Texas Mechanic’s Lien Law Update: New Law Brings a Little Relief for Subcontractors and a Lot of Relief for Design Professionals
June 07, 2021 —
Tracey L. Williams - Peckar & Abramson, P.C.After several recent failed attempts to amend Chapter 53 of the Texas Property Code (the “Texas Mechanic’s Lien Statute”), it appears that long awaited relief may, at least in part, be on the horizon for subcontractors in Texas. Additionally, architects, engineers, and surveyors also appear to be significant benefactors of House Bill 2237 (“HB 2237”). Under existing law, many subcontractors often fail to perfect their mechanic’s liens under the Texas Mechanic’s Lien Statute because of complex notice requirements which must be sent for every month in which labor or material are furnished. And architects, engineers and surveyors currently have no lien rights unless they have a direct contractual relationship with the owner of the project. Effective January 1, 2022, HB 2237 amends the Texas Mechanic’s Lien Statute in several significant respects.
Subcontractor Impacts
HB 2237 impacts subcontractors in the following ways:
- Establishes uniformity in the notice requirements by imposing the same notice obligation on all subcontractors regardless of with whom they have contracted. Rather than sending one notice to the owner and one to the general contractor, the single notice now required must be sent to both simultaneously. Additionally, HB 2237 prescribes the form of the notice to be given under both Section 53.056 (notice of derivative claimant) and 53.057 (notice of contractual retainage).
Read the court decisionRead the full story...Reprinted courtesy of
Tracey L. Williams, Peckar & Abramson, P.C.Ms. Williams may be contacted at
twilliams@pecklaw.com
Claim Against Broker for Failure to Procure Adequate Coverage Survives Summary Judgment
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe broker's motion for summary judgment, seeking to dismiss negligence claims for failure to obtain adequate coverage, was denied by the court in Voss v. The Netherlands Ins. Co., 2014 N.Y. LEXIS 384 (N.Y. Ct. App. Feb. 25, 2014).
The insured met with a representative of CH Insurance Brokerage Services Co., Inc. (CHI) to discuss coverage for the premises and her two companies. At CHI's request, the insured shared information on sales figures for calculating business interruption coverage. The broker represented that CHI would reassess and revisit the coverage needs as her business grew.
CHI recommended $75,000 per incident in coverage for business interruption losses. The insured questioned whether the $75,000 limit was adequate, but the broker assured her that it was sufficient. The insured then accepted the recommendation. Subsequently, the insured's business grew, but CHI renewed the policy with the same $75,000 business interruption limit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mississippi Supreme Court Addresses Earth Movement Exclusion
December 09, 2019 —
Anthony Hatzilabrou - Traub LiebermanRecently, the Mississippi Supreme Court held that structural damages to the foundation of an insured’s home came within the earth movement exclusion in a homeowner’s policy, notwithstanding a provision in the policy which provided coverage for water damage resulting “from accidental discharge or overflow of water … from within … [p]lumbing, heating, air condition or household appliance.”
In Mississippi Farm Bureau Cas. Ins. Co. v. Smith, 264 So. 3d 737 (Miss. 2019), the appellee, Smith, filed a lawsuit against her homeowner's insurance company, Mississippi Farm Bureau Casualty Insurance Company (“Farm Bureau”) for its refusal to pay for repairs to the foundation of Smith’s home. Smith alleged that the refusal to pay for repairs amounted to breach of contract and asserted claims for bad faith and tortious breach of contract. In response, Farm Bureau filed a motion for summary judgment on the basis of the policy’s earth-movement exclusion, which provided that Farm Bureau “did not insure for loss caused directly or indirectly by…Earth Movement…[which] means…[a]ny other earth movement including earth sinking, rising or shifting... caused by or resulting from human or animal forces.” Smith filed a cross-motion for partial summary judgment on the basis that the earth-movement exclusion did not preclude coverage because her insurance policy also contained a clause expressly covering water damage.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Hatzilabrou, Traub LiebermanMr. Hatzilabrou may be contacted at
thatzilabrou@tlsslaw.com
How BIM Can Serve Building Owners
September 17, 2018 —
Aarni Heiskanen - AEC BusinessBuilding Information Models typically end their active life after the construction phase. An experimental project was initiated to find out whether and how they can serve owners throughout the life cycle of a building.
