Lewis Brisbois Moves to Top 15 in Law360 2022 Diversity Snapshot
August 15, 2022 —
Rima Badawiya - Lewis Brisbois NewsroomLos Angeles, Calif. (August 4, 2022) - Lewis Brisbois has ranked 13th in Law360’s 2022 Diversity Snapshot – a measure of the overall presence of individuals from underrepresented backgrounds in law firms of all sizes.
Throughout Lewis Brisbois’ history, the firm has been recognized for high achievements in the areas of diversity, equity, and inclusion. Over the past year, its focus on capturing the full picture of its diversity has led to the firm’s rise in several diversity rankings – including the Law360 Diversity Snapshot. As described in the Law360 Pulse article,
"Diversity Snapshot: Representation in the Ranks," the Diversity Snapshot serves as a “comprehensive ranking of law firms on their overall representation of minority attorneys,” providing “a picture of where firms are now, and where the future might lead.”
Moreover, as explained in the main article of this special publication,
"Diversity Snapshot: How Firms Stack Up," Law360 used its own historical surveys as well as data from the American Bar Association to evaluate the diversity in firm headcounts against benchmarks that reflected diversity in the potential marketplace of new hires. Lewis Brisbois’ efforts to capture its diversity numbers has led to a significant increase in the firm’s position from 58th to 13th. This year's Snapshot includes 291 law firms, with 75 in the 600+ attorneys category.
Read the court decisionRead the full story...Reprinted courtesy of
Rima Badawiya, Lewis BrisboisMs. Badawiya may be contacted at
Rima.Badawiya@lewisbrisbois.com
Additional Insured Not Entitled to Coverage for Post-Completion Defects
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe general contractor, an additional insured on the subcontractor's policy, was not entitled to coverage for construction defect claims that arose after completion of the project. Weitz Co. v. Acuity, 2016 U.S. Dist. LEXIS 150433 (S.D. Ohio Oct. 31, 2016).
Weitz was the general contractor hired by Twin Lakes for construction of a residential community. One of the subcontractors, Miter Masonry, was insured by Acuity under a CGL policy. Work on the project began in 2002 and was substantially completed in 2005. In 2011, Twin Lakes notified Weitz that there were moisture infiltration issues at the project that may be related to work during the project.
Twin Lakes filed a Demand for Arbitration against Weitz on November 30, 2012. Twin Lakes alleged that the defects included the building wrap, windows, doors, wood trim, aluminum wrap, vinyl siding, flashing and brick veneer not being installed in accordance with contract documents and/or industry standards. The arbitration panel awarded damages to Twin Lakes in the amount of $2,775,771.86. The panel found that Weitz breached sections of the contract which caused moisture intrusion and damage to all the units. The panel ultimately held that Weitz could recover from the subcontractors 100% of the $2,775,771.86 awarded. Acuity's insured, Miter Masonry, was determined to be 4% at fault for the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Negligent Failure to Respond to Settlement Offer Is Not Bad Faith
May 03, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit found that the insurer's negligent failure to respond to a settlement offer did not constitute bad faith. McDaniel v. Gov't Employees Ins. Co., 2017 U.S. App. LEXIS 4029 (9th Cir. March 7, 2017).
McDaniel was the assignee of claims against GEICO assigned by the insured after settling a wrongful death suit. McDaniel alleged that GEICO unreasonably refused to accept a $100,000 policy limits offer. The case went to trial and a jury awarded McDaniel over $3 million against the insured.
On August 7, 2009, McDaniel's attorney Steven Nichols extended a $100,000 policy limits settlement offer with a fifteen day acceptance deadline to GEICO's attorney Michael Griott. The parties subsequently agreed to extend the acceptance deadline to ten days following MacDaniel's service of responses to outstanding interrogatories, which Nichols hand-delivered to Griott on August 27, 2009. On September 1, 2009, Griott emailed GEICO claims adjuster Aldin Buenaventura with a letter attachment indicating that Nichols had submitted the requested interrogatories and, in bold and underlined text, that "[o]ur response to Plaintiff's policy limits demand is due on or before September 11, 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Recent Supreme Court Decision Could Have Substantial Impact on Builders
January 23, 2023 —
Cassidy Ingram - Ahlers Cressman & SleightOn October 27, 2022, the Washington State Supreme Court issued a decision which could have a substantial impact on the enforceability of contract clauses that require litigation to be commenced within a stated period of time from project completion. In Tadych v. Noble Ridge Construction, Inc.,the Supreme Court held that the contractual one-year statute of limitations for bringing claims against the contractor was substantively unconscionable and reversed the Court of Appeals.
