Construction Litigation Roundup: “A Fastball Right to the Bean!”
May 06, 2024 —
Daniel Lund III - LexologyThe Metropolitan Municipality of Lima, Peru, filed suit in federal court in Washington DC to vacate two separate arbitration awards rendered against the city in international arbitration proceedings subject to the Federal Arbitration Act.
The city had contracted to build, improve, and maintain various highways in and around the city. To pay for this infrastructure, Lima agreed that the contractor would “receive revenues from existing and new toll booths.”
Apparently, the City of Lima forgot how much citizens of the area loathed tolls, and, according to the court, the local public officials “quickly truckled” (how apropos for a road project!) to the pressure. As a result, revenues promised to the contractor were not forthcoming, and the city did nothing about it.
The contractor initiated arbitration, and the city countered by arguing that the contractor had bribed its way into the contract. The city lost and was held in breach.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Occurrence-Based Insurance Policies and Claims-Made Insurance Policies – There’s a Crucial Difference
April 13, 2017 —
Garret Murai – California Construction Law BlogI’ve yet to find reading through an insurance policy on anyone’s “bucket list.”
But read them you should. Or have your attorney read through them (wink, wink).
Because when you need to tender a claim there’s probably no more important document in the world.
In Tidwell Enterprises, Inc. v. Financial Pacific Insurance Company, Inc., Case No. C078665 (November 29, 2016), a client whose attorney did read the policy, bested the insurer of a policy it issued.
Tidwell Enterprises, Inc.
In 2006 or 2007, Tidwell Enterprises, Inc. installed a fireplace at a single-family home located in Copperopolis, California. At the time, Tidwell had a general commercial liability policy issued by Financial Pacific Insurance Company, Inc. which expired in March 2010.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Massachusetts Supreme Judicial Court Strikes a Deathblow to Substantial Factor Causation in Most Cases; Is Asbestos Litigation Next?
March 22, 2021 —
Christian J. Singewald, Rochelle Gumapac & Timothy J. Keough - White and Williams LLPIn Doull v. Foster, the Massachusetts Supreme Judicial Court (SJC) addressed the proper causation standard in a medical malpractice case. In reaching this issue, the SJC reached far beyond the medical malpractice case before it. The SJC concluded that the substantial factor test for causation, which had been regularly employed in the Commonwealth for decades, was “unnecessarily confusing.” In doing so, the SJC effectively ended the use of the substantial factor test in all negligence cases going forward, except in toxic tort litigation. However, the SJC openly questioned its usefulness in toxic tort litigation and all but welcomed a direct challenge to its use there.
Reprinted courtesy of
Christian J. Singewald, White and Williams LLP,
Rochelle Gumapac, White and Williams LLP and
Timothy J. Keough, White and Williams LLP
Mr. Singewald may be contacted at singewaldc@whiteandwilliams.com
Ms. Gumapac may be contacted at gumapacr@whiteandwilliams.com
Mr. Keough may be contacted at keought@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
California Court Confirms Broad Coverage Under “Ongoing Operations” Endorsements
December 01, 2017 —
Kevin C. Brantley - Payne & FearsA California Court of Appeal has confirmed that additional insured endorsements (“AIE”) granting coverage for liability arising out of a named insured’s “ongoing operations,” and in effect during those “ongoing operations,” do not require that the liability arise while the named insured is performing work. McMillin Mgmt. Servs., L.P. v. Financial Pacific Ins. Co., Cal. Ct. App., November 14, 2017, Case No. D069814.
In McMillin, a construction defect insurance coverage action, Lexington Insurance Company argued that McMillin had no liability to homeowners until after their homes closed escrow; thus, McMillin did not face liability while the named insureds’ work was ongoing. The Court of Appeal rejected Lexington’s argument, finding that the “ongoing operations” AIEs provide only that McMillin’s liability “be ‘linked’ through a ‘minimal causal connection or incidental relationship’ with [the named insureds’] ongoing operations.” (internal citations omitted). The Court reasoned that Lexington had not established that all of the damage in the underlying action occurred after the named insureds completed their work, thus Lexington had not established as a matter of law that there was no potential for coverage for McMillin under the policies.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin C. Brantley, Payne & FearsMr. Brantley may be contacted at
kcb@paynefears.com
No Coverage for Foundation Collapse
November 08, 2017 —
Tred R. Eyerly - Insurance Law HawaiiCoverage for the collapse of a foundation was not covered under the contractor's builder's risk policy. Taja Investments LLC v. Peerless Ins. Co., 2017 U.S. App. LEXIS 19855 (4th Cir. Oct. 11, 2017).
Taja Construction LLC was renovating a row house owned by Taja Investments LLC when the east wall of the property collapsed. Taja submitted a claim for repair costs in the amount of $400,000. Peerless denied coverage because the collapse was caused by Taja's failure to support the building's foundation properly while excavating the basement. The policy excluded coverage for defects in construction or workmanship. The claim was also denied under the earth movement exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Drafting the Bond Form, Particularly Performance Bond Form
July 14, 2016 —
David Adelstein – Florida Construction Legal UpdatesOftentimes, when it comes to payment and performance bonds (in particular), the bond forms are drafted by the obligee. For example, an owner (as the obligee) may draft the bond forms that it wants its general contractor’s surety to execute. And, a general contractor (as the obligee) may draft the bond forms that it wants its subcontractors’ sureties to execute. As an obligee, it is always beneficial to draft the bond form (particularly the performance bond) that you want the surety to execute. The bond is to benefit you—the obligee—so having a hand in creating conditions to trigger the application of the bond is important, specifically when it comes to triggering a performance bond upon the bond-principal’s default.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of