Guessing as to your Construction Damages is Not the Best Approach
November 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitrarily guessing as to your construction damages is NOT the best approach. Sure, experts can be costly. No doubt about it. Having an expert versus guessing as to your construction damages caused by another party’s breach of contract is a no brainer. Engage an expert or, at a minimum, be in a position to competently testify as to your damages caused by another party’s breach of contract. Otherwise, the guessing is not going to get you very far as a concrete subcontractor found out in Patrick Concrete Constructors, Inc. v. Layne Christensen Co., 2018 WL 6528485 (W.D. New York 2018) where the subcontractor could not competently support its delay-related damages or change orders and, equally important, could not support that the damages were proximately caused by the general contractor’s breach of the subcontract.
In this case, the concrete subcontractor entered into a subcontract to perform concrete work for a public project. The project was delayed and the general contractor was required to pay liquidated damages to the owner. Not surprisingly, the subcontractor disputed liability for delays and sued the general contractor for all of its delay-related damages “in the form of labor and materials escalation, loss of productivity, procurement and impact costs, field and home office overhead, idle equipment, inability to take on other work, lost profits, and interest.” Patrick Concrete Constructors, 2018 WL at *1.
The general contractor moved for summary judgment as to the plaintiff’s delay-related damages – the subcontractor’s damages were nothing but guesses and the subcontractor could not prove the general contractor was the cause of the subcontractor’s damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Defect Claim over LAX Runways
October 22, 2013 —
CDJ STAFFThe city of Los Angeles is claiming that problems with the south runway at Los Angeles International Airport are due to construction defects. The city as filed a lawsuit against four of the firms involved in building the runway, CH2M Hill, R&L Brosamer, HNTB, and Tutor-Saliba Corp. The lawsuit also includes the possibility of naming up to 200 individuals or corporations.
The suit alleges that the firms incorrectly installed the concrete, leading to accelerated wear. As a result, renovation of the runway will likely have to be done earlier than anticipated. The runway was opened in 2007 as part of a safety improvement effort.
Read the court decisionRead the full story...Reprinted courtesy of
Zero-Net Energy Homes Costly Everywhere but at the Electric Meter
August 27, 2013 —
CDJ STAFFOn one hand, your walls are about nine inches thick. On the other hand, your heating and cooling costs are nonexistent. Greenhill Contracting is building “zero-net energy” homes in New Paltz, New York. The homes are designed to create more power than they consume. In addition to the walls, which WDTN News describes as “castle thick,” the homes include solar panels, triple-glazed windows, and geothermal heating and cooling systems. The cost for a three-bedroom home in this development starts at about $400,000.
Meritage Homes is offering net-zero as an option on its homes. Based in Arizona, Meritage builds homes across the country. Another national builder, Shea Homes, calls its net-zero option “SheaXero,” and has built about a thousand in four western states and in Florida. One Arizona homeowner notes that she runs her air conditioner constantly, but “I still have never paid more than $18 and some change.” Sometimes she even gets a credit.
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Key Legal Considerations for Event Cancellations
March 30, 2020 —
Michael G. Platner, Solomon B. Zoberman, & Jane C. Luxton - Lewis BrisboisEvery passing day brings stark new reports of novel coronavirus (COVID-19) cases and increasing numbers of cancelled conventions, concerts, and other major events. Both the hospitality and travel industry on the one hand, and organizations that are canceling events on the other, are scrambling to understand the legal consequences of these costly terminations. Cancellation fees can be breathtaking, and affected parties are quickly learning that there are no simple answers as to whether a disease outbreak of this scope and scale falls within force majeure (or Act of God) clauses that either do not explicitly list, or arguably may never have contemplated, circumstances of this type.
Generally, force majeure clauses excuse parties’ performance under a contract when circumstances that are beyond their control arise and prevent them from fulfilling their obligations. The party electing to enforce its rights under the force majeure clause must show that the triggering event qualifies as a force majeure event, and that the event has rendered the party’s performance impossible or impracticable.
