Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Properly Trigger the Performance Bond
January 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesOriginally Published by CDJ on January 5, 2017
A performance bond is a valuable tool designed to guarantee the performance of the principal of the contract made part of the bond. But, it is only a valuable tool if the obligee (entity the bond is designed to benefit) understands that it needs to properly trigger the performance bond if it is looking to the bond (surety) to remedy and pay for a contractual default. If the performance bond is not properly triggered and a suit is brought upon the bond then the obligee could be the one materially breaching the terms of the bond. This means the obligee has no recourse under the performance bond. This is a huge downside when the obligee wanted the security of the performance bond, and reimbursed the bond principal for the premium of the bond, in order to address and remediate a default under the underlying contract.
A recent example of this downside can be found in the Southern District of Florida’s decision in Arch Ins. Co. v. John Moriarty & Associates of Florida, Inc., 2016 WL 7324144 (S.D.Fla. 2016). Here, a general contractor sued a subcontractor’s performance bond surety for an approximate $1M cost overrun associated with the performance of the subcontractor’s subcontract (the contract made part of the subcontractor’s performance bond). The surety moved for summary judgment arguing that the general contractor failed to property trigger the performance bond and, therefore, materially breached the bond. The trial court granted the summary judgment in favor of the performance bond surety. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
No Occurrence Where Contract Provides for Delays
March 01, 2017 —
Tred R. Eyerly – Insurance Law HawaiiApplying Montana law, the federal district court found there was no coverage for a subcontractor who was sued by the contractor for breach of the subcontract. Phoenix Ins. Co. v. Ed Boland Constr., Inc., 2017 U.S. Dist. LEXIS 6654 (D. Mont. Jan 18, 2017).
Northbank was the general contractor on a project to repair a bridge for the Federal Highway Administration (FHA). Ed Boland Construction, Inc. (EBC) was the subcontractor to perform drilling and pile installation. After beginning its work, EBC ran into difficulties with unforeseen conditions at the work site. The FHA informed Northbank that it had concerns over EBC's ability to complete the work. The FHA alleged that EBC had brought equipment to the work site that differed from the equipment it had represented would be used.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Reinsurer Must Reimburse Health Care Organization for Settlement Costs
June 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Supreme Court reversed summary judgment issued to reinsurer Continental Casualty Company (CNA) and determined it must reimburse the insured for settlement costs under the E & O policy. Wellpoint, Inc., et al. v. National Union Fire Ins. Co. of Pittsburgh, PA, et al., 2015 Ind. LEXIS 316 (Ind. April 22, 2015).
Anthem, Inc. was a large managed health care organization. Anthem was its own primary and excess insurer for E&O liability. It had numerous excess reinsurers. Beginning in 1998, anthem was confronted by various lawsuits alleging it and other managed care organizations failed to pay claims in a full and timely manner, thereby breaching state and federal statutes. The various lawsuits alleged substantially the same wrongful conduct, namely that after promising to pay doctors in a timely manner for their services, Anthem sought to improperly deny, delay and diminish payments due.
The cases were consolidated into a federal multi-district litigation proceeding in the Southern District of Florida. Claims for breach of contract, unjust enrichment, and violations of state prompt pay statutes were dismissed or dropped. Anthem then settled the underlying litigation in July 2005 without admitting and instead denying any wrongdoing or liability. The settlement called for both cash payments and implementation of specific business practices consistent with requested injunctive relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Richest NJ Neighborhood Fights Plan for Low-Cost Homes on Toxic Dump
May 28, 2024 —
Nacha Cattan - BloombergJosh Bauers has long had his sights set on the town dump in Millburn.
Bauers wants to put 75 affordable apartments on the site where piles of Styrofoam and food scraps lie in heaps.
But that’s a bridge too far for many residents of New Jersey’s richest ZIP code, Short Hills, where multimillion dollar Tudor and colonial-style mansions are perched atop grassy hillocks less than an hour’s commute from Manhattan.
Many in the community, favored by finance types and lawyers, are up in arms over the development’s potential effect on the environment and its highly-rated schools. But the years-long fight to put affordable housing in the town has become about far more than that, and has raised accusations over inequality and race.
