Not Pandemic-Proof: The Ongoing Impact of COVID-19 on the Commercial Construction Industry
December 06, 2021 —
George B. Green Jr. - Construction ExecutiveThe impact of COVID-19 has been felt in nearly every industry and arena across the country, with the exception of construction—or so that is the general perception. Perceptions are often wrong though, and this one is no different. The truth is that the construction industry has been hit just as hard, if not harder, than every other industry.
As the COVID-19 pandemic struck in the spring of 2020, construction projects plowed forward full steam ahead. Roadwork seemed to increase and developers continued to systematically acquire property and initiate large-scale projects. Perhaps it was these observations that led many to the conclusion that construction was pandemic-proof as the rest of society attempted to cobble together something that vaguely resembled a normal business year. But the construction industry has endured many challenges over the last 18 months, and unfortunately, the challenges do not appear to be evaporating anytime soon.
The industry has been primarily affected in the areas of scheduling, manpower and permitting, which has ultimately affected pricing. The entire way jobs are scheduled has been turned upside down. The supply chain issues that many have experienced for everyday household items have hit the construction industry as well.
Reprinted courtesy of
George B. Green Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Green may be contacted at
ggreen@wwhgd.com
eRent: Construction Efficiency Using Principles of the Sharing Economy
November 06, 2018 —
Aarni Heiskanen - AEC BusinesseRent has developed a digital equipment management portal for construction equipment. At the very heart of the concept lies the resource efficiency that can be achieved using principles of the sharing economy.
Olli Aaltonen, CEO of eRent Solutions, is confident about the platform his company has created: “Besides offering a digital solution to a rather inefficient workflow in the construction business, we are also introducing a way to track and manage your construction equipment, whether it is owned, rented, or leased. The cost savings are obvious we believe our tracking feature brings our customers even more value.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
How to Lose Your Contractor’s License in 90 Days (or Less): California and Louisiana
November 15, 2021 —
Rafael Boza - Gravel2Gavel Construction & Real Estate Law BlogHaving your Contractor’s License up and running to perform work when needed, where needed, is an indispensable compliance matter that contractors face every year. However, this indispensable process may also be cumbersome and time consuming. Knowing the regulations applicable to your business in each state and what to do, how to do it, and when to do it, is of critical importance to maintain compliance and your ability to work in different states.
In this post we will do a high-level review of reporting obligations in California and Louisiana.
California’s
Contractors’ State License Law, Bus. & Prof. Code §§ 7000 et seq., requires licensees to report various information to the Contractors State License Board (CSLB) “within 90 days” of the effective date or event. Louisiana State
Licensing Laws and Regulations, R.S. §§ 37:24 et seq. and La. Admin. Code tit. 46, XXIX, §§ 101 et seq. also require similar reporting to the Louisiana State Licensing Board for Contractors (LSLBC), sometimes “within 15 days” of the event.
Read the court decisionRead the full story...Reprinted courtesy of
Rafael Boza, PillsburyMr. Boza may be contacted at
rafael.boza@pillsburylaw.com
As Some States Use the Clean Water Act to Delay Energy Projects, EPA Issues New CWA 401 Guidance
August 26, 2019 —
Anthony B. Cavender - Gravel2GavelIn just the past few weeks, three states have used their Clean Water Act 401 authority to delay, for an indefinite period, FERC-authorized pipeline expansion projects. On May 6, 2019, the Oregon Department of Environmental Quality denied, without prejudice, Jordan Cove’s application for a Section 401 water quality certification. Jordan Cove plans to build an LNG export terminal at Coos Bay, Oregon, if it can obtain the necessary federal and permits. Under Section 401(a) of the Clean Water Act, any applicant for a federal permit to conduct any activity, including the operation of facilities which may result in any discharge into the navigable waters, shall provide the permitting agency a certification from the State in which the discharge may originate that any such discharge will comply with the applicable provisions of the Clean Water Act, including effluent limitations and state water quality standards. The States have a “reasonable time”—which shall not exceed one year after the receipt of the 401 application—in which to act, or the state’s authority may be waived by this inaction. The Oregon DEQ concluded that Jordan Cove has not demonstrated that its project, as presently configured, will satisfy state water quality standards. The 401 applications submitted by Transcontinental Gas Pipe Line Co. (Transco) to the New Jersey Department of Environmental Protection and the New York State Department of Environmental Protection were similarly rejected without prejudice on May 15, 2019 (New York) and June 5, 2019 (New Jersey). This use of the states’ 401 authority has frustrated plans to build and operate LNG pipelines around the country.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Three-Year Delay Not “Prompt Notice,” But Insurer Not “Appreciably Prejudiced” Either, New Jersey Court Holds
November 04, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Harleysville Preferred Insurance Company v. East Coast Painting & Maintenance, LLC, 2019 U.S. Dist. LEXIS 135295 (D.N.J. Aug. 12, 2019) (East Coast Painting), the U.S. District Court for the District of New Jersey held that an insurer, which received notice of a bodily injury accident three years after it happened, was not “appreciably prejudiced” by such late notice, even as the court acknowledged notice three years later did not satisfy the policy’s “prompt notice” condition. The court also held that the policy’s “Operational Exclusion,” which excluded coverage for bodily injury arising out of the operation of “cherry pickers and similar devices,” did not apply because the accident arose out of the use of a “scissor lift,” which is not a device similar to a cherry picker.