Reprinted courtesy of Lewis Brisbois attorneys
Michael G. Platner,
Solomon B. Zoberman and
Jane C. Luxton
Mr. Platner may be contacted at Michael.Platner@lewisbrisbois.com
Mr. Zoberman may be contacted at Solomon.Zoberman@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Policyholder Fails to Build Adequate Record to Support Bad Faith Claim
May 19, 2011 —
Tred R. EyerlyThe importance of careful preparation and documentation was the take away lesson in a Texas bad faith case, C.K. Lee v. Catlin Specialty Ins. Co., 2011 U.S. Dist. LEXIS 19145 (S.D. Tex. Feb. 28, 2011).
C.K. Lee owned a commercial shopping center in Houston. Catlin issued a commercial property policy to Lee. On September 12, 2008, Hurricane Ike hit and caused substantial property damage throughout the Texas Gulf Coast area. On September 24, 2008, Lee submitted a claim for damage to the roof of his shopping center to Catlin.
Catlin hired Engle Martin to represent its interests in adjusting the claim. Engle Martin eventually adjusted over 200 Ike-related claims for Catlin.
In November 2008, Engle Martin and Emergency Services Inc., retained by Lee, inspected Lee’s property. Engle Martin observed evidence of roof repairs that had apparently been made both before and after Hurricane Ike. Engle Martin decided it was necessary to use an infrared scan of the roof to help identify which damages, if any, were attributable to wind and which, if any, were attributable to sub par, prior repairs or natural deterioration.
Engle Martin retained Project, Time & Cost (PT&C) to conduct the infrared inspection. PT&C’s inspection determined there was no wind-related damage to the roof and no breaches or openings created by wind. Instead, the roof had exceeded its life expectancy and was in need of replacement due to normal wear and weathering. Consequently, Catlin decided that the damage to Lee’s roof was not caused by winds from Hurricane Ike.
Meanwhile, Lee’s contractor, Emergency Services, prepared a report estimating that the total cost of repairing the roof would be $871,187. Engle Martin’s estimate for repair of the roof was $22,864.
Lee filed suit for breach of contract, breach of the duty of good faith and fair dealing, and violations of the Texas Insurance Code. Catlin moved for summary judgment on all claims but breach of contract, arguing that because there was a bona fide dispute concerning the cause of the damages and whether they were covered under the policy, there was no evidence of bad faith or violations of the Texas Insurance Code.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Fargo Shows Record Home Building
October 01, 2013 —
CDJ STAFFHome builders in the area of Fargo, North Dakota are describing growth in the area as “enormous.” Darrick Guthmiller, the president of the Home Builders Association of Fargo-Moorhead noted that in sixteen years of building homes, this was the best he’d seen. The Home Builders Association expects that next year might even be better.
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful How You Terminate: Terminating for Convenience May Limit Your Future Rights
January 19, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLC BlogMany construction contracts contain a termination clause that allows a contractor to be terminated either for convenience or for cause. Termination for convenience and termination for cause clauses have been discussed previously on the blog
here,
here and
here. The distinction between a termination for convenience or for cause is an important one.
If a contractor is terminated for convenience, the rights of the party who has terminated the contractor for convenience could be limited in the future. This is specifically true as to any defects in the terminated contractor’s work that are discovered after the termination for convenience.
This issue was addressed in an Oregon Court of Appeals case where a general contractor attempted to recover costs incurred in correcting a terminated subcontractor’s work after the subcontractor was terminated for convenience. Shelter Prods. v. Steel Wood Constr., Inc., 257 Or. App 382 (2013). In that case, the subcontractor sued the general contractor for its termination expenses. The general contractor asserted an offset/backcharge claim for damages incurred by the general contractor in correcting the subcontractor’s defective work. The general contractor had incurred the costs after it had terminated the subcontractor. The general contractor did not notify the subcontractor that its work was defective and did not give the subcontractor an opportunity to cure before the repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Hong Kong Popping Housing Bubbles London Can’t Handle
July 30, 2014 —
Frederik Balfour – BloombergTake a look at the world’s dizzying surges in the price of housing for 12 months at the end of June: London, up 20 percent. Manhattan, 18 percent. Sydney, 15.4 percent.
Then there are Singapore and Hong Kong: down 3.7 percent and 0.6 percent.
Prompted by concerns over potential property bubbles and affordability for the middle class, the governments of the two Asian cities have been reining in home prices by imposing measures including mortgage caps, taxes on property flippers, and levies on foreign buyers as high as 15 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Frederik Balfour, BloombergMr. Balfour may be contacted at
fbalfour@bloomberg.net