Attempt to Overrule Trial Court's Order to Produce Underwriting Manual Fails
April 25, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter being ordered by the trial court to produce its underwriting manual, the insurer's writ of certiorari to quash the order was denied by the Florida Court of Appeals. People's Trust Ins. Co. v. Foster, 2022 Fla. App. LEXIS 542 (Fla. Ct. App. Jan. 26, 2022).
The insured sued after his claim for damage caused by a water pipe in his home that leaked. In discovery, the insurer refused to produce its underwriting manual. Ruling on a motion to compel, the trial court ordered that the manual be produced. The insurer appealed.
On appeal, the insurer argued its underwriting manual was categorically prohibited in breach of contract cases until and unless bad faith litigation commenced. Although courts had quashed the premature discovery of insurers' business practices, claims files, underwriting files, underwriting manuals, and the like in breach of contract actions, there was no categorical legal rule prohibiting discovery of underwriting manuals in breach of contract cases, especially if they were relevant.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Certified Question Asks Hawaii Supreme Court to Determine Coverage for Allegations of Greenhouse Gas Emissions
October 09, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court certified questions to the Hawaii Supreme Court regarding coverage for underlying allegations of greenhouse gas emissions. Aloha Petroleum, Ltd. v. Nat'l Union Fire Ins. Co. of Pittsburgh, 2023 U.S. Dist. LEXIS 156211 (D. Haw. Sept. 5, 2023).
Aloha was sued in two lawsuits, one filed by the County of Maui and the second filed by the City and County of Honolulu. The underlying lawsuits alleged that Aloha disregarded known risks of harm to the counties when selling its fuel products that would inevitably combust and produce greenhouse gasses, particularly carbon dioxide, thereby changing the climate and causing harm to the counties.
Aloha tendered the suits to AIG. Coverage was denied based on AIG's determination there was no "occurrence" and the pollution exclusion barred coverage. Aloha sued AIG in federal district court seeking a declaratory judgment on AIG's obligations under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Balestreri Potocki & Holmes Attorneys Named 2020 Super Lawyers and Rising Star
July 06, 2020 —
Balestreri Potocki & HolmesThe law firm of Balestreri Potocki & Holmes is pleased to announce that Shareholders
Thomas A. Balestreri, Jr. and
Joseph P. Potocki have been selected as 2020 Super Lawyers and Associate
Robin H. Smith has been named a 2020 Rising Star.
Each year no more than 5 percent of the lawyers in the state are selected to receive the honor of being included in the Super Lawyers list and no more than 2.5 percent of the lawyers are selected to the Rising Stars list.
Balestreri has been selected to the Super Lawyers list in the areas of Construction Litigation. Balestreri has dedicated most of his 30 plus years in practice to the representation of developers, property owners, and general contractors in litigation, negotiations, and risk management. A seasoned trial lawyer, he has tried a number of high exposure cases with great success.
Selected as a Super Lawyer in the area of Construction Litigation, Potocki’s practice concentrates on litigation, transactional matters and construction contract drafting and negotiation. His extensive litigation experience involves high-value disputes relating to a wide variety of issues in the real estate, business and construction arenas.
Smith has been named a Rising Star by Super Lawyers in the area of Civil Litigation. In her varied litigation practice, Smith represents individuals and business entities in complex catastrophic personal injury matters. She also represents employers in labor and employment matters and a variety of businesses, including automobile dealers, in breach of contract, unfair competition, unfair business practices, defamation, and consumer claims.
Super Lawyers, a Thompson Reuters business, is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The annual selections are made using a patented multiphase process that includes a statewide survey of lawyers, an independent research evaluation of candidates and peer reviews by practice area. The result is a credible, comprehensive and diverse listing of exceptional attorneys.
Balestreri Potocki & Holmes is headquartered in San Diego, California. The firm provides comprehensive counsel to large and small companies across a wide range of established and emerging industries. Balestreri Potocki & Holmes is located in downtown San Diego at 401 B Street, Suite 1470. More information about the firm can be found at: www.bph-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Balestreri Potocki & Holmes
A Classic Blunder: Practical Advice for Avoiding Two-Front Wars
August 23, 2021 —
William Underwood - ConsensusDocs“Ha ha! You fool! You fell victim to one of the classic blunders – the most famous of which is ‘never get involved in a land war in Asia’ – but only slightly less well-known is this: ‘Never go in against a Sicilian when death is on the line.’”[1]
Vizzini forgot to include “never fight a two-front war with your owner and a subcontractor” on his list of classic blunders, but it certainly belongs there. This article examines practical tips and tricks for general contractors to avoid the classic blunder of a two-front war, including recommended contract provisions and sound project documentation practices.
