How Are You Dealing with Material Delays / Supply Chain Impacts?
June 07, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a prior article I discussed a material escalation provision in your construction contract to account for the volatility of the material price market. While including such a provision may not have been much of a forethought before, it is now!
What about concerns with the actual supply chain that impacts the availability of and the lead time of materials? How are you addressing this concern in your construction contract?
The pandemic has raised awareness to this issue as certain material availability has been impacted by the pandemic. As a result, parties in construction have tried to forecast those materials where delivery issues may occur including those materials with longer than expected lead times. But equally important is how this issue is being addressed in your construction contract including how you want to negotiate this risk in future construction contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Requirement to Post Collateral Under General Agreement of Indemnity Is Real
May 16, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn prior postings, I have discussed the all-powerful General Agreement of Indemnity (click
here and
here). This is the document a bond-principal executes to obtain bonds (e.g., performance and payment bonds). Not only does the bond-principal execute this General Agreement of Indemnity, but typically, so do other indemnitors such as the company’s principals and their spouses, other related companies, etc. The objective is that the surety has financial comfort that if a claim is made against the bond, there are avenues where it will get reimbursed and indemnified for any cost it incurs, or payment it makes, relative to that claim against the bond. When a surety issues bonds, the objective is that all losses it incurs gets reimbursed because the bonds are NOT insurance policies.
One of the powerful tools the surety can exercise in the General Agreement of Indemnity is to demand the bond-principal and other indemnitors to post collateral in an amount the surety deems sufficient to cover any losses it may incur. This is a right in any General Agreement of Indemnity I have seen and is a right the surety can rightfully exercise.
A recent example is shown from the opinion in Philadelphia Indemnity Ins. Co. v. Quinco Electrical, Inc., 2022 WL 1230110 (M.D.Fla. 2022), which pertains to the surety’s motion for preliminary injunction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Round-Up (11/30/22) – Proptech Trends, Green Construction, and Sustainable Buildings
December 13, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores 4 key trends expected to impact proptech in 2023, global investment in green construction technologies, sustainable buildings and their perceived value for tenants in Europe, and more.
- Sitting at the crossroads between real estate and technology, proptech has experienced significant growth, which is expected to accelerate via 4 key trends in 2023. (Zain Jaffer, Forbes)
- Global investment in green construction technologies reached $2.2 billion in 2022, with legislation and technological innovation serving as the key driving forces behind this growth. (Jennifer Kite-Powell, Forbes)
- In Europe, sustainable buildings have increased the asset values for commercial real estate managers, with tenants willing to pay more for efficient buildings. (David Worford, Environment + Energy Leader)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Building a Case: Document Management for Construction Litigation
October 07, 2019 —
Robert A. Gallagher, Jane Fox Lehman, & Michael I. Frankel, Pepper Hamilton LLP - ConsensusDocsSuccess in construction litigation often turns less on counsel’s ability to craft legal arguments and more on counsel’s ability to gather, master and present the often complex set of facts underlying the case. In construction matters, most of the key facts are found in documents: contract documents, drawings, plans and specifications, schedules, submittals, progress reports, daily logs, change orders, invoices and payment records. Nowadays, these documents will almost certainly be created, exchanged and stored electronically; many will never exist in hard copy. As such, timely collection, organization and analysis of electronically stored information (ESI) is crucially important in construction litigation.
The construction industry has always involved a large quantity of records. Today, the majority of those records exist only as ESI: Design professionals use computer-aided design (CAD) software to create construction plans. Construction managers use Primavera or similar software to create schedules and workflows. Estimators use job cost control programs. Innovative firms capture digital photos of the project, from mobilization through the punch process.
Because ESI is created and exchanged at a higher rate than hard-copy documents, ESI has facilitated a dramatic increase in the volume of records associated with construction projects. Further compounding the increase is the proliferation of mobile devices. With a smartphone in every pocket, ESI creation has moved out of the home office and the site trailer and onto the site itself. As the volume of ESI expands, so too does the time and expense associated with storing, processing, reviewing and producing these records. This article will cover strategies for balancing time and expense with the requirements of the rules and the needs of the case.
