New York Shuts Down Majority of Construction
March 30, 2020 —
Laura Bourgeois LoBue & Matthew D. Stockwell - Gravel2Gavel Construction & Real Estate Law BlogDue to pressure from construction workers, officials, and some construction workers having tested positive for COVID-19, the Empire State Development Corp. (acting on behalf of Governor Cuomo) has frozen all construction in New York today, with the exception of work on hospitals and health care facilities, transit facilities, roads and bridges, affordable housing and homeless shelters.
As a result, commercial construction and condominium projects are on hold, with the exception of work that must be completed to prevent unsafe conditions. Until now, construction has been considered “essential” in New York.
Reprinted courtesy of
Laura Bourgeois LoBue, Pillsbury and
Matthew D. Stockwell, Pillsbury
Ms. LoBue may be contacted at laura.lobue@pillsburylaw.com
Mr. Stockwell may be contacted at matthew.stockwell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner Alex Giannetto for Being Named to San Diego Business Journal’s Top 100 Leaders in Law List
December 03, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner Alexander Giannetto for being selected as a “2024 Leaders of Influence in Law” by the San Diego Business Journal! To read and download the SDBJ publication, please click
here.
Alex Giannetto is a managing partner with Bremer, Whyte, Brown & O’Meara LLP’s San Diego office. He has extensive experience in all aspects of civil litigation handling liability matters including slip and falls, catastrophic injuries, wrongful death, traumatic brain injuries, landslides, and construction claims. He has obtained favorable trial results defending clients on personal injury and premises matters in San Diego and Los Angeles. He also has appellate experience. He is an AV-rated attorney by Martindale-Hubbell who has been voted Best of the Bar in San Diego as well as a Top Lawyer in San Diego.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Additional Insured Not Entitled to Coverage for Named Insured's Defective Work
September 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the Seventh Circuit determined there was no duty to defend or to indemnify the additional insured for the named insured's defective work. St. Paul Guardian Ins. Co., et al. v. Walsh Construction Co., 99 F. 4th 1035 (7th Cir. 2024).
The City of Chicago contracted with Walsh Construction Company to manage the construction of a canopy and curtain wall system at O'Hare International Airport. Walsh entered into a contract with Carlo Steel Corporation, which in turn subcontracted with LB Steel, LLC to fabricate and install steel columns to support the wall and canopy. LB Steel listed Walsh as an additional insured in its commercial general liability policies. LB Steel's insurers were St. Paul, Travelers, and Charter Oak Fire Insurance Company.
Several years into the project, the City discovered cracks in the welds of the steel columns and sued Walsh. Walsh, in turn, sued LB Steel under its subcontract. Walsh also asked LB Steel's insurers to defend it in the City's lawsuit, but they refused to do so. Walsh eventually secured a judgment against LB Steel, but LB Steel declared bankruptcy. Walsh then sued LB Steel's insurers to recover the costs of defending against the City's lawsuit and indemnification for any resulting losses.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
Home Prices in 20 U.S. Cities Increase at Slower Pace
February 25, 2014 —
Victoria Stilwell – BloombergHome prices in the U.S. climbed at a slower pace in the year through December, pointing to a moderation in the market that will help keep more properties within reach for prospective buyers.
The S&P/Case-Shiller index of property values in 20 cities rose 13.4 percent from December 2012 after increasing 13.7 percent in the year ended in November, the group said today in New York. It was the first deceleration since June. The gain matched the median estimate of 33 economists surveyed by Bloomberg.
Price appreciation is slowing as rising mortgage rates combined with harsh winter weather to cool home purchases over the past few months. Smaller increases mean more homes will remain affordable as the labor market improves, helping maintain the rebound in residential real estate that has boosted growth.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Miller Act Payment Bond Surety Bound to Arbitration Award
December 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting case binding a Miller Act payment bond surety to an arbitration award against its prime contractor (bond principal) that it received sufficient notice of. Notice is the operative word. The surety could have participated in the arbitration, elected not to, and when its prime contractor (bond principal) lost the arbitration, it was NOT given another bite out of the apple to litigate facts already been decided.
In BRC Uluslararasi Taahut VE Ticaret A.S. v. Lexon Ins. Co., 2020 WL 6801933 (D. Maryland 2020), a prime contractor was hired by the federal government to make security upgrades and interior renovations to a United States embassy in the Czech Republic. The prime contractor hired a subcontractor to perform all of the installed contract work. The prime contractor terminated the subcontractor for default during the course of construction.