In Tadych, plaintiff owners (the Tadychs) contracted with defendant contractor (Noble Ridge Construction, Inc., or NRC) for the construction of a custom home in 2012. The contract included a one-year claim limitations clause that required claims to be raised within a one year period from project completion and that any claims not raised during the one-year period would be waived. In December 2013, as the project neared completion, the Tadychs met with NRC to identify any outstanding project issues. The Tadychs noted several, including rainwater pools at the landing at the bottom of the stairs and several nicks and cracks on the stucco exterior walls.
The Tadychs moved into the home on April 8, 2014, and the City of Seattle Department of Planning and Development conducted its final site inspection on April 15 and approved the residence for occupancy on April 23. In January or February of 2015, the Tadychs began to notice a shift in their home. In February of 2015, the Tadychs engaged the Construction Dispute Resolution (CDR) to review NRC’s work. CDR raised concerns about the adequacy of the home’s construction and prepared a written report in March 2015 indicating several deviations from the architectural plans and building codes. The Tadychs sent this report to NRC, who assured the Tadychs that NRC’s work followed all requirements and rejected any claims that there were deviations from the plans. The Tadychs continued to notice issues with the home through October 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Cassidy Ingram, Ahlers Cressman & SleightMs. Ingram may be contacted at
cassidy.ingram@acslawyers.com
Construction Defect Lawsuit May Affect Home Financing
February 14, 2013 —
CDJ STAFFHomeowners in the Burlingame Ranch I Condominium Association already say they have problems with the siding on their units. The Aspen Business Journal says that their next problem might be with lenders. According to the homeowners’ attorney, Chris Brody, the association attempted to work things out, but this was not successful.
Mr. Brody was unaware of any issues with sales or refinancing, but the article notes that “at least one homeowner was told he could not refinance with a Fannie Mae backed loan if there’s pending litigation.” Last year, Fannie Mae did adopt a guideline that made homes involved in construction defect lawsuits ineligible for home loans.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Problem Halts Wind Power Park
November 13, 2013 —
CDJ STAFFEngineers have yet to determine why a blade on a wind turbine broke at a wind power plant in Michigan, but as part of their investigation they are halting work on the final 10 turbines. The already completed 60 turbines have been taken out of operation. As a result, the Echo Wind Park is no longer generating power.
Scott Simons, a spokesperson for the project, said “we’re not going to put anyone or anything at risk until we get to the bottom of this.” However, Dennis Buda, the project manager, attributed the broken blade to a manufacturing defect. Construction was planned to end in November.
Read the court decisionRead the full story...Reprinted courtesy of
Crossrail Audit Blames Busted Budget and Schedule on Mismanagement
August 13, 2019 —
Peter Reina - Engineering News-RecordIn a new report on London’s Crossrail, the U.K. National Audit Office says the beleaguered transportation project is around two years late and nearly 20% over budget because of poor management. The NAO, charged by Parliament with monitoring public spending, pointed to ill-conceived “aspirational” plans that proved to be unfit for the technologically challenging and vast program when things went wrong.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Reina, ENR
Scaffolding Purchase Suggests No New Building for Board of Equalization
July 30, 2014 —
Beverley BevenFlorez-CDJ STAFFEmployees at California’s Board of Equalization spoke out against the Brown administration after the state purchased new scaffolding for the defect-riddled building, rather than finding a new facility, reported the Sacramento Bee. The existing scaffolding was leased for $10,000 per month, but the lease expired, prompting the purchase of new scaffolding for about $100,000.
The board’s Chairman Jerome Horton stated “that while the change may make financial sense in the short term, it sends a signal that the Department of General Services intends to keep Equalization’s 2,200 or so employees in the troubled building,” according to the Sacramento Bee.
Building problems include “toxic mold, defective elevators, leaking windows, corroded wastewater pipes, floods, and exterior glass panels that spontaneously break or pop off.” So far, $2.3 million has been paid “in connection with building-related employee injury claims” along with $60 million in repairs. However, an additional $115 million is estimated to completely fix the defects.
Read the court decisionRead the full story...Reprinted courtesy of