Court Finds That SIR Requirements are Not Incorporated into High Level Excess Policies and That Excess Insurers’ Payment of Defense Costs is Not Conditioned on Actual Liability
April 22, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Deere & Co. v. Allstate Ins. Co. (No. A145170, filed 2/25/19), a California appeals court held that the insured was not required to pay additional self-insured retentions (SIRs) in order to trigger higher level excess coverage because the retained limits applicable to the first layer of coverage did not also apply to the higher-layer excess policies.
In Deere, the insured was sued for injuries from alleged exposure to asbestos-containing assemblies used in Deere machines. In a declaratory relief action against its umbrella and excess insurers, the case was tried on: (1) whether the higher-layer excess policies were triggered once the first-layer excess policy limits, which were subject to an SIR paid by Deere, had been exhausted; and (2) whether the insurers’ indemnity obligation extended to Deere’s defense costs incurred in asbestos claims that had been dismissed. The trial court found in favor of the insurers, concluding that the retained limits in the first layer of coverage also applied to the higher-layer excess, which was not triggered until Deere paid additional SIRs. The court also concluded that the insurers were not obligated to pay defense costs when underlying cases were dismissed without payment to a claimant either by judgment or settlement.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of
Contractors Struggle with Cash & Difficult Payment Terms, Could Benefit From Legal Advice, According to New Survey
December 30, 2019 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back with a post from my pal Scott Wolfe. Scott is the founder and CEO of Levelset, which is used by thousands of contractors to make payments fast and easy. Scott, previously a construction attorney himself, founded Levelset to even the $1 trillion construction playing field, and is on a mission to make payments less stressful for contractors and suppliers across the globe.
Getting paid in construction is slow, hard, and stressful, according to a survey conducted by Levelset & TSheets by Quickbooks that polled over 500 construction professionals. Half of the contractors surveyed complained that they did not get paid on time, which caused serious cash flow issues that negatively impacted their customer relationships and frequently forced them to dip into personal savings and lines of credit to keep their business afloat.
View the 2019 Construction Payment Report here.
Unfortunately, since the construction industry’s slow payment problems are well-documented, this sad reality isn’t too surprising. The findings, though, do demonstrate a massive cash crunch for the 1.5 million+ contractors in the United States, and underscores the importance of having legal help and counsel from a construction lawyer before, during, and after jobs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Constructive Change Directives / Directed Changes
June 06, 2018 —
David Adelstein - Florida Construction Legal Updatesrime contracts typically contain a constructive change directive clause. A constructive change directive also goes by the acronym CCD (and for purposes of this article, such changes will be referred to as a CCD), however it can also be known as a Work Change Directive, Interim Directed Change, or Directed Change, depending on the type of contract beign utilized. An owner can order a CCD, versus issuing the contractor a formalized change order, as a mechanism to direct the prime contractor to perform work if there is a dispute as to contract amount, time, or scope. Just because an owner issues a CCD does not mean the owner is conceding that it owes the contractor a change order. Rather, the owner is ordering the CCD as a mechanism to keep the project moving forward notwithstanding a disagreement with the contractor as to the price or time impact. Standard form construction agreements such as the AIA, EJCDC, or ConsensusDocs, will have a standard provision dealing with change directives where the owner can order the contractor to proceed with work in the absence of a change order. In the federal government context, most construction contracts will contain a changes clause that authorizes the government to formally direct changes; and, there is authority for contractors to equitably pursue a constructive change based on certain directives or instructions issued by the government. Naturally, from the contractor’s perspective, this CCD provision is an important consideration as it could likely require the contractor to finance a change to the owner’s project, particularly if there is a scope dispute where the owner does not believe the contractor is entitled to any change order.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Party Loses Additional Insured Argument by Improper Pleading
September 20, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Archdiocese failed to plead breach of contract against the County for failure to name the Archdiocese as an additional insured under the liability policy. Pachella v. Archdiocese of Philadelphia, 2017 Pa. Commw. Unpub. LEXIS 595 (Pa. Commw. Ct. Aug. 14, 2017).
