A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Instant Hotel Tower, But Is It Safe?
March 28, 2012 —
CDJ STAFFBroad Sustainable Building has leapfrogged in China’s construction boom by building a thirty-story hotel in just fifteen days in the city of Changsha. According to an article in the Los Angeles Times, most of the building was prefabricated, but most prefabricated buildings require a longer time for assembly. Broad claimed that it cut no corners on safety. However, Zhang Li, a Beijing architect, told the Times that “incredible speed also means incredible risk.”
At the completion date, the interior was still partially finished. Some rooms were furnished, while others weren’t quite so ready. The hotel will be used to house clients who are visiting Broad and some of its employees.
Broad called their process “the most profound innovation in human history” and predicted that soon a third of new buildings worldwide would be constructed this way. The company anticipates using the same process to build taller buildings, with hopes of eventually constructing a 150-story building.
China is currently undergoing a building boom which Zhang attributed to a desire to catch up to the developed world. As a result of this boom, he noted that building inspections are often skipped in China to speed up building.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Assessments Underway After Hurricane Milton Rips Off Stadium Roof, Snaps Crane Boom in Florida
November 05, 2024 —
James Leggate - Engineering News-RecordHurricane Milton and tornados it spurred killed at least five people and knocked out power to 4 million homes and businesses in Florida after making landfall Oct. 9 near Siesta Key in Sarasota County. With assessments and rescues still underway, state officials say the damage was not as bad as it could have been.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Funding the Self-Insured Retention (SIR)
August 17, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnlike a deductible, a self-insured retention (referred to an “SIR”) is, as the name suggests, a self-insured obligation of the insured before its insurer picks up coverage. The SIR needs to be exhausted by the insured (as the primary self-insurance component) before the carrier’s excess defense and indemnification obligations kick-in under the terms of the policy. However, an insured can generally exhaust an SIR by paying legal fees and costs associated with a claim.
Oftentimes, the language in the policy requires the SIR to be paid for by the named insured or an insured under the policy. This was an issue addressed by the Florida Supreme Court in Intervest Const. of Jax, Inc. v. General Fidelity Ins. Co., 133 So.3d 494 (Fla. 2014).
In this matter, a personal injury claimant asserted a claim against the contractor dealing with a residential home. The contractor hired a subcontractor to install attic stairs and the subcontract required the contractor to indemnify it. The owner of the house injured herself on the attic stairs and sued the contractor. The contractor, in turn, sought indemnification against the subcontractor that installed the attic stairs.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Bar Against Forum Selection Clauses in Construction Contracts Extended to Design Professionals
October 28, 2015 —
Garret Murai – California Construction Law BlogIt’s a tactic as old as war itself.
You can often gain a strategic advantage by selecting the location of battle.
The same is true in litigation.
But as the next case illustrates, when it comes to disputes between contractors (and design professionals), it isn’t always the combatants who dictate where the battle will be fought.
Vita Planning and Landscape Architecture, Inc. v. HKS Architects, Inc.
In Vita Planning and Landscape Architecture, Inc. v. HKS Architects, Inc., Case No. A141010, California Court of Appeals for the First District (September 25, 2015), Texas architecture firm HKS Architects, Inc. (“HKS”) was hired to provide architectural services. HKS’ design service agreement included a Texas forum selection clause which provided:
As a condition precedent to the institution of any action [or] lawsuit all disputes shall be submitted to mediation” and “[a]ll claim , disputes, and other matters in question between the parties arising out of or related to the Agreement . . . be resolved by the . . . courts in . . . Texas.”
Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Wendel Rosen Black & Dean LLP
Mr. Murai may be contacted at gmurai@wendel.com
New York Team Secures Appellate Win on Behalf of National Home Improvement Chain
September 26, 2022 — Lewis Brisbois
New York, N.Y. (August 12, 2022) - New York Appellate Partner Nicholas P. Hurzeler, with New York Partners John J. Doody and David M. Pollack, obtained a significant appellate victory on behalf of a national home improvement chain when a New York Appellate Division panel for the Second Department reduced a jury verdict by more than half.
In this matter, which was covered by Law360, the plaintiff was a customer at one of the chain's stores when he was involved in a confrontation with a man and his wife as they exited the store. The chain's loss prevention official told police that the plaintiff had assaulted the female customer. As a result of the incident, the plaintiff was arrested, spent the night in jail, and was arraigned at the same courthouse where he worked as a staff attorney while wearing only an undershirt and jogging shorts. He also had to disclose his arrest on his judgeship nomination application. The charges against him were ultimately dropped after the chain's loss prevention official told prosecutors that surveillance video showed that the female customer’s assault claims were false.
The plaintiff subsequently sued the home improvement chain and its loss prevention official for allegedly causing his false arrest and interfering with his career goal of securing a New York state court judgeship. At the close of the trial in this case, the jury determined that the defendant was liable for battery and false imprisonment, and awarded the plaintiff $1.8 million for pain and suffering. Read the court decision
Read the full story...
Reprinted courtesy of Lewis Brisbois
Reconciling Prompt Payments and Withholding of Retention Payments
March 30, 2016 — Eric J. Rollins, Esq. – Newmeyer & Dillion, LLP
It is common in California for the owners of a project to make monthly payments to a contractor for work as it is completed, but withhold a certain percentage as a guarantee of future satisfactory performance. Contractors almost always pass these withholdings on to their subcontractors. Unsurprisingly, disputes can arise regarding when the withheld retentions must be paid.
Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after receiving all or part of a retention payment. However, an exception exists -- a direct contractor may withhold from the retention paid to a subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount, whenever a “good faith dispute exists between the direct contractor and a subcontractor.” (See Cal. Civ. Code, § 8814, subd. (c).) The problem with the statute is that it offers no help in defining a “good faith dispute,” and the California courts have historically not provided much guidance either. Can a “good faith dispute” be any dispute between the contracting parties, e.g., a dispute regarding change orders, mismanagement, etc.? Or must the dispute relate specifically to the retention? Unfortunately for California litigants, the answer may depend on the appellate district in which the parties find themselves. Read the court decision
Read the full story...
Reprinted courtesy of Eric J. Rollins, Esq., Newmeyer & Dillion, LLP
Mr. Rollins may be contacted at eric.rollins@ndlf.com
9th Circuit Closes the Door on “Open Shop” Contractor
September 04, 2018 — Garret Murai - California Construction Law Blog
At the height of the Great Depression nearly one-quarter of Americans were unemployed. In response, Congress enacted a series of laws including the Smoot-Hawley Tariffs Act, which raised tariffs on foreign goods in an effort to spur domestic investment and to increase the number of jobs. Sound familiar?
Background
The Davis-Bacon Act
Among the new laws enacted by Congress was the Davis-Bacon Act which required contractors on federal works projects to pay their workers the wages prevailing in the area where a project was located, also known as “prevailing wages,” in an effort to stem the practice of employers bringing in lower-wage workers from outside the area. The same year that the Davis-Bacon Act was enacted, California enacted its own prevailing wage law modeled after the Davis-Bacon Act and applicable to state and local public works projects. Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Wendel, Rosen, Black & Dean LLP
Mr. Murai may be contacted at gmurai@wendel.com