Engineers Found ‘Hundreds’ of Cracks in California Bridge
January 24, 2014 —
James Nash – Bloomberg NewsEngineers spotted “hundreds” of cracks in welds on parts produced for the San Francisco-Oakland Bay Bridge in 2008 and were encouraged to stay quiet rather than delay the $6.4 billion project, according to a California Senate committee report.
James Merrill, then a senior engineer with a quality assurance company known as Mactec, told Senate investigators that his complaints about work done at Shanghai Zhenhua Heavy Industry Co. Ltd. (900947), known as ZPMC, were rebuffed by managers of the California Department of Transportation as “too rigorous,” according to the report released yesterday.
Read the court decisionRead the full story...Reprinted courtesy of
James Nash, Bloomberg NewsMr. Nash may be contacted at
jnash24@bloomberg.net
Construction Defects Lead to Demolition of Seattle’s 25-story McGuire Apartments Building
March 16, 2011 —
CDJ STAFFAccording to a story published last Thursday in Seattle PI: " The 25-story McGuire Apartments, at Second Avenue and Wall Street, would cost more to fix than the building is worth, according to its owners. Its most serious defect involves steel cables that are corroding inside of concrete slabs because the ends weren’t properly treated with a rust-proof coating and a pocket in the edge of the concrete that wasn’t properly sealed"
The report by Aubrey Cohen outlines the demolition plans which are expected to take between 12 and 18 months, and will utilize robotic Brokk Machines. The demolition plan calls for one story at a time to be demolished, with the debris to be trucked offsite. Demolition plans aim to minimize disruption to residents and businesses in the area by Limiting work 7 a.m. to 6 p.m. on weekdays and 9 a.m. to 6 p.m. Saturdays with "impact and percussive activities" limited to 8 a.m to 5 p.m weekdays.
Read More...
Read the court decisionRead the full story...Reprinted courtesy of
Green Energy Can Complicate Real Estate Foreclosures
November 30, 2016 —
Bob L. Olson – Snell & Wilmer Real Estate Litigation BlogA quick drive through almost any newer residential community in the Southwest will show that a lot of residents are embracing “Green Energy” or renewable energy by placing solar panels on their properties. While most people would agree that increasing the use of alternative energy is socially responsible, there are a number of real estate investors that may view it as an opportunity to make additional profits by purchasing distressed properties with solar panels and then reselling those properties for more than they would be worth without solar panels. The theory is relatively straight forward as many believe that foreclosure of a deed of trust that was recorded before the solar panels were installed would extinguish any liens in favor of the vendor that sold or financed the sale of the solar panels. After all, it is generally held that “a valid foreclosure of a mortgage terminates all interest in the foreclosed real estate that are junior to the mortgage being foreclosed.” See SFR Investments Pool 1, LLC v. U.S. Bank, N.A., 130 Nev. Adv. Op. 75, 334 P.3d 408, 412 (2014) (quoting Restatement (Third) of Property, Mortgages §7.1 (1997)).
NOT SO FAST! While the general rule is that foreclosure of a senior lien terminates junior liens, most purveyors of solar panels do not encumber the property with mortgages or deeds of trust to secure payment of amounts they are owed. Rather, they typically either lease the solar panels to the property owner or secure repayment of the purchase price of the solar panels with a fixture filing under the Uniform Commercial Code (the “UCC”).
Read the court decisionRead the full story...Reprinted courtesy of
Bob L. Olson, Snell & WilmerMr. Olson may be contacted at
bolson@swlaw.com
Bad Faith Claim For Independent Contractor's Reduced Loss Assessment Survives Motion to Dismiss
January 28, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's bad faith claim based upon the insurer's alleged use of an independent contractor to assess the amount of loss in order to lower the amount paid survived a motion to dismiss. Williamson v. Chubb Indem. Ins. Co., 2013 U.S. Dist. LEXIS 178022 (E.D. Pa. Dec. 19, 2013).
The insureds' home was damaged. Chubb, their insurer, retained an independent contractor, Eastern Diversified Services (EDS) to assess the amount of loss. EDS estimated the loss to be $193,270.43, and Chubb paid this amount.
