Traub Lieberman Partners Ryan Jones and Scot Samis Obtain Affirmation of Final Summary Judgment
February 28, 2022 —
C. Ryan Jones & Scot E. Samis - Traub LiebermanTraub Lieberman Partners Ryan Jones and Scot Samis recently obtained affirmation of final summary judgment in favor of a windstorm and general insurance provider (“Insurer”) in the Florida First District Court of Appeal. The Appellant, a restoration service provider (“Restoration Service”), provided emergency mitigation services in the wake of hurricane damage to a residential home that was covered by an insurance policy issued by the Insurer. The Restoration Service invoiced the Insurer and, following an investigation, the Insurer paid a portion of the invoiced amount and invoked the policy’s appraisal clause to resolve the dispute over the difference. The Restoration Service brought suit against the Insurer, arguing that the appraisal process did not apply to mitigation services. The Insurer countered that it was entitled to resolve the claim by appraisal and, following arguments, the Court determined that the appraisal provision applied to mitigation services.
Reprinted courtesy of
C. Ryan Jones, Traub Lieberman and
Scot E. Samis, Traub Lieberman
Mr. Jones may be contacted at rjones@tlsslaw.com
Mr. Samis may be contacted at ssamis@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Budget Remains at Impasse over Construction Defect Law
June 01, 2011 —
CDJ STAFFNegotiations for the Nevada state budget have stalled over proposals to amend the state’s construction defect laws. Assembly Republicans had offered changes to the law to make it friendlier to contractors; however, after a state Supreme Court ruling that the state could not move a local government entity’s funds into state coffers, pressure has increased on the governor to lift the expiration dates of taxes approved in 2009.
The Reno Gazette-Journal quotes John Madole, a construction industry lobbyist, “We agree with them that you have to address the issue of the attorney fees, and for all practical purposes, they are automatically awarded when anybody brings any kind of suit.”
Speaker of the Assembly, John Oceguera, a Democrat, has proposed a bill that “makes it absolutely crystal clear that the only time you get attorney's fees is if you're the prevailing party.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Could Impact Contractor Performance Bonds
March 30, 2020 —
Ben Williams & MG Surety - Construction ExecutiveAs COVID-19 continues to expand around the United States and the world, it may only be a matter of time before U.S. construction projects are affected by the virus. Performance bonds guarantee that a project will be completed by a contractor according to the contract. However, what if a contractor cannot complete a project on time due to widespread disease? What, if any, impact could the virus have on a contractor’s surety bond program?
Risk Factors
Several risks associated with the virus could trigger a performance bond claim.
1. Materials. The Chinese account for a large supply of construction materials, including steel, copper, cabinetry, etc. An inability to obtain these materials could significantly delay or stop a project all together. Even if a contractor is able to obtain them from other sources, it may be at a significantly higher cost than they put into the bid.
2. Labor. There is already a shortage of qualified labor in the construction industry. Additionally, construction already lends itself to the spreading of viruses; workers are often in close proximity, handling common materials, and they may not have an easily accessible place to wash their hands. Furthermore, even though many now have paid sick leave, there is often pressure not to use it. These things could magnify the labor shortage and make it difficult to complete projects on time.
3. Safety. Finally, the world is having a serious shortage of respirators. Because of widespread panic, many people have been purchasing N95 respirators—so much that the Surgeon General has asked people to stop buying them. It has created a shortage for people who really need them, like contractors. If contractors can’t get these safety masks, certain trades will either be unable to work, or risk continuing the project without masks, which would endanger workers and open them up to OSHA penalties.
Reprinted courtesy of
Ben Williams and MG Surety, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Williams may be contacted at
benw@mgsuretybonds.com
Court of Appeals Invalidates Lien under Dormancy Clause
January 05, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPOn October 27, 2016, the Georgia Court of Appeals determined whether the Dormancy Statute, which bars the enforcement of judgments after seven years, applied to a lienholder’s action to foreclose its lien.
A property owner (“Owner”), contracted with a contractor Contractor (“Contractor”) to build a home in January 2006. Contractor purchased building materials from a supplier (“Supplier”). In September 2006, Contractor failed to pay for the materials, and Supplier filed a lien on Owner’s property in November 2006. Supplier filed a claim of lien and instituted a lien action against Contractor. In March 2007, a default judgment was entered in favor of Supplier for the lien amount.
It was not until November 2014 that Supplier sued Owner, seeking a declaration of a special lien in the amount of $14,655.65. The trial court granted Supplier’s motion for summary judgment and awarded Supplier a special lien in the amount of $14,655.65 plus $8,305 in accrued interest. Owner appealed, arguing that the lien was rendered unenforceable by the Dormancy Statute.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Claims are on the Rise Due to Pandemic-Related Issues
April 25, 2022 —
Beverley BevenFlorez – CDJ StaffAccording to a recent
New York Times article, pandemic-related issues such as “stop-and-start construction, global supply chain issues, pressure from lenders and yo-yoing housing prices” has caused an increase in construction defect suits for new apartment developments: “Complaints and legal claims are already emerging, signaling that a confluence of all factors amid the Covid crisis could continue to be a problem for new construction — from entry-level studios to top-tier penthouses — for years to come, according to lawyers and development consultants.”
A Times analysis of Department of Buildings data by Marketproof demonstrated an increase in complaints beginning March 1st, 2020: “During the first year of the pandemic, new residential buildings recorded an average of five complaints per building, a 46 percent jump from the same period the previous year.”
Steven D. Sladkus, a partner at Schwartz Sladkus Reich Greenberg Atlas told the Times that his “'phone’s been ringing off the hook' with complaints from homeowners in new condo buildings” regarding “heating problems, poor sound insulation, fire safety issues and faulty elevators.”
Developers have faced a variety of pandemic-related challenges including a disrupted supply chain, shut downs, shipping delays, labor shortages, and increased material prices. In 2020, the lack of availability of vaccines caused some construction to halt: “Suddenly one guy calls in sick and the whole crew of electricians can’t show up,” Steven Zirinsky, co-chair of the building codes committee at the New York chapter of the American Institute of Architects told the Times.
Read the court decisionRead the full story...Reprinted courtesy of
Two Things to Consider Before Making Warranty Repairs
January 21, 2019 —
David McLain - Colorado Construction Litigation BlogIn my last article, “What a construction defect ‘win’ looks like for a builder,” I made the point that builders should go to great lengths to work with homeowners to resolve legitimate problems through the entire statute of repose, in order to prevent the homeowners from involving attorneys. Again, happy homeowners do not call attorneys and do not bring construction defect claims. In this article, I want to address the ramifications of this strategy that builders should consider.
First, builders must be aware that any repairs performed will likely start anew the statutes of limitation and repose for the repairs. Second, builders should inform and involve their insurers in this process so as to avoid running afoul of their carriers’ “voluntary payments” clauses. In the long run, keeping homeowners happy is well worth the cost, especially if you keep in mind these additional considerations.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Brenner Base Tunnelers Conquer Peaks and Valleys in the Alps
October 21, 2019 —
Scott Blair - Engineering News-RecordA logistics tangle decades in the unraveling, the Brenner Base Tunnel project is having a banner year. Twin tunnel boring machines in May were released on their relentless journey to mine the main tunnels underneath the Alps between Austria and Italy, while a multinational crew of 2,400 workers armed with a toolkit of just about every mining technique is swarming four major worksites, including a particularly challenging area where workers must undercut a river and pass through the fast-flowing aquifer below it.