Out of the Black
May 30, 2022 —
John Drentlaw - Construction ExecutiveEven if you previously weren’t familiar with the term “black swan event,” you’ve likely become intimately familiar with what one looks like over the past two years. Coined by author Nassim Taleb in his book The Black Swan: The Impact of the Highly Improbable, the term refers to a rare, unpredictable event—perhaps, say, a pandemic—that has an extreme impact.
“Extreme” certainly seems to be an accurate description of the impact that the COVID-19 pandemic has had on the construction industry, at nearly every level. The Commercial Construction Index (CCI) fell from 74 to 56 during Q2 2020 and remained statistically unchanged through Q3 of that year. Recovery has been slow, with the CCI remaining eight points below pre-pandemic levels through the end of 2021. Prices for raw materials such as lumber and steel have been extremely volatile, reaching historic highs and dramatic lows. March and April of 2020 alone saw 1.1 million jobs disappear from the industry—roughly half as many jobs as were lost throughout the entire Great Recession (although many of these jobs have since returned).
While the industry has persevered through what should be the worst of these effects, many contractors and project owners are now wondering: How can we predict the next black swan event?
Reprinted courtesy of
John Drentlaw, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Peak of Hurricane Season Is Here: How to Manage Risks Before They Manage You
September 21, 2020 —
Vincent E. Morgan - Construction ExecutiveThe Atlantic hurricane season runs from June 1 to Nov. 30, but it peaks sharply during August, September and October. The latest forecasts predict this will be one of the most active seasons in history, in terms of frequency and severity, though it is always important to remember that even a single hurricane or tropical storm making landfall can still be a devastating event.
Hurricanes pose unique risks to the construction industry ranging from project and labor force disruptions to concerns about the availability and price of construction materials. This is even more true this year, which requires merging hurricane preparedness and response plans with the realities of COVID-19. Because hurricanes cannot be avoided, preparing for them is the only way to manage these risks. Ensuring the personal safety and wellbeing of affected individuals is the first priority. After that, here are some key issues, and suggestions for handling them, that may help guide construction companies through the storm.
SITE PROTECTION
Construction contracts often place responsibility for site protection on contractors. Where those duties exist, failing to properly carry them out can lead to enormous losses that then turn into liability claims. This could be anything from removing materials that can become projectiles, covering exposed ventilation shafts, and sealing electrical conduits to ensuring that key equipment such as generators and pumps can remain functional in a storm. One way to approach it is to imagine sustained 100-mph winds and relentless water, and then make sure preparedness efforts are likely to survive that kind of test. This is not the time for guessing. It is far better to go through a rigorous analytical process now than in a courtroom years later.
Reprinted courtesy of
Vincent E. Morgan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “You Left Out a Key Ingredient!”
September 12, 2023 —
Daniel Lund III - Lexology“Baking is as much of a science as it is an art. It’s important to take the time to understand what you’re doing and why. Skipping steps can make or break your cupcakes, and there are a lot of things that can go wrong when baking from scratch.”
And so it is with construction contract drafting.
Defendants on a Miller Act claim filed by a second-tier subcontractor in federal court in Pensacola, Florida, sought to have the case transferred to Virginia, based upon a forum selection clause in the first-tier subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Home Builders and Developers Beware: SC Supreme Court Beats Up Hybrid Arbitration Clauses Mercilessly
November 15, 2022 —
Matthew Devries - Best Practices Construction LawToday’s guest post is by one of my favorite construction lawyers and friends, Burr partner Ned Nicholson in our Columbia, SC office. Ned regularly represents clients in construction defect and compensation claims, manufacturer/dealer disputes, and insurance coverage lawsuits. He is also a South Carolina certified mediator. Ned can be reached at nnicholson@burr.com or (803) 799-9800.
If you are a homebuilder, residential housing developer, construction industry insurer, or any one of the many participants in the industry providing affordable and decent housing for the citizens of South Carolina, you are already aware that South Carolina courts have for decades prioritized the promotion of consumer (i.e., home buyer) rights, usually at the expense of the providers of housing. There is nothing inherently wrong with that; the goal is laudable. But as in so many things, the implementation has been extremely costly for the residential construction industry as a savvy plaintiff’s bar has taken advantage of grey areas that are inevitably created in our judicial system.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Devries, Burr & Forman LLPMr. Devries may be contacted at
mdevries@burr.com
Colorado General Assembly Sets Forth Prerequisites for an Insurance Company to Use Failure to Cooperate as a Defense to a Claim for First Party Insurance Benefits
August 10, 2020 —
Christine Kroupa, John Palmeri & Katelyn Werner - Gordon & ReesDespite first party insurance policies generally requiring cooperation from an insured in the investigation of a claim, insurers can no longer rely on the failure to cooperate as a defense in a claim for first party insurance benefits in Colorado unless certain conditions are met.
The Bill:
On July 2, 2020, Colorado Governor Jared S. Polis signed House Bill 20-1290 which addresses the ability of an insurer to use a failure to cooperate defense in an action where the insured has made a claim for benefits under an insurance policy. This bill bars an insurer from raising the failure to cooperate unless the following conditions are met:
- The insurer submitted a written request to the insured or the insured’s representative for the information (via electronic means if consent was given by insured or insured’s representative, or via certified mail);
- The information is not available to the insurer without the assistance of the insured;
- The written request provides the insured 60 days to respond;
- The written request is for information a reasonable person would determine the insurer needs to adjust the claim filed by the insured or to prevent fraud; and
- The insurer gives the insured an opportunity to cure, which must:
- Provide written notice to the insured of the alleged failure to cooperate, describing with particularity the alleged failure within 60 days after the alleged failure; and
- Allow the insured 60 days after receipt of the written notice to cure the alleged failure to cooperate.
Reprinted courtesy of Gordon & Rees attorneys
Christine Kroupa,
John Palmeri and
Katelyn Werner
Ms. Kroupa may be contacted at ckroupa@grsm.com
Mr. Palmeri may be contacted at jpalmeri@grsm.com
Ms. Werner may be contacted at kwerner@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Bailout for an Improperly Drafted Indemnification Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact. In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect).
This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts. Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06. The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06. (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Biden Unveils $2.3 Trillion American Jobs Plan
May 10, 2021 —
Garret Murai - California Construction Law BlogThis past week, President Biden unveiled his American Jobs Plan, a $2.3 trillion dollar plan to upgrade the nation’s infrastructure over 8 years.
As we wrote about this past month, the American Society of Civil Engineers recently issued its 2021 Infrastructure Report Card which gave the country’s infrastructure a cumulative grade point average across several areas including roads, public transportations and schools of a disappointing C-. According to a White House fact sheet on the American Jobs Plan, while the United States is the wealthiest county in the world it currently ranks 13th when it comes to the overall quality of its infrastructure.
Infrastructure spending at the federal level has historically been paid for through the gas tax. Currently, that tax is 18.4 cents per gallon for gasoline and 24.4 cents per gallon for diesel. The last time the federal gas tax was increased, however, was nearly 30 years ago in 1993. The reason for this long hiatus? Voter backlash and backlash by big businesses whose fleets still primarily rely on fossil fuels and diminishing returns as the number of electrical and hybrid vehicles increasingly hit the streets.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com