Chubb's standard practice was to conduct damage estimates itself using an estimating program called Symbility. EDS used a different program with a data base creating lower payments for loss. When this was brought to Chubb's attention, Chubb refused to recalculate the plaintiff's estimate.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Substitute Materials — What Are Your Duties? What Are Your Risks? (Law Note)
June 27, 2022 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn managing a project as the design professional, you are called upon to wear many hats. One of those hats is that of material specifier and, at times, substitute material approver. What are your duties in looking at substitute materials?
As always, the legal answer is “it depends”. In part, it will depend on your role on the project and what, specifically, the contract says. However, at its most basic, you can be sued for accepting an out of spec substitute material. This is so even if you believed the spec met requirements based on information that the contractor gave you. So, tread carefully in this area.
Do not assume any information that the contractor presents to you– take the time to research for yourself, call the manufacturer, and otherwise ensure that the product will work.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
In One of the First Civil Jury Trials to Proceed Live in Los Angeles Superior Court During Covid, Aneta Freeman Successfully Prevailed on Behalf of our Client and Obtained a Directed Verdict and Non-Suit
July 05, 2021 —
Aneta B. Freeman – Chapman Glucksman Dean & Roeb News AlertIn one of the first civil jury trials to proceed live in Los Angeles Superior Court during Covid, Aneta Freeman obtained a rare directed verdict and nonsuit in a complex, high exposure action, after seven days of trial. The dismissal was obtained after the parties rested after the liability phase of the bifurcated trial.
Ms. Freeman represented a general contractor in an action in which Plaintiff alleged that the general contractor and the County of Los Angeles (which was dismissed earlier on statutory immunity grounds) created a dangerous condition when they allegedly allowed mosquitos to breed in 2015 during construction at a flood retention basin in Marina Del Rey.
Plaintiff contracted West Nile Virus, and subsequently developed myasthenia gravis and a myriad of other conditions and ailments. Plaintiff relied heavily on a 2015 report from the Los Angeles West Vector Control District which suggested that the construction was the source of mosquitos which resulted in a “cluster” of West Nile Virus cases in the Marina Del Rey and surrounding areas.
In pretrial motions, Ms. Freeman successfully excluded that report, opinion testimony from the vector control former executive director, narrowed the scope of plaintiff’s entomologist testimony, and excluded Brad Avrit from testifying for the Plaintiff on construction standard of care.
The matter proceeded with a stipulated a 10 person jury, and all participants socially distanced and masked throughout the trial. Witnesses appeared live, with the exception of Plaintiff’s entomologist, portions of whose video deposition were played.
Following seven days of trial after both parties rested, Judge Mark Young granted the general contractor’s nonsuit and also, in the alternative, a directed a verdict for our client.
Plaintiff had demanded $10,000,000 of the County and the general contractor globally prior to trial, and $5,000,000 from the general contractor. The general contractor issued two CCP 998s, which were ignored by Plaintiff.
Read the court decisionRead the full story...Reprinted courtesy of
Aneta B. Freeman, Chapman Glucksman Dean & RoebMs. Freeman may be contacted at
afreeman@cgdrlaw.com
"Multiple Claims" Provisions on Contractor's Professional Liability Policy Creates a Trap for Policyholders
May 24, 2021 —
Michael V. Pepe - Saxe Doernberger & VitaIn Berkley Assurance Company v. Hunt Construction Group, Inc., 465 F.Supp.3d 370 (S.D.N.Y., 2020), professional liability insurer Berkley sued its insured, Hunt, a construction management firm, seeking a declaration that it did not owe Hunt a duty to defend and indemnify against breach of contract claims. The United States District Court for the Southern District of New York granted Berkley’s motion for summary judgment and denied Hunt’s motion for partial summary judgment. Among other things, the court held that the policy’s automatic extended reporting period did not apply to Hunt’s first claim. The multiple claims provision barred Hunt’s second claim because the claims were related.
The court’s holding creates a potential trap for policyholders who wait to see how a claim develops before reporting it to their insurance carrier. This case demonstrates that waiting to see how a claim develops can result in a loss of coverage. Policyholders need to be aware of this trap and report all claims and circumstances immediately.
Read the court decisionRead the full story...Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & VitaMr. Pepe may be contacted at
MPepe@sdvlaw.com