Millburn Township, whose largest community is Short Hills, may be forced to build on the dump after a state court ruled last month that it will decide where the development will go. The town had agreed to build on the polluted site three years ago, only to backtrack.
Read the court decisionRead the full story...Reprinted courtesy of
Nacha Cattan, Bloomberg
Mixing Concrete, Like Baking a Cake, is Fraught with Problems When the Recipe is Not Followed
February 26, 2015 —
Garret Murai – California Construction Law Blog“Mixing concrete, like baking a cake, is fraught with problems when the recipe is not followed.” – Justice Kenneth Yegan, State Ready Mix, Inc. v. Moffatt & Nichol, California Court of Appeal for the Second District, Case No. B253421 (January 8, 2015).
I love jurists who aren’t afraid to mix in a little humour in their opinions.
But “[t]he law,” as a framed needlepoint in one of my colleague’s offices says, “is serious business.” And the State Ready Mix case involved one of the thorniest problems in construction litigation:
What to do when you’re sued and you think someone else is to blame.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Vaccine Mandate Confusion Continues – CMS Vaccine Mandate Restored in Some (But Not All) US States
January 03, 2022 —
David S. Harvey, Jr. & Sarah Hock - Lewis BrisboisTampa, Fla. (December 16, 2021) - As has been widely publicized, the Biden Administration has attempted to impose various forms of vaccine mandates under a variety laws and programs. At the same time, we have seen a flurry of opposition to these efforts ranging from new state laws (for example, in Florida) to court challenges seeking to enjoin the effort.
One of the federal mandates was issued by the Centers for Medicare & Medicaid Services (CMS) and is applicable to staff at Medicare- and Medicaid-certified healthcare providers. Initially, fourteen states sued in opposition to the CMS mandate and were able to obtain a nationwide injunction issued by a federal district judge in Louisiana. That injunction was appealed to the Fifth Circuit Court of Appeals, which has now issued a decision that awards points to both sides.
The Fifth Circuit ruled the injunction only applies to the 14 states that participated in the Louisiana lawsuit and not nationwide. Those states are Alabama, Arizona, Georgia, Idaho, Indiana, Kentucky, Louisiana, Mississippi, Montana, Ohio, Oklahoma, South Carolina, Utah, and West Virginia. This opinion has the potential to revive the CMS vaccine mandate in just over half of U.S. states. We can anticipate new suits will be filed as to other states, with the outcome still uncertain. It is unknown at this point whether the United States Supreme Court will agree to review the issues when such review is sought in the near future.
Reprinted courtesy of
David S. Harvey, Jr., Lewis Brisbois and
Sarah Hock, Lewis Brisbois
Mr. Harvey may be contacted at David.Harvey@lewisbrisbois.com
Ms. Hock may be contacted at Sarah.Hock@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Breach of an Oral Contract and Unjust Enrichment and Implied Covenant of Good Faith and Fair Dealing
December 23, 2023 —
David Adelstein - Florida Construction Legal UpdatesIn an ideal world, parties would have written contracts. In reality, parties should endeavor to ensure every transaction they enter into is memorialized in a written contract. This should not be disputed. Of course, written contracts are not always the case. Parties enter transactions too often whereby the transaction is not memorialized in a clean written agreement. Rather, it is piecemealing invoices, or texts, or discussions, or proposals and the course of business. A contract can still exist in this context but it is likely an oral contract. Keep in mind if there is a dispute, what you think the oral contract says will invariably be different than what the other party believes the oral contract says. This “he said she said” scenario gets removed, for the most part, with a written contract that memorializes the written terms, conditions, and scope.
A recent federal district court opinion dealt with the alleged breach of an oral contract. In Movie Prop Rentals LLC vs. The Kingdom of God Global Church, 2023 WL 8275922 (S.D.Fla. 2023), a dispute concerned the fabrication and installation of a complex, modular stage prop to be used for an event. But here lies the problem. The dispute was based on an oral contract and invoices. The plaintiff, the party that was fabricating the modular stage prop, sued the defendant, the party that ordered the stage prop for the event, for non-payment under various claims. The defendant countersued under various claims.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com