Admittedly, general contractors face a wide array of obligations on a project. And perhaps one of the most delicate balancing acts is managing relationships with the owner and your subcontractors. But far too often general contractors find themselves in the difficult position of fighting a two-front war against one (or more) of their subcontractors and the project owner.
But this does not always have to be the case—there are ways for general contractors to reduce the risk of finding themselves in a two-front war. And every project does not have to devolve in a circular firing squad with you in the middle. That said, this article comes with the caveat that a general contractor cannot avoid a two-front war in every instance, nor does this article examine every imaginable way to reduce the risk of a two-front war (see e.g. https://www.consensusdocs.org/pass-through-subcontractor-claims-liquidating-agreements-and-avoiding-a-two-front-war/). But this article will provide an overview of several key tools that can be used to minimize the risk of falling into a classic blunder.
Read the court decisionRead the full story...Reprinted courtesy of
William Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Economic Damages Cannot be Based On Speculation
October 16, 2018 —
David Adelstein - Florida Construction Legal UpdatesEconomic damages, unlike non-economic damages (such as those in personal injury disputes), need to rest on a reasonable basis. Economic damages are those routinely seen in a construction dispute. These damages cannot be based on conjecture or guesswork and need to be supported by competent substantial evidence. Otherwise, the economic damages will be deemed too speculative because they are not reasonably quantifiable. I recently discussed a case involving the professional boxer Canelo Alvarez that was sued by a former promoter for unjust enrichment. Although the promoter recovered a jury verdict for unjust enrichment damages against Canelo Alvarez, the verdict was reversed because the methodology utilized by the promoter to demonstrate damages was speculative. This is definitely not what a plaintiff wants to happen after prevailing at the trial level!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Don’t Assume Your Insurance Covers A Newly Acquired Company
February 19, 2019 —
Patrick M. McDermott & Michael S. Levine - Hunton Insurance Recovery BlogThe Supreme Court of Virginia’s decision yesterday finding no coverage for fire damage to a building is a cautionary tale for companies acquiring other companies. Erie Ins. Exch. v. EPC MD 15, LLC, 2019 WL 238168 (Va. Jan. 17, 2019). In that case, Erie Insurance issued a property insurance policy to EPC. The policy covered EPC only and did not cover any subsidiaries of EPC. EPC then acquired the sole member interest in Cyrus Square, LLC. Following the acquisition, fire damaged a building that Cyrus Square owned.
EPC sought coverage under its property insurance policy. Because the policy did not cover Cyrus Square, EPC argued that a provision extending coverage to “newly acquired buildings” applied, contending that EPC had newly acquired Cyrus Square’s building by virtue of becoming the sole member interest in the LLC. Based on the law relative to LLCs and its interpretation of the policy, the Supreme Court of Virginia ruled against EPC. It found that although EPC had acquired Cyrus Square, it had not “newly acquired” the building and so the “newly acquired buildings” coverage extension did not apply.
Reprinted courtesy of
Patrick M. McDermott, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA/VOSH Roundup
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsIn an unusual flurry of occupational safety related activity, the Virginia courts decided two cases in the last week relating to either the review of occupational safety regulations themselves or their enforcement.
In Nat’l College of Business & Technology Inc. v. Davenport (.pdf), the Virginia Court of Appeals considered what constitutes a “serious” violation of the exposure to asbestos Virginia Occupational Safety & Health (VOSH) regulations. The facts found by the Salem, Virginia Circuit Court were that employees of the petitioner college were exposed to asbestos insulation when they were required to enter a boiler room to retrieve paper files. However, no evidence was presented regarding the length of time or level of exposure at the Circuit Court level. Despite the lack of evidence regarding the level or extent of exposure, the Circuit Court upheld the VOSH citation for exposure and the level of violation at a “serious” level with the attendant penalty.
The Virginia Court of Appeals disagreed with the second finding. The appellate court determined that the lack of evidence regarding the level of exposure (whether length or extent) made the serious level violation an error. The Court stated that merely presenting evidence that asbestos is a carcinogen is not enough given the number of carcinogenic materials in existence and then remanded the case back to Circuit Court to reconsider the penalty level.
Read the court decisionRead the full story...Reprinted courtesy of