New American Home Construction Nears Completion Despite Obstacles
January 29, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction of the New American Home in Las Vegas, Nevada, to be completed for the 2014 International Builders’ Show, has faced enormous challenges, according to Jennifer Goodman writing for Big Builder. Josh Anderson, owner of Element Building Co., told Goodman “he couldn’t have imagined what lay ahead when he signed on in fall 2012 to the project, which is co-sponsored by BUILDER and the NAHB.”
Challenges began during the “design phase” when Anderson “was troubled by the sitting of the house on its lot in the tony Sky Terrace subdivision.” Furthermore, he “balked at the floor plan, which encompassed a traditional design aesthetic and opulent touches.” The project’s architect, Barry Berkus, passed away in late 2012, and his son, Jeffrey Berkus, took over for him.
After the plans were “complete and approved by the city,” a labor shortage in Las Vegas made it “particularly difficult to find skilled framers.” The shortage also increased labor costs. Anderson also contended with weather anomalies: “Over the summer, the area set a record for the most consecutive wet days in 30 years. Winds blew sawdust and rain into the open structure, ruining 350 sheets of drywall and slowing down construction,” according to Big Builder.
The “mammoth project” is close to completion. Anderson told Big Builder, “I’ve always been a sucker for a challenge.”
Read the court decisionRead the full story...Reprinted courtesy of
TOP TAKE-AWAY SERIES: The 2023 Annual Meeting in Vancouver
May 22, 2023 —
Marissa L. Downs - The Dispute ResolverProgram coordinators Katie Kohm and Peter Marino put together an amazing annual meeting last week in Vancouver. While its impossible to retread all of the ground we covered in discussing the "future of construction law," here are my top 10 take-aways:
10. Public-private partnerships may finally be taking off in the United States. P3s were slow to be pursued within the United States. According to panelists Peter Hahn, John Heuer, Sean Morley, and Lee Weintraub, this was chiefly because of the reticence of public bodies to deviate from the standard vendor model. Looking at the recent trends, it seems as though the United States--the "sleeping giant of public-private partnerships"--may finally be waking up. In 2022, a total of 29 public-private partnership projects were signed or reached financial close within the United States, representing an increase of 16% from the prior year. Thirty-eight states also now have some form of P3 enabling legislation. While we still lag behind our Canadian cousins, the future of P3s in this country is looking a little brighter.
9. The value proposition for the architecture profession is broken. Architects Lakisha Ann Woods (the CEO of AIA) and Phillip Bernstein (Associate Dean & Professor Adjunct Yale University) shared their thoughts with moderator Kelly Bundy on the challenges facing the architecture profession. The biggest issue they noted was the need to recruit qualified (and diverse) candidates into the profession. Unfortunately, this is difficult to do given the long career track (on average, it becomes 13.1 years to become a licensed architect) and the low salaries paid compared to other professions. Phillip shared that the high average starting salary for architecture grads from Yale (one of the leading programs in the country) is just $76,000. If we want to recruit the best and most innovative candidates into the field, the value proposition needs to change.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Blockbuster Breakwater: Alternative Construction Method Put to the Test in Tampa Bay
August 14, 2023 —
Scott Judy - Engineering News-RecordOn June 7, 2023, Tampa Bay news reporters trekked to the Sunshine Skyway bridge for a Florida Dept. of Transportation press conference that would explain the mystery behind the hundreds of curiously shaped concrete structures lining nearly the entire length of the span’s mile-plus-long south fishing pier access road.
Reprinted courtesy of
Scott Judy, Engineering News-Record
Mr. Judy may be contacted at judys@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
THE CALIFORNIA SUPREME COURT HAS RULED THAT THE RIGHT TO REPAIR ACT (SB800) IS THE EXCLUSIVE REMEDY FOR CONSTRUCTION DEFECT CLAIMS NOT INVOLVING PERSONAL INJURIES WHETHER OR NOT THE UNDERLYING DEFECTS GAVE RISE TO ANY PROPERTY DAMAGE in McMillin Albany LL
January 24, 2018 —
Chapman, Glucksman, Dean, Roeb, & BargerRICHARD H. GLUCKSMAN, ESQ.