Gradia, the Jyväskylä Educational Consortium, provides education to students of all ages in central Finland. It has around 25,000 students, a staff of 1,100, and buildings with a total floor area of 150,000 square meters. Gradia and a team from Gravicon and XRM Finland carried out a government-supported KIRA-digi experimentation project in 2017 on the use of BIMs for building maintenance and repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Traub Lieberman Attorneys Recognized as 2022 New York – Metro Super Lawyers®
October 17, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that seven Partners from the Hawthorne, NY Office have been selected to the 2022 New York - Metro Super Lawyers list.
2022 New York – Metro Super Lawyers
- Copernicus Gaza – Insurance Coverage
- Jonathan Harwood – Professional Liability
- Lisa Rolle – Construction Litigation
- Christopher Russo – Professional Liability
- Lisa Shrewsberry – Professional Liability
- Stephen Straus – Insurance Coverage
- Richard Traub – Insurance Coverage
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Agreement Authorizing Party’s Own Engineer to Determine Substantial Compliance Found Binding on Adverse Party
August 30, 2021 —
Garret Murai - California Construction Law BlogWhen it comes to resolving construction disputes it’s a bit like the “31 Flavors” of Baskin Robins. There’s a flavor for nearly everyone. From mediation, to arbitration, to litigation, to dispute resolution boards (DRBs), to the architect as the “initial decision maker” under AIA contracts, parties and their counsel have developed numerous ways to resolve disputes on construction projects, including by expert review.
But if you’re going to agree to a dispute resolution procedure, make sure it’s one you can live with, because if you don’t, it’s often going to be too late to go back to the proverbial drawing board as the parties in the next case discovered.
The Coral Farms Case
In December 2010, a mudslide impacted three properties in San Juan Capistrano, California. One of the properties was owned by Coral Farms, L.P., another by Paul and Susan Mikos, and the third by Thomas and Sonya Mahony.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Get Creative to Solve Your Construction Company's Staffing Challenges
February 25, 2024 —
Kit Dickinson - Construction ExecutiveConstruction projects are on the rise due to a generational investment in infrastructure spending. The Infrastructure Investment and Jobs Act passed by Congress in August 2021 includes around $550 billion in new federal investment in America’s roads and bridges, water infrastructure and more to be allocated over the next five years.
Because of the influx of federal funds for infrastructure, construction firms that previously focused on local, private sector clients are incentivized to pursue public projects in other states and regions. There are a couple of bumps in the road, however. Payroll becomes more complex when you’re paying across multiple jurisdictions and at different pay rates, and reporting requirements for government work make managing projects and controlling costs trickier. Add to this the changes in the Davis-Bacon Act prevailing wage rules which went into effect on October 23, 2023. To capture this business and make it worthwhile, construction professionals need technology built specifically for the industry.
Reprinted courtesy of
Kit Dickinson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Breach of an Oral Contract and Unjust Enrichment and Implied Covenant of Good Faith and Fair Dealing
December 23, 2023 —
David Adelstein - Florida Construction Legal UpdatesIn an ideal world, parties would have written contracts. In reality, parties should endeavor to ensure every transaction they enter into is memorialized in a written contract. This should not be disputed. Of course, written contracts are not always the case. Parties enter transactions too often whereby the transaction is not memorialized in a clean written agreement. Rather, it is piecemealing invoices, or texts, or discussions, or proposals and the course of business. A contract can still exist in this context but it is likely an oral contract. Keep in mind if there is a dispute, what you think the oral contract says will invariably be different than what the other party believes the oral contract says. This “he said she said” scenario gets removed, for the most part, with a written contract that memorializes the written terms, conditions, and scope.
A recent federal district court opinion dealt with the alleged breach of an oral contract. In Movie Prop Rentals LLC vs. The Kingdom of God Global Church, 2023 WL 8275922 (S.D.Fla. 2023), a dispute concerned the fabrication and installation of a complex, modular stage prop to be used for an event. But here lies the problem. The dispute was based on an oral contract and invoices. The plaintiff, the party that was fabricating the modular stage prop, sued the defendant, the party that ordered the stage prop for the event, for non-payment under various claims. The defendant countersued under various claims.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com