the economic environment and real estate stability is testing the feasibility and resilience of the environmental, social and corporate governance (ESG) framework used by corporations to measure their societal impact. (Anna Staropoli, Commercial Observer)
- Adopting Web3 and decentralization in the real estate industry is projected to bring about significant changes and improvements. (David Bitton, Forbes)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Federal Court Rejects Insurer's Argument that Wisconsin Has Adopted the Manifestation Trigger for Property Policy
April 03, 2013 —
Tred Eyerly - Insurance Law HawaiiThe federal district court disagreed with the insurer's strident claim that Wisconsin followed the manifestation trigger for deciding coverage under a homeowner's policy. Strauss v. Chubb Indem. Ins. Co., 2013 U.S. Dist. LEXIS 224 (E.D. Wis. Jan. 2, 2013).
Several years after their house was constructed, the insureds discovered water damage. Chubb denied the claim. The insureds sued. Chubb moved for summary judgment and argued that the loss first manifested many years after its policy expired. Further, Chubb argued that Wisconsin followed the manifestation trigger for first-party property insurance, meaning that only the insurance policy in effect when the loss manifested was required to respond.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Federal Court Finds Occurrence for Faulty Workmanship Under Virginia Law
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe Federal District Court in Virginia found that allegations of faulty workmanship could arise from an occurrence. Nautilus Ins. Co. v. Strongwell Corp., 2013 U.S. Dist. LEXIS 79163 (W. D. Va. June 4, 2013).
Strongwell supplied certain fiberglass reinforced plastic materials to a subcontractor of Black & Veatch for a construction project at power plant. Black & Veatch subsequently sued Strongwell, claiming that numerous defects in Strongwell's materials and work were discovered after the project was completed. The complaint further alleged that as a result of the defects, there was widespread property damage to portions of the power plant.
Nautilus defended under a reservation of rights. Nautilus also filed suit for a declaratory judgment that to establish it had no duty to defend or indemnify Strongwell. Strongwell moved to dismiss the complaint insofar as it requested a declaration that there was no duty to defend. Strongwell also filed a motion to stay the coverage action until the underlying case was completed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Massive Wildfire Near Boulder, Colo., Destroys Nearly 1,000 Homes and Businesses
January 03, 2022 —
Mark Shaw - Engineering News-RecordA wildfire, driven by wind gusts up to 105 mph, swept through 6,000 acres in suburban neighborhoods east of Boulder, Colo., destroying 991 homes and damaging 127 others in the towns of Superior and Louisville, according to estimates from the Boulder County sheriff’s office.
Reprinted courtesy of