GLENN T. BARGER, ESQ.
JON A. TURIGLIATTO, ESQ.
DAVID A. NAPPER, ESQ.
The Construction Industry finally has its answer. The California Supreme Court ruled that the Right to Repair Act (SB800) is the exclusive remedy for construction defect claims alleged to have resulted from economic loss, property damage, or both. Our office has closely tracked the matter since its infancy. The California Supreme Court’s holding resolves the split of authority presented by the Fifth Appellate District’s holding in
McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132, which outright rejected the Fourth Appellate District’s holding in
Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98.
By way of background, the Fourth District Court of Appeal held in
Liberty Mutual that compliance with SB800’s pre-litigation procedures prior to initiating litigation is only required for defect claims involving violations of SB800’s building standards that have not yet resulted in actual property damage. Where damage has occurred, a homeowner may initiate litigation under common law causes of action without first complying with the pre-litigation procedures set forth in SB800. Two years later, the Fifth District Court of Appeal, in
McMillin Albany, held that the California Legislature intended that all claims arising out of defects in new residential construction sold on or after January 1, 2003 are subject to the standards and requirements of the Right to Repair Act, including specifically the requirement that notice be provided to the builder prior to filing a lawsuit. Thus, the Court of Appeal ruled that SB800 is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003.
After extensive examination of the text and legislative history of the Right to Repair Act, the Supreme Court affirmed the Fifth District Court of Appeal’s ruling that SB800 preempts common law claims for property damage. The Complaint at issue alleged construction defects causing both property damage and economic loss. After filing the operative Complaint, the homeowners dismissed the SB800 cause of action and took the position that the Right to Repair Act was adopted to provide a remedy for construction defects causing only economic loss and therefore SB800 did not alter preexisting common law remedies in cases where actual property damage or personal injuries resulted. The builder maintained that SB800 and its pre-litigation procedures still applied in this case where actually property damages were alleged to have occurred.
The Supreme Court found that the text and legislative history reflect a clear and unequivocal intent to supplant common law negligence and strict product liability actions with a statutory claim under the Right to Repair Act. Specifically the text reveals “…an intent to create not merely
a remedy for construction defects but
the remedy.” Additionally certain clauses set forth in SB800 “…evinces a clear intent to displace, in whole or in part, existing remedies for construction defects.” Not surprisingly, the Court confirmed that personal injury damages are expressly not recoverable under SB800, which actually assisted the Court in analyzing the intent of the statutory scheme. The Right to Repair Act provides that construction defect claims not involving personal injury will be treated the same procedurally going forward whether or not the underlying defects gave rise to any property damage.
The Supreme Court further found that the legislative history of SB800 confirms that displacement of parts of the existing remedial scheme was “…no accident, but rather a considered choice to reform construction defect litigation.” Further emphasizing how the legislative history confirms what the statutory text reflects, the Supreme Court offered the following summary: “the Act was designed as a broad reform package that would substantially change existing law by displacing some common law claims and substituting in their stead a statutory cause of action with a mandatory pre-litigation process.” As a result, the Supreme Court ordered that the builder is entitled to a stay and the homeowners are required to comply with the pre-litigation procedures set forth in the Right to Repair Act before their lawsuit may proceed.
The seminal ruling by the California Supreme Court shows great deference to California Legislature and the “major stakeholders on all sides of construction defect litigation” who participated in developing SB800. A significant win for builders across the Golden State, homeowners unequivocally must proceed via SB800 for all construction defect claims arising out of new residential construction sold on or after January 1, 2003. We invite you to contact us should you have any questions.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard Glucksman,
Glenn Barger,
Jon Turigliatto and
David Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Turgliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Bridge to Be Largest Infrastructure Project in North America
October 22, 2013 —
CDJ STAFFNew York’s Tappan Zee Bridge is going to be replaced by the New NY Bridge, but it might be a while in coming. Work has begun, but the project is expected to last most of the next five years. Howard P. Milstein, chairman of the Thruway Authority notes that “the New NY Bridge is the largest transportation infrastructure project in North America and one of the largest construction contracts in New York State history.”