East Coast Painting arose out of a Queens, New York bridge-painting project, during which an employee of the insured, East Coast Painting and Maintenance LLC was injured while “standing on a scissor lift mounted to the back of a truck,” owned and operated by East Coast. The employee sued various project-related entities which, in turn, joined East Coast as a defendant. East Coast sought coverage under its business auto policy, and the insurer agreed to defend the insured under a reservation of rights. The insurer subsequently sought a declaration that it did not owe coverage based on, among other things, the policy’s “Operational Exclusion,” and the insured’s failure to satisfy the policy’s “prompt notice” condition. The insurer moved for summary judgment on both of those bases, but the court in East Coast Painting denied the motion.
As for the insurer’s “prompt notice” defense, the court in East Coast Painting concluded that, the insured’s notice to the insurer was not prompt because it did not receive notice until three years after the accident. But, the court added, the inquiry does not end there. “[T]his Court must determine whether [the insurer] was appreciably prejudiced by that delay.” Reviewing the facts, the court held that the insurer was not “appreciably prejudiced,” even though during the three-year delay the lift truck was “not properly maintained” or “in the same condition it was at the time of the Accident.” The court observed that the insurer had “ample other evidence with which it can defend itself,” such as experts who inspected the lift truck and opined about the cause of the accident.” [Emphasis added.] Further, “there are multiple contemporaneous accident reports,” “a list of the East Coast employees on site at the time,” “photographs of the lift truck and its location when [the employee] was injured,” and “depositions of [the employee] and others regarding the events at issue.” Thus, the court held, the insurer was not prejudiced and summary judgment was inappropriate.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Industry Practices Questioned After Girder Fractures at Salesforce Transit Center
April 10, 2019 —
Nadine M. Post - Engineering News-RecordAttendees of a recent presentation on the earthquake-resistant structure of San Francisco’s Salesforce Transit Center—intended to provide a safe haven when the Big One hits—lauded the engineering of the 4.5-block-long hollow tube that supports the 1.2-million-sq-ft “groundscraper.” But there also was much talk of the project’s black eye, as a consequence of brittle fractures of the bottom flanges of two bridge-like built-up plate girders that span 87 ft over Fremont Street.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Augmenting BIM Classifications – Interview with Eveliina Vesalainen of Granlund
July 19, 2017 —
Aarni Heiskanen - AEC BusinessBuildingSMART Finland is supplementing building information modeling (BIM) guidelines in a national standardization project, as a part of the KIRA-digi program. In her Master’s thesis, Eveliina Vesalainen, of Granlund, has compared European BIM classifications for mechanical, electrical, and plumbing (MEP) design. Her study is the groundwork for the upcoming Finnish norms.
“I’m a 26-year-old, soon to be Master of Science, and I come from Mäntsälä. I live in Helsinki and work at Granlund, a leading Finnish MEP consultancy,” Eveliina explains. She has a bachelor’s degree in environmental engineering, but became interested in MEP by chance.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com