Richard and Pachella filed a complaint against the Archdiocese, alleging that Mrs. Pachella was injured when she tripped and fell on the sidewalk outside of St. Patrick's Parish. At the time, the County was leasing St. Patrick's premises for use as an election polling place. The Archdiocese filed a third party complaint alleging negligence and breach of contract claims under a Lease Agreement between St. Patrick's and the County.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Kiewit and Two Ex-Managers Face Canada Jobsite Fatality Criminal Trial
October 12, 2020 —
Scott Van Voorhis - Engineering News-RecordCanada appears set to try a rare criminal case against a major company—U.S. contractor Kiewit Corp.—for a workplace fatality stemming from a more than decade-old accident on a remote British Columbia hydroelectric project that killed a 24-year-old field employee.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Limits Indemnification Obligations of Design Professionals
August 24, 2017 —
William L. Doerler - White and Williams LLPThe California legislature recently enacted legislation – SB 496 – limiting a design professional’s indemnification obligations in private contracts related to design services. The term “design professional” refers to licensed architects, landscape architects and professional land surveyors, and registered professional engineers. As revised, Cal. Civ. Code § 2782.8 states that, for all contracts entered into on or after January 1, 2018 for design professional services, all provisions that purport to have the design professional indemnify the indemnitee for claims against the indemnitee – or require the design professional to provide a defense to the indemnitee – are unenforceable except to the extent that the claims against the indemnitee arise out of, or relate to, the negligence, recklessness or willful misconduct of the design professional. In addition, as revised, § 2782.8 limits a design professional’s liability for the cost of defense to the design professional’s percentage of fault.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Fourth Circuit Finds Insurer Reservation of Rights Letters Inadequate to Preserve Coverage Defenses Under South Carolina Law
January 17, 2023 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Stoneledge at Lake Keowee Owners Ass'n v. Cincinnati Ins. Co., 2022 U.S. App. LEXIS 34292 (D.S.C. Dec. 13, 2022), the Fourth Circuit Court of Appeals addressed the adequacy of reservation of rights letters issued by Builders Mutual Insurance Company (“Builders Mutual”) and Cincinnati Insurance Company (“Cincinnati”) to their insureds, Marick Home Builders, LLC (“Marick”) and Rick Thoennes (“Thoennes”), Marick’s managing member, for an underlying construction defect lawsuit. In short, the Fourth Circuit found that the reservation letters were inadequate to preserve the insurers’ coverage defenses because they did not sufficiently explain the basis of the carriers’ position.
Stoneledge, a homeowners association, managed a community of 80 townhomes on South Carolina’s Lake Keowee. In 2009, Stoneledge brought suit against Marick and Thoennes, among other defendants, alleging construction defects in the townhomes that resulted in water intrusion and other physical damage. Marick and Thoennes held commercial general-liability policies through Cincinnati and Builders Mutual covering, in relevant part, “property damage” as defined by the policies. Builders Mutual issued policies covering the period from January 2004 to October 2007, and Cincinnati issued policies covering the period from April 2008 to April 2012. After Marick notified the insurers of the underlying action, Builders Mutual sent Marick two reservation of rights letters, one in May 2009 and one in July 2009. Cincinnati sent Marick one reservation of rights letter in March 2010.
In March 2014, Stoneledge brought a declaratory-judgment action against Cincinnati seeking coverage for a judgment entered in the underlying action. The insurers removed the case to federal court, and in September 2016, Stoneledge amended its complaint, adding Builders Mutual as a defendant and seeking coverage for additional damages pursuant to a settlement agreement entered into by Stoneledge, Marick, Thoennes. The district court granted Stoneledge's motion for summary judgment, primarily on the ground that the insurers failed to reserve the right to contest coverage. The insurers appealed to the Fourth Circuit, which affirmed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Sinking Floor Does Not Meet Strict Definition of Collapse
August 17, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that the sinking of the insured's floor caused by termites and rot deterioration did not meet the homeowners policy's definition of collapse. Stewart v. Metro. Lloyds Ins. Co., 2020 U.S. Dist. LEXIS 111527 (S.D. Tex. June 24, 2020).
Beatrice Stewart, the homeowner, heard a loud bang one night as she lay in bed. The next day, she found that the floor near her bathroom and hallway had sunk and the house was sitting lower. She admitted the house never completely fell down. Upon investigation, Lloyds found that rot in the floor joists and subfloor decking were caused by a combination of termite damage and exposure to moisture. Lloyds denied the claim.
Stewart sued. Lloyds argued the policy required an "entire collapse" of the building or any part of a building, which did not occur here. The policy defined "collapse" as "an abrupt falling down or caving in of a building or any part of a building." The record did not show that any part of Stewart's floor caved in.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com