The current bridge was designed for 100,000 vehicles daily, or about 38,000 fewer than cross the bridge each day. Maintenance costs have been hundreds of millions of dollars in the last few years. The cost of the new bridge is expected to be less than $4 billion. The initial estimate was that it would cost more than $5 billion to build the new bridge.
Read the court decisionRead the full story...Reprinted courtesy of
Students for Fair Admissions: Shaking the Foundations of EEOC Programs and M/WBE Requirements
October 16, 2023 —
Denise Farris Scrivener - The Dispute ResolverOn June 29, 2023, the Supreme Court issued a landmark decision,
Students for Fair Admissions, Inc. v. President & Fellows of Harvard College, holding that race-based affirmative action programs in college admissions violate the Equal Protection Clause of the Fourteenth Amendment. 143 S. Ct. 2141, 216 L. Ed. 2d 857 (2023). On July 13, 2023, thirteen state Attorney Generals, relying on Students for Fair Admissions, issued a joint letter to the CEOs of the Fortune 100 companies, urging the elimination of all race-based programs in EEOC and government and private contracting. On July 19, 2023, a Tennessee district court judge issued an injunctive order against the Small Business Administration’s 8(a) application program on the basis of the program’s race-based presumption of disadvantage. Ultima Servs. Corp. v. U.S. Dep't of Agric., No. 220CV00041DCLCCRW, 2023 WL 4633481 (E.D. Tenn. July 19, 2023).
The message to be taken from these developments: all race-based programs and, by extension, potentially all gender-based programs—including ones that require or reward participation of Minority Business Enterprises (“MBE”) or Women Business Enterprise (“WBE”) in construction programs—currently stand on shaky ground.
This post will explain the constitutional foundations at play, the decisions shaking things up, and why well-rounded dialogue is urgently needed to address the status of these programs before they’re dead in the water.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Farris Scrivener, Farris Legal Services LLCMs. Scrivener may be contacted at
denise@farrislegal.net
Mandatory Arbitration Provision Upheld in Construction Defect Case
May 18, 2011 —
CDJ STAFFThe Superior Court of New Jersey reversed the decision in Frumer v. National Home Insurance Company (NHIC) and the Home Buyers Warranty Corporation (HBW), stating that the mandatory arbitration provision within the Frumer’s home warranty policy was binding.
The Frumers alleged that the construction defects were discovered immediately after moving into their million dollar home. After failing to achieve any results from dealing with the builder, they turned to their home warranty. There was some dispute over claims, and a settlement offer was rejected by the Frumers. The Frumers elected to commence litigation rather than utilize the binding arbitration.
The NHIC and the HBW filed a motion to compel arbitration, however, the motion judge denied the motion: “…the Warranty leaves open the option for [plaintiffs] to commence litigation, which [plaintiffs have] done in this case. The clause also states that ‘the filing of a claim against this limited Warranty shall constitute the election of remedy and shall bar the Homeowner from all other remedies.’ However, the provision does not state that the filing of a claim elects arbitration as the exclusive remedy, and any ambiguity in the language must be inferred against the drafter.”
The NHIC and the HBW appealed the decision. The Superior Court reversed the decision: “Where, such as here, the homeowner files a claim against the warranty for workmanship/systems defects, the warranty clearly and unequivocally establishes binding arbitration as the exclusive remedy. There is, however, no election of remedies for a dispute involving a major structural defect claim. The warranty clearly and unequivocally establishes binding arbitration as the exclusive remedy.”
Charles Curley of Halberstadt Curley in Conshohocken, Pa., the local counsel for National Home and Home Buyers, told the New Jersey Law Journal that “the ruling reaffirms New Jersey’s commitment to enforcing arbitration agreements and requiring people to go to mandatory arbitration when the contracts call for it.”
“At this point, their hope is that the warranty company will do what it's supposed to do — repair covered defects,” Eric McCullough, the Frumer’s lawyer said to the New Jersey Law Journal.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Legal Fallout Begins Over Delayed Edmonton Bridges
June 22, 2016 —
Scott Van Voorhis - Engineering News-RecordThe project teams for Edmonton’s two problem bridge-replacement projects have put most of their woes behind them—if trips to civil court and possible late-completion penalties are excluded.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, Engineering News-RecordENR may be contacted with questions or comments at