The subcontractor demanded arbitration in accordance with the subcontract claiming it was wrongfully terminated. The subcontractor also filed a lawsuit asserting a Miller Act payment bond claim against the prime contractor’s surety (as well as a breach of contract action against the prime contractor). The subcontractor made clear it intended to pursue its claims in arbitration and hold the payment bond surety jointly and severally liable. The parties agreed to stay the lawsuit since the facts were identical to those being arbitrated. The arbitration went forward and an award was entered in favor of the subcontractor and against the prime contractor for approximately $2.3 Million.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Exact Dates Not Needed for Construction Defect Insurance Claim
March 01, 2012 —
CDJ STAFFThe Texas Court of Appeals reversed the decision of the trial court in Vines-Herrin Custom Homes v Great American Lloyds Insurance Company on December 21, 2011. Vines-Herrin Custom Homes built a single-family home in Plano, Texas in 1999. They obtained a commercial general liability policy from Great American, later purchasing coverage from Mid-Continent, which the decision describes as “a sister company of Great American.”
While the home was under construction, Emil G. Cerullo sought to purchase it. At the time, it was under contract to another buyer. Two months later, Vines-Herrin told Cerullo that the deal had “fell through.” Cerullo bought the house with modifications from the original plan. Upon moving in, Cerullo began having water intrusion and other problems. “Cerullo noticed water gathering on window sills and damage to the sheetrock and baseboard.” Additional problems followed, including cracks, leaks, “and in early 2002, the ceiling and roof began to sag.”
Cerullo sued Vines-Herrin, claiming negligent construction. Vines-Herrin filed a claim seeking defense and indemnification under the insurance policies. Coverage was denied and Vines-Herrin filed suit to require coverage and also bringing claims for “breach of the duty of good faith and fair dealing, breach of contract, and DTPA and insurance code violations.”
In May, 2006 Vines-Herrin stated that it had no more defense funds and went into arbitration with Cerullo. The underlying construction defect action was settled for about $2.5 million. As part of the settlement, “Cerullo became the rightful owner of all remaining claims, rights, and causes of action against” Vines-Herrin’s insurers. He then joined the coverage lawsuit.
The non-jury trial was held under the controlling law of the time which “imposed a duty to defend only if the property damage manifested or became apparent during the policy period.” The court concluded in Cerullo’s favor. During the post-judgment motions, the Texas Supreme Court rejected the manifestation rule. Under this ruling, the trial court set aside its judgment and found in favor of the insurance companies. The trial court noted that although “the Residence was covered by an uninterrupted period of insurance (which began before the Residence was constructed) and that the damages to the Residence manifested during the uninterrupted period of insurance coverage,” “Mr. Cerullo failed to allege the date when actual physical damage to the property occurred.”
The first claim by Cerullo and Vines-Herrin was that the “Final Judgment” occurred in October 2004, and that all proceedings thereafter were void. The court rejected this as the “final judgment” is not “final for the purposes of an appeal unless it actually disposes of every pending claim and party or unless it clearly and unequivocally states that it finally disposes of all claims and all parties.” Despite the use of the word “final,” the trial court’s decision did not do this.
The second issue was the application of the Texas Supreme Court case Don’s Building Supply Inc. v. OneBeacon Insurance. In this case, framing rot due to defective stucco was not discovered until after the end of the policy period. The Supreme Court noted that “the key date is when injury happens, not when someone happens on it.”
The appeals court found that the trial court misapplied the Don’s Building Supply decision. Rather than an exact date, “so long as that damage occurred within the policy period, coverage was provided.” The appeals court noted that “Cerullo alleged the house was constructed in 1999 and he purchased it in May 2000.” “By April of 2001, Cerullo noticed that the windowsills in the study were showing signs of leakage and water damage.” As the court put it, “the petitions then alleged a litany of defects.”
The court noted that coverage by Great American was in effect from November 9, 1999 to November 9, 2000. In May of 2000, the house suffered “substantial flooding from a rainstorm that caused damage.” This was during the policy period. “As a matter of law, actual damages must occur no later than when they manifest.”
The court concluded that as damage manifested during the period of coverage, so must have the damage. The court ruled that “contrary to the trial court’s determination otherwise, the evidence showed Great American’s duty to indemnify was triggered, and expert testimony establishing the exact date of injury was not required to trigger the duty.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (03/08/23) – Updates on U.S. Mortgage Applications, the Inflation Reduction Act, and Multifamily Sector
March 20, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores the cooling housing market and plummeting mortgage applications, potential tax-savings as a result of the 2022 Inflation Reduction Act (IRA), and new developments in the multifamily sector.
- Rising interest rates are impacting affordability and cooling the U.S. housing market, driving mortgage applications to lowest levels in decades. (Nicole Friedman, The Wall Street Journal)
- A number of companies are going all out to entice workers back to the office, and as new data on New York City emerges, upscale offices might help do the trick. (Emily Peck, Axios)
- For real estate developers and investors across the U.S., tax-saving opportunities are popping up as a result of the Inflation Reduction Act of 2022. (David Harlan & Laura Theiss, Dallas Business Journal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team