Velazquez Framing, LLC v. Cascadia Homes, Inc. (Take 2) – Pre-lien Notice for Labor Unambiguously Not Required
May 13, 2024 —
Travis Colburn - Ahlers Cressman & SleightPre-lien Notice for Labor Unambiguously Not Required.
In January 2024, almost a year after Division 2 of the Washington Court of Appeals decided Velazquez Framing, LLC v. Cascadia Homes, Inc.,1 the Washington Supreme Court, sitting en banc, reversed and remanded the matter for further proceedings.2
The relevant background facts are that Cascadia Homes, Inc. (“Cascadia”), was a general contractor and also owned the property that was the subject matter of the underlying dispute. Cascadia wished to construct a new home on the property. Cascadia hired High End Construction, LLC (“High End”) – a framing subcontractor – to provide framing for the new home. High End, in turn, hired Velazquez Framing, LLC (“Velazquez”). Velazquez did not provide Cascadia – the owner – with notice of its statutory right to claim a lien.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Third Circuit Court of Appeals Concludes “Soup to Nuts” Policy Does Not Include Faulty Workmanship Coverage
December 11, 2018 —
Timothy Carroll - White and Williams LLPEarlier this month, in Frederick Mutual Insurance Company v. Hall, the U.S. Court of Appeals for the Third Circuit concluded that coverage for faulty workmanship claims is “simply not the kind of coverage insurance agents and insurance companies expect to provide” to construction industry professionals “unless the insured explicitly requests such coverage.” 2018 U.S. App. LEXIS 31666, at *9 (3d Cir. Nov. 8, 2018). In Hall, a stone masonry contractor was sued by its customer for causing over $350,000 in property damage resulting from “substandard and defective work” performed on the customer’s residence. The insurer sought a declaration that it owed neither a defense nor indemnity for those damages because, under Pennsylvania law, the policy did not cover property damage caused by faulty workmanship.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy Carroll, White and Williams LLPMr. Carroll may be contacted at
carrollt@whiteandwilliams.com
Termination of Construction Contracts
November 30, 2020 —
Stuart Rosen - Construction ExecutiveLately, in view of the COVID-19 pandemic, there is a heightened concern that some construction projects will not proceed as planned. Therefore, it is important to review each party’s right to terminate a construction contract and to examine some of the resulting consequences.
While the parties to a construction contract can, as always, agree to other mutually acceptable terms and provisions, in broad terms, a typical construction contract includes four triggering events that can lead to termination.
First, an owner can terminate a construction contract if the contractor defaults and thereafter fails to cure such default, which may include, without limitation, the failure to remediate deficient work, the failure to meet the construction schedule, the failure to pay subcontractors and the failure to comply with applicable law. A contractor must be mindful of the fact that in the case of such termination by the owner for cause, the vast majority of construction contracts provide that the contractor will not be entitled to receive any further payment for work performed by the contractor until the work is finished.
Reprinted courtesy of
Stuart Rosen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rosen may be contacted at
srosen@proskauer.com
The Dog Ate My Exclusion! – Georgia Federal Court: No Reformation to Add Pollution Exclusion
September 28, 2017 —
Philip M. Brown-Wilusz - Saxe Doernberger & Vita, P.C.While schoolchildren know that the classic “the dog ate my homework” excuse doesn’t work, insurance companies are willing to try a variation of that excuse. Ace American Insurance Company (Ace), sold a property policy (the Policy) to Exide Technologies, Inc. (Exide). Exide sought coverage under the Policy for acid damage at its former battery factory. Ace denied coverage, citing to the pollution exclusion. The only problem? The Policy contained no pollution exclusion!
Exide had procured policies from other insurers for several years prior to the inception of the Policy, all of which contained pollution exclusions. Exide instructed Marsh USA Inc. (Marsh), its broker, to procure insurance “on the same or better terms and conditions.” The resulting policy contained no pollution exclusion, and Exide sought coverage under the Policy for pollution-related losses.
Read the court decisionRead the full story...Reprinted courtesy of
Philip M. Brown-Wilusz, Saxe Doernberger & Vita, P.C.Mr. Brown-Wilusz may be contacted at
pbw@sdvlaw.com
Reminder: In Court (as in life) the Worst Thing You Can Do Is Not Show Up
September 28, 2017 —
Christopher G. Hill - Construction Law MusingsAs long time (and possibly recent) readers of Construction Law Musings know, I am a Virginia Supreme Court Certified Mediator. In that capacity, I spend quite a bit of time sitting in general district court courtrooms in places like Goochland and Caroline Counties “court sitting” awaiting a referral from the judge of a case with parties ready and willing to take advantage of the mediation process.
As I sit there wearing my mediator “hat,” I see case after case be called for the first return date. Without fail, several cases are called where the defendant fails to appear after being served with process. There are even a case or two where the plaintiff (the party that picked the return date in the first place) fails to appear. In the first instance, where the defendant doesn’t appear, the judge almost inevitably enters a judgment for the amount sued for by the plaintiff. In the latter instance, the case is dismissed without prejudice to the plaintiff with a shake of the head by the judge at the wasted time and filing fee. This post focuses on the first case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Chambers USA 2021 Ranks White and Williams as a Leading Law Firm
June 07, 2021 —
White and Williams LLPWhite and Williams is once again recognized by Chambers USA as a leading law firm in Pennsylvania for achievements and client service in the areas of insurance law, real estate finance and banking and finance law. The firm has also been recognized for achievements and client service in banking and finance law in Philadelphia and the surrounding area. In addition, five lawyers received individual honors – two for their work in insurance, one for his work in real estate finance, another for her work in bankruptcy and restructuring and one for his work in commercial litigation.
White and Williams is acknowledged for our renowned practice offering exceptional representation to insurers and reinsurers across an impressive range of areas including coverage, bad faith litigation and excess liability. The firm is recognized for notable strength in transactional and regulatory matters, complemented by the team's adroit handling of complex alternative dispute resolution proceedings. Chambers USA also acknowledged the firm's broad trial capabilities, including handling data privacy, professional liability, toxic tort coverage claims, and experience in substantial claims arising from bodily injury and wrongful death suits. White and Williams' cross-disciplinary team is also highlighted, as one source commented that "all advice was reasoned and respectful. They worked well together and provided exceptional representation."
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
UPDATE: Trade Secrets Pact Allows Resumed Work on $2.6B Ga. Battery Plant
April 19, 2021 —
Mary B. Powers - Engineering News-RecordConstruction on a $2.6-billion battery manufacturing plant near Atlanta can continue under an agreement reached April 11 between two rival South Korean auto battery makers—including SK Innovation, which is owner of the half-completed project.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Developers Celebrate Arizona’s Opportunity Zones
May 24, 2018 —
Patrick J. Paul - Snell & Wilmer Real Estate Litigation BlogPresident Trump’s Tax Cuts and Jobs Act passed by Congress in December included a new community development program designed to promote investment in low income urban and rural communities. These “Opportunity Zones” provide that every Governor may nominate up to 25% of qualifying low-income Census tracts for consideration in the program which provides substantial reductions on capital gains taxes with the greatest benefits to those holding their investments for a period of at least 10 years.
States were required by March 21st to submit nominations or request a 30 day extension to subsequently submit. The Treasury Department in turn has 30 days from the date of submission to designate the nominated zones. On April 9, 2018, the Treasury Department and the IRS formally dedicated opportunity zones in 18 states including Arizona. The Department will make future designations as submissions by the states that have requested an extension are received and certified.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Paul, Snell & WilmerMr. Paul may be contacted at
ppaul@swlaw.com