Reprinted courtesy of Pepper Hamilton LLP attorneys
Robert A. Gallagher,
Jane Fox Lehman and
Michael I. Frankel
Mr. Gallagher may be contacted at gallagherr@pepperlaw.com
Ms. Lehman may be contacted at lehmanj@pepperlaw.com
Mr. Frankel may be contacted at frankelm@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wall Street Is Buying Starter Homes to Quietly Become America’s Landlord
February 27, 2023 —
Patrick Clark - BloombergJavier Vidana started out as a real estate agent in 2013, when Arizona’s Salt River Valley seemed wide open. It was the aftermath of a housing market crash that had seen the typical home value in the Phoenix metro area fall more than 50%, and a single parent with good credit could tap loan programs geared toward first-time homeowners and find a pretty decent place to live. For Vidana, the challenge was convincing potential clients that a house was something they wanted to own. “We were on the phone begging people to buy,” he says. “There was no buyer confidence whatsoever.”
The economy crawled forward, and the housing market with it. Vidana made a specialty of tutoring young buyers on real estate basics. Soon he was supplementing his commission income by selling how-to PDFs on his website and collecting ad revenue on his YouTube channel. Then the pandemic sparked a boom that gave him something new to explain.
Americans responded to the work-from-home era by house shopping, and no big city was hotter than Phoenix. The median home was worth about $285,000 at the beginning of the pandemic; it was valued at $435,000 two years later. It wasn’t unheard of for a seller to receive 50 offers or more, or for a prospective buyer to make offers on a dozen different homes before finally closing a deal.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Updated Covid-19 Standards In The Workplace
August 23, 2021 —
Mustafa Karim - Wilke FleuryWith California reopening, many Californians will be heading back to the workplace soon and are wondering if employers may require their employees to get vaccinated. According to the Fair Employment and Housing Act (“FEHA”), an employer may require employees to receive an FDA-approved vaccination against COVID-19 infection so long as the employer (a) does not discriminate against nor harass employees on the basis of a protected characteristic, (b) provides reasonable accommodations related to disability or sincerely-held religious beliefs, and (c) does not retaliate against anyone for engaging in protected activity.[1]
On June 15, 2021, California lifted its mask mandate across the state. The California Department of Public Health (“CDPH”) updated its guidance for the use of face coverings stating that masks are no longer required for fully vaccinated individuals.[2] However, masks are still required on public transit, indoors in k-12 schools, childcare, other youth settings, healthcare settings, long-term care facilities, correctional and detention facilities, and homeless shelters.[3]
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury LLP
Construction Goes Green in Orange County
December 04, 2013 —
CDJ STAFFConstruction has completed on ParkLanding, which is the first residential project in Orange County with a green roof. Developed in partnership with the City of Buena Park Redevelopment Agency, the project replaces an abandoned 2-acre site with affordable apartments. The design was done by Newport Beach-based Newman Garrison + Partners.
During the design process, attention was paid to sustainable element, including better performing insulation, and more efficient HVAC, electrical, and plumbing systems. The development was designed with the intention of achieving a LEED Gold rating.
Read the court decisionRead the full story...Reprinted courtesy of
The “Builder’s Remedy” Looms Over Bay Area Cities
February 20, 2023 —
Allan C. Van Vliet, Cara M. MacDonald, Robert G. Howard & Robert C. Herr - Gravel2Gavel Construction & Real Estate Law BlogCities in the San Francisco Bay Area are frantically working to finalize their state-mandated “housing elements” in their General Plans by the January 31, 2023, deadline imposed by the California Department of Housing and Community Development (HCD). For Bay Area cities like San Francisco, Oakland, San Jose and Berkeley, the plans must be approved by HCD
on or before January 31, 2023. California municipalities have extra incentive to get their housing elements approved this year, because the failure to meet the deadline may subject them to a remedy known as
the “builder’s remedy.”
The failure of cities in California to adopt and implement adequate housing elements as part of their General Plans has contributed to the state’s serious housing affordability crisis. The “builder’s remedy” incentivizes cities to meet housing element deadlines, because failure to do so could cause cities to lose control over certain land use entitlement decisions for projects that include housing under the state’s Housing Accountability Act (HAA).
Reprinted courtesy of
Allan C. Van Vliet, Pillsbury,
Cara M. MacDonald, Pillsbury,
Robert G. Howard, Pillsbury and
Robert C. Herr, Pillsbury
Mr. Van Vliet may be contacted at allan.vanvliet@pillsburylaw.com
Ms. MacDonald may be contacted at cara.macdonald@pillsburylaw.com
Mr. Howard may be contacted at robert.howard@pillsburylaw.com
Mr. Herr may be contacted at robert.herr@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of