Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
Rio de Janeiro's Bursting Real-Estate Bubble
September 17, 2015 —
Juan Pablo Spinetto & Peter Millard – BloombergAt opposite ends of downtown Rio de Janeiro, projects tied to Donald Trump and Eike Batista-- one a billionaire-turned-politician, the other Brazil’s most famous ex-billionaire -- have come to represent the city’s real estate bust.
The 23-story Serrador building, a granite-and-glass art deco tower near Rio’s Santos Dumont airport, has sat empty since Batista’s failed empire of commodities companies abandoned it last year. Four miles away, in the city’s gritty port district, an ambitious office project that Trump lent his name to is still nothing more than a weed-filled lot about a year after construction was slated to begin.
Reprinted courtesy of
Juan Pablo Spinetto, Bloomberg and
Peter Millard, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
NY State Appellate Court Holds That Pollution Exclusions Bar Duty to Defend Under Liability Policies for Claims Alleging Exposure to PFAS
February 01, 2022 —
Robert F. Walsh & Paul A. Briganti - White and Williams LLPOn January 6, 2022, the New York Supreme Court, Appellate Division, Third Department, held that the “sudden and accidental” pollution exclusion (SAPE) and “absolute” pollution exclusion (APE) in liability policies relieved two insurers of a duty to defend the insured-manufacturer in connection with claims alleging damages as a result of exposure to perfluorooctanoic acid (PFOA) and perfluorooctane sulfonate (PFOS), which are man-made chemicals within the group of per- and polyfluoroalkyl substances (PFAS). See Tonoga, Incorporated v. New Hampshire Insurance Company, No. 532546, 2022 N.Y. App. Div. LEXIS 105 (App. Div. 3rd Dep’t Jan. 6, 2022).
In Tonoga, starting in 1961, the insured and its predecessors owned and operated a manufacturing facility in Petersburg, New York that produced materials coated with polytetrafluoroethylene (PTFE). Until 2013, the manufacturing process involved the use of PFOA and/or PFOS. In early 2016, excessive PFOA and/or PFOS concentrations were detected in Petersburg’s municipal water supply. Later that year, the New York Department of Environmental Conversation designated the insured’s facility a Superfund site, and the insured entered into a consent agreement that required it to assist in remedial measures. 2022 N.Y. App. Div. LEXIS 105, at *1-2.
Reprinted courtesy of
Robert F. Walsh, White and Williams LLP and
Paul A. Briganti, White and Williams LLP
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
NY Is Set To Sue US EPA Over ‘Completion’ of PCB Removal
June 25, 2019 —
Mary B. Powers - Engineering News-RecordNew York state intends to sue the U.S. Environmental Protection Agency for issuing a certificate to General Electric Co. affirming the company completed its $1.7-billion cleanup of about 40 miles of the upper Hudson River, contaminated with PCBs from two former factories. State Attorney General Letitia James said April 11 that a December state study showed elevated PCB levels in river sediment and concentrations in fish, which were not recovering at the rate EPA anticipated.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com
BKV Barnett, LLC v. Electric Drilling Technologies, LLC: Analyzing the Impact of Colorado’s Anti-Indemnification Statute
December 23, 2024 —
David M. McLain – Colorado Construction Litigation BlogIn the recent case of BKV Barnett, LLC v. Electric Drilling Technologies, LLC, the United States District Court for the District of Colorado dealt with significant legal issues concerning indemnification and insurance obligations in construction agreements. The ruling, handed down on September 26, 2024, serves as a crucial reminder of the limitations imposed by Colorado’s Anti-Indemnification Statute, C.R.S. § 13-21-111.5, and its implications for contracts in the construction industry.
This case arose from a Master Service Contract (“MSC”) between BKV Barnett, LLC (“BKV”) and Electric Drilling Technologies, LLC (“EDT”), in which EDT provided electrical services and equipment to an oil and gas lease wellsite in Texas. Following a lightning strike in early 2022 that damaged electrical infrastructure at the site, EDT dispatched Turn Key Utility Construction to repair the damage. During the repair work, an arc flash occurred, causing significant injuries to one of Turn Key’s employees, Matthew Lara, leading to a personal injury lawsuit filed by Lara in Dallas County, Texas. BKV sought indemnification, defense, and additional insured status from EDT under the terms of their MSC, which EDT contested.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Toll Brothers Shows how the Affluent Buyer is Driving Up Prices
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFJohn McManus of Big Builder explained how prices per square foot are rising due to an increase in more affluent buyers: “Discretionary buyers—ones with access to cash treasure troves, robust and growing stock portfolios, sovereign wealth in search of anti-inflationary investment, and, for good measure, throw in a smattering of seven-figure income households flush with this year’s bonus payouts—are who, unit by unit, have electrified the housing market’s recovery on the heels of institutional bulk buyers of 2012 and early 2013.”
Toll Brothers, according to McManus, “was, is, and will be the organization most committed to home buying’s discretionary buyer.”
“Thanks to the demand for luxury, and for three- and four-bedroom places, we’re seeing pricing-per-square-foot get better and better the greater number of square feet we offer,” David Von Spreckelsen, Toll Brothers City Living division president, told Big Builder.
Read the court decisionRead the full story...Reprinted courtesy of
Oregon Court of Appeals Rules That Negligent Construction (Construction Defect) Claims Are Subject to a Two-Year Statute of Limitations
October 20, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCStatutes of limitations are distinct from statutes of repose. There is a lot of confusion between the two.
Generally, a statute of limitations is a law which sets the maximum period of time which one can wait before filing a lawsuit, depending on the type of case or claim. The periods vary by state and by type of claim. Most states also employ a “discovery rule,” which provides that the statute of limitations does not “accrue” until such time as the plaintiff knew or should have reasonably known that the injury or property damage has occurred.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of