A Quick Virginia Mechanic’s Lien Timing Refresher
February 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those who read Construction Law Musings on a regular basis know,
mechanic’s liens are a big part of my construction law practice. These
tricky and strictly enforced statutory collection tools are very powerful when correctly recorded and utterly useless if they aren’t recorded in a timely fashion and with the correct information contained within them. Couple that fact with recent
changes to the mechanic’s lien form in 2019, and I feel the need to give a quick refresher.
If you’ve kept up with Musings, you know about the two big numbers for Virginia mechanic’s lien timing, 90 and 150. These should be kept in mind for every general contractor, subcontractor, or supplier on any construction project in Virginia.
Virginia Code Section 43-4 sets out the reasons to keep these numbers in mind. The code section sets out why you need to know these numbers.
The 90 refers to the deadline for recording a lien. This number affects the right to a lien in Virginia. In order to preserve lien rights, a construction contractor must record the lien within ninety days of the last day of the last month in which the last work was performed or no later than ninety days from the date of completion of the project or other termination of work. The short version is that most general contractors on commercial projects have 90 days from the last work in which to record their lien and most subcontractors have 90 days from the last day of the last month of work. However, the best practice is to simply calculate the 90 days from the last work performed or material supplied to avoid issues and arguments between attorneys regarding timing.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
EEOC Focuses on Eliminating Harassment, Recruitment and Hiring Barriers in the Construction Industry
September 09, 2024 —
Aaron C. Schlesinger & Stephen E. Irving - Peckar & Abramson, P.C.The
Equal Employment Opportunity Commission (EEOC), whose mission is to enforce the nation’s anti-discrimination laws, released new guidelines on June 18, 2024, entitled
Promising Practices for Preventing Harassment in the Construction Industry. The guidelines are in support of its Strategic Enforcement Plan for the fiscal years 2024-2028 for combatting systemic harassment and eliminating barriers in recruitment and hiring in the construction industry. With these guidelines, the EEOC has identified harassment as an ongoing issue in the construction industry, and that immediate attention and resolution is required.
The EEOC specifically recommends that the following five core principles that it has found effective in preventing and addressing harassment be implemented by construction industry employers:
- Committed and engaged leadership;
- Consistent and demonstrated accountability;
- Strong and comprehensive harassment policies;
- Trusted and accessible complaint procedures; and
- Regular, interactive training tailored to the audience and the organization.
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. and
Stephen E. Irving, Peckar & Abramson, P.C.
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Mr. Irving may be contacted at sirving@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Lump Sum Subcontract? Perhaps Not.
August 20, 2019 —
David Adelstein - Florida Construction Legal UpdatesLump sum subcontract? Perhaps not due to a recent ruling where the trial court said “No!” based on the language in the subcontract and contract documents generally incorporated into the subcontract.
This is a ruling on an interpretation of a subcontract and contract documents incorporated into the subcontract that I do not agree with and struggle to fully comprehend. The issue was whether the subcontract amount was a lump sum or subject to an audit, adjustment, and definitization based on actual costs incurred. Of course, the subcontractor (or any person in any business) is not just interested in recouping actual costs, but there needs to be a margin to cover profit and home office overhead that does not get factored into field general conditions.
In United States v. Travelers Casualty and Surety Company, 2018 WL 6571234 (M.D.Fla. 2018), a prime contractor was hired to perform work on a federal project. During the work, the Government issued the prime contractor a Modification that had a not-to-exceed value and required the prime contractor to track its costs for this Modification separate from other contract costs. In other words, based on this Modification, the prime contractor was paid its costs up to a maximum amount and the prime contractor would separately cost-code and track the costs for this work differently than other work it was performing under the prime contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Remote Depositions in the Post-Covid-19 World
September 06, 2021 —
Islam M. Ahmad - Wilke Fleury, LLPDespite the easing of COVID-19 restrictions in California, many of the changes imposed on the legal industry by the pandemic will likely remain in effect for the foreseeable future. One major change for litigators has been conducting depositions remotely. This change takes an already intricate task and makes it further complex by adding a new dimension of factors to consider. It is imperative that litigators understand these factors to avoid giving their opposition an undue advantage and to maximize the utility of depositions. While we may disagree as to whether remote depositions are a welcome change, the fact of the matter is that lawyers must adapt to them and provide adequate legal representation. This article explores some of the challenges and opportunities presented by remote depositions.
- The Deponent
The deponent is the single most important element of any deposition and handing it properly becomes even more delicate in remote settings. I recently took a deposition where the plaintiff met their attorney for the first time at their deposition. The result was not spectacular. The plaintiff was ill-prepared, and the case eventually settled for far less than what it might have if it had been better prepared.
Read the court decisionRead the full story...Reprinted courtesy of
Islam M. Ahmad, Wilke Fleury, LLPMr. Ahmad may be contacted at
iahmad@wilkefleury.com
Thanks to All for the 2024 Super Lawyers Nod!
May 13, 2024 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the seventh straight year to the
Virginia Super Lawyers in the Construction Litigation category for 2024. Add this to my recent election to the
Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer-elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the
5% of Virginia attorneys that made this list for 2024.
The full list of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
If you want to see the lists before then, a digital version of the Virginia Super Lawyers Magazine is
available here (click on the Virginia magazine).
Thanks again to all of you who participated in my nomination and election.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Terms of Your Teaming Agreement Matter
February 11, 2019 —
Christopher G. Hill - Construction Law MusingsThese days in construction, and other pursuits, teaming agreements have become a great method for large and small contractors to work together to take advantage of various contract and job requirements from minority participation to veteran ownership. With the proliferation of these agreements, parties must be careful in how they draft the terms of these agreements. Without proper drafting, the parties risk unenforceability of the teaming agreement in the evewnt of a dispute.
One potential pitfall in drafting is an “agreement to agree” or an agreement to negotiate a separate contract in the future. This type of pitfall was illustrated in the case of InDyne Inc. v. Beacon Occupational Health & Safety Services Inc. out of the Eastern District of Virginia. In this case, InDyne and Beacon entered into a teaming agreement that provided that InDyne as Prime would seek to use Beacon, the Sub, in the event that InDyne was awarded a contract using Beacon’s numbers. The teaming agreement further provided:
The agreement shall remain in effect until the first of the following shall occur: … (g) inability of the Prime and the Sub, after negotiating in good faith, to reach agreement on the terms of a subcontract offered by the Prime, in accordance with this agreement.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
SEC Climate Change Disclosure Letter Foreshadows Anticipated Regulatory Changes
November 08, 2021 —
Karen C. Bennett & Jane C. Luxton - Lewis BrisboisWashington, D.C. (October 13, 2021) - In late September 2021, the Division of Corporation Finance of the Securities and Exchange Commission (SEC) issued a Sample Letter providing guidance to companies on how their climate disclosures will be analyzed for compliance with material risk reporting obligations. The Sample Letter precedes the SEC’s issuance of mandatory climate-related disclosure rules anticipated by year-end and signals a greater focus on specific information used to support securities filings, a development that businesses should take seriously.
The Sample Letter builds on climate change guidance the SEC issued in 2010 and identifies nine categories of disclosures the SEC suggests may be material risks that must be disclosed. These include:
- Consistency between a company’s corporate social responsibility report and its SEC filings;
- Risks associated with climate-related legislation, regulation, or policy, and resulting compliance costs;
- Litigation risks related to climate change; and
- Risks linked to an array of operational and market factors, including capital expenditures, continuity of business operations, supply chain stability, changing demand, reputation, availability of credit and insurance, and other climate-change related potential impacts on the financial condition of the company.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois and
Jane C